Building Inspection in Singapore: The Complete Guide to Every Mandatory Check

Nov 12
12 min read

Building inspection in Singapore is not one regime but a stack of separate statutory checks, each with its own agency, inspector and interval. A typical commercial or strata building answers to BCA for its structure, facade, lifts and escalators, to SCDF for fire safety, to MOM for pressure vessels and lifting equipment, to EMA for electrical and gas installations, to PUB for water tanks and to NEA for pools and cooling towers. This guide sets out every regime we could verify against the agency's own published rules as at November 2026, with the source and date for each.

What are the mandatory building inspections in Singapore?

The list below gives each regime in the same order: who it applies to, how often, who inspects, and which agency.

  • Periodic Structural Inspection (PSI): all buildings except landed houses used solely as residences and temporary buildings; every 10 years where at least 90% of the floor area is residential and every 5 years for all other buildings; a Professional Engineer in civil or structural engineering appointed by the owner; BCA.

  • Periodic Facade Inspection (PFI): buildings more than 13 m high and more than 20 years old, except landed houses and temporary buildings; every 7 years; a Competent Person (PE or registered architect holding the Certificate in Facade Inspection); BCA.

  • Lifts, escalators and mechanised car parking systems: every installation; maintenance monthly for escalators and most lifts, plus an annual examination, inspection and test to renew the Permit to Operate; a BCA-registered service contractor supervised by a Specialist Professional Engineer; BCA.

  • Fire safety: designated buildings above SCDF's size and occupancy thresholds; fire protection systems inspected annually, with a Fire Certificate valid 36 months from 1 April 2026; a Professional Engineer and contractor engaged by the owner or occupier; SCDF.

  • Windows: every home; casement windows retrofitted with stainless steel rivets and all windows checked at least every 6 months; the homeowner, using a BCA-approved window contractor for any work; BCA.

  • Exterior features and air-conditioner supports: every building; a continuing duty, with supports checked at least every 6 months; the owner, using trained installers; BCA.

  • Pressure vessels: workplaces; steam boilers yearly, air and steam receivers every 2 years; an Authorised Examiner; MOM.

  • Lifting equipment: workplaces; periodic test and examination, with hoists at least every 12 months; an Authorised Examiner; MOM.

  • Electrical installations: licensed installations (non-domestic above 45 kVA); at least once a year, and at least every 6 months for communal services in multi-tenanted buildings and condominiums; the appointed Licensed Electrical Worker; EMA.

  • Gas installations: non-residential premises annually, and residential buildings with multiple consumers on a 5-yearly programme for the pipework up to the meters; a licensed gas service worker or PE; EMA, with notices from SP PowerGrid.

  • Water storage tanks: any water service installation with a tank, except landed residential property; at least once every 12 months; a Licensed Plumber; PUB.

  • Swimming pools and other aquatic facilities: licensed facilities; daily on-site tests, monthly laboratory tests and quarterly Legionella tests where applicable; the licensee and an accredited laboratory; NEA.

  • Cooling towers: every operational cooling tower, which must be registered; Legionella count quarterly and plate count monthly; the owner or occupier; NEA.

  • Retaining walls and slopes: every owner with a slope or wall; no fixed statutory interval outside the PSI; a PE in civil, structural or geotechnical engineering; BCA.

  • Voluntary inspections: pre-purchase surveys, defects inspections and condition surveys; whenever the owner or buyer chooses; any suitably qualified engineer or inspector; no agency.

Periodic Structural Inspection (BCA)

The PSI is a structural inspection required under section 28 of the Building Control Act 1989, every 5 years for non-residential buildings and every 10 years for buildings where at least 90% of the floor area is solely residential. Detached, semi-detached, terraced and linked houses used solely as residences, and temporary buildings, are excluded. BCA serves a notice, the owner (or the MCST in a strata development) appoints a PE in civil or structural engineering with no professional or financial interest in the building, and that engineer carries out a Stage 1 visual inspection and, if needed and approved by BCA, a Stage 2 full structural investigation. Since December 2024 jetties, docks and wharves, and since March 2025 bridges, underpasses and floating structures, also receive PSI notices at 5-yearly intervals (BCA circular APPBCA-2024-13, 2 September 2024). Read the detailed guide: Periodic Structural Inspection in Singapore: Stage 1, Stage 2 and what happens next, and our earlier overview of the BCA periodic structural inspection.

Periodic Facade Inspection (BCA)

The PFI applies to buildings more than 13 m high once they are more than 20 years old, every 7 years, and has been in force since 1 January 2022. A Competent Person inspects 100% of the facade visually and at least 10% of each elevation at close range, and BCA's FAQ states that an owner who fails to appoint a Competent Person within 2 months of the notice is liable to a fine of up to $20,000. BCA estimated in October 2021 that about 30,000 buildings would be inspected in the first 7-year cycle. See Periodic Facade Inspection: which buildings and what is checked, the comparison PSI vs PFI and drones and technology in facade inspection.

Lifts and escalators: the Permit to Operate (BCA)

Every lift, escalator and mechanised car parking system needs a valid Permit to Operate (PTO), renewed after an annual examination, inspection and test. Under the Building Control (Fixed Installations) Regulations 2025, in force from 1 October 2025, escalators must be maintained every month, and most lifts at the manufacturer's recommended frequency or at least monthly, whichever is more frequent, by a BCA-registered service contractor. For PTO renewal the owner appoints a Specialist Professional Engineer to supervise the annual examination, inspection and test. A Ministry of National Development speech in March 2020 put the national stock at about 70,000 lifts and 7,000 escalators. Details: lift and escalator inspections and the Permit to Operate.

Fire safety: the Fire Certificate (SCDF)

Owners or occupiers of designated buildings must hold a Fire Certificate under section 35 of the Fire Safety Act 1993, and from 1 April 2026 new certificates are valid for 36 months instead of 12. Designated buildings include public buildings with an occupant load above 200, industrial buildings and foreign employee dormitories with an occupant load of 1,000 or more, a floor or site area of 5,000 sqm or more or a habitable height above 24 m, and all hospitals. SCDF states that every such building has to be inspected annually, with a Professional Engineer and contractor engaged to inspect and test the fire safety systems. Larger buildings must also appoint a Fire Safety Manager, for example public buildings of 9 storeys or more, 1,000 occupants or more, or 5,000 sqm or more. See Fire Certificate inspections and fire safety jargon explained.

Windows (BCA)

Homeowners have been required since 2004 to replace aluminium rivets in casement windows with stainless steel rivets, and BCA advises checking all windows at least once every 6 months. Only a BCA-approved window contractor with trained window installers may retrofit or replace windows. A joint BCA and HDB release of 11 December 2021 recorded 43 fallen windows in the first 11 months of 2021, and 388 people fined and 92 prosecuted since 2006. The same release gives the penalties: up to $5,000 or 6 months' jail for failing to retrofit, and up to $10,000 or 1 year's jail if a window falls for lack of maintenance. Details: window safety and retrofitting.

Exterior features and the building maintenance duty

Owners have a standing legal duty to keep exterior features such as cladding, plaster, brackets and air-conditioner supports in good repair and securely fixed, whether or not an inspection notice has been served. BCA's PFI FAQ describes this duty under the Building Maintenance and Strata Management Act, with a fine of up to $10,000 or imprisonment of up to 12 months for failing to keep exterior features properly maintained or securely fixed; the Building Control (Amendment) Act 2020 consolidates these maintenance provisions into the Building Control Act. BCA advises checking air-conditioner supports for corrosion at least every 6 months. Since the Building Control (Reportable Matters) Regulations 2025, a fallen exterior feature must be reported to BCA's Safety Incident Hotline within 6 hours and in writing within 24 hours. BCA has said it receives more than 20 reports of fallen facade elements a year on average. See building maintenance duties of MCSTs.

Pressure vessels, lifting equipment and other statutory equipment (MOM)

Pressure vessels and lifting equipment in workplaces must be examined at set intervals by an Authorised Examiner, a Professional Engineer specifically approved by MOM. MOM's published intervals for pressure vessels are yearly for steam boilers and every 2 years for air receivers, steam receivers and autoclaves, with at least one hydrostatic test and thickness gauging every 10 years. Since 5 August 2023 MOM no longer sends reminders, so owners must track due dates themselves. For lifting equipment, MOM's 2025 update removed periodic overload tests after first registration and moved material hoists from 6-monthly to 12-monthly examination. Related reading: PE endorsement for lifting operations.

Electrical installations (EMA)

A licensed electrical installation must be inspected and certified fit for operation by the appointed Licensed Electrical Worker (LEW) at least once a year. An electrical installation licence is required for all non-domestic installations with an approved load above 45 kVA, installations in hazardous trades and non-domestic supply installations. EMA's handbook sets shorter intervals for higher-risk settings: at least once in 6 months for communal services in multi-tenanted buildings and condominiums, and at least monthly on construction worksites.

Gas installations (EMA)

Gas pipework in non-residential premises must be inspected annually by a licensed gas service worker or Professional Engineer, under EMA's Gas Supply Code. In residential buildings with multiple consumers the pipework from the gas service isolation valve to the unit meters is on a 5-yearly programme, and the gas transporter inspects from meter to appliance on a 15-yearly programme. From 1 September 2025 the Gas Act 2001 names a Prescribed Person for each part of the installation (the MCST in a strata development), who is notified of a due date and must appoint the inspector; the Certificate of Fitness goes to SP PowerGrid within 30 days. Failure by the Prescribed Person carries a fine of up to $10,000 or up to 12 months' imprisonment.

Water storage tanks (PUB)

Anyone responsible for a water service installation with a storage tank must engage a Licensed Plumber at least once every 12 months to inspect, where necessary clean and disinfect, and certify the tank. Water samples must pass chemical and bacteriological tests at an accredited laboratory. Landed residential properties are exempt from the mandatory annual certification. PUB states that late certification is an offence under the Public Utilities (Water Supply) Regulations, with a fine of up to $10,000, imprisonment of up to 12 months, or both, and it carries out random inspections of tanks.

Swimming pools and cooling towers (NEA)

Licensed swimming pools, spa pools and water playgrounds must test pH and disinfectant on site at least once daily and send samples to an accredited laboratory at least once a month. Pools with aerosol-generating features and all spa pools are also tested quarterly for Legionella (NEA licensing requirements, 17 August 2023). Cooling towers must be registered with NEA as aerosol-generating systems; owners submit quarterly Legionella bacteria counts and, since 1 October 2024, keep monthly heterotrophic plate count results for at least 12 months rather than submitting them. Operating an unregistered cooling tower is an offence, with a fine of up to $5,000 for a first offence.

Retaining walls and slopes (BCA)

Property owners are responsible for inspecting and maintaining their slopes and retaining walls and for rectifying defects on detection. There is no fixed statutory interval outside the PSI: BCA's guidance asks owners and MCSTs to inspect and maintain regularly and to engage a PE in civil, structural or geotechnical engineering when tell-tale signs appear. Retaining walls as standalone civil engineering structures are currently exempt from PSI, but slopes, retaining walls and slope protection within a building's premises are surveyed during that building's PSI. See retaining walls and slopes for landed houses and slope stability in Singapore.

Dangerous buildings and unauthorised works (BCA)

Outside the periodic cycle, BCA can act at any time on a building it considers dangerous, including by Dangerous Building Order and Closure Order. In published cases the owner has been required to close the affected area and appoint a Professional Engineer to investigate and design permanent rectification. Unauthorised building works are a recurring cause and carry a fine of up to $200,000, up to 2 years' imprisonment, or both. See dangerous buildings: BCA orders, closure and owner duties, lessons from recent enforcement on unauthorised mezzanines and regularisation of unauthorised structures.

Voluntary inspections: pre-purchase, defects and condition surveys

Voluntary inspections are not required by any statute; they exist because the statutory cycle is long and does not cover everything. A PSI happens once in 5 or 10 years, landed houses are outside both PSI and PFI, and neither regime looks at finishes, waterproofing or services in a single unit. The common voluntary inspections are:

Completion inspections for new works are a separate matter, covered in TOP and CSC in Singapore.

The inspection calendar: every check by frequency

Sorted by interval, an owner's inspection calendar looks like this.

  • Daily: on-site pH and disinfectant tests for licensed pools (NEA).

  • Monthly: maintenance of escalators and most lifts (BCA); laboratory water tests for pools (NEA); plate count tests for cooling towers (NEA).

  • Quarterly: Legionella tests for cooling towers, spa pools and pools with aerosol features (NEA).

  • Every 6 months: owner checks of windows and air-conditioner supports (BCA advice); LEW inspection of communal electrical services in multi-tenanted buildings and condominiums (EMA).

  • Yearly: lift and escalator examination, inspection and test for the Permit to Operate (BCA); inspection of fire safety systems (SCDF); steam boilers (MOM); licensed electrical installations (EMA); gas installations in non-residential premises (EMA); water tank certification (PUB).

  • Every 2 years: air receivers, steam receivers and autoclaves (MOM).

  • Every 3 years: Fire Certificate renewal, for certificates starting on or after 1 April 2026 (SCDF).

  • Every 5 years: PSI for non-residential buildings and listed civil engineering structures (BCA); gas pipework up to the meters in multi-consumer residential buildings (EMA).

  • Every 7 years: PFI (BCA).

  • Every 10 years: PSI for residential buildings (BCA); hydrostatic test and thickness gauging of pressure vessels (MOM).

What changed recently

These are the dated changes owners most often miss.

  • 1 January 2022: the Periodic Facade Inspection regime took effect.

  • 1 September 2022: BCA issued enhanced PSI Guidelines with minimum inspection coverage; the Differentiated PSI Approach for ageing buildings followed on 1 February 2023.

  • 5 August 2023: MOM stopped sending reminders for pressure vessel examinations.

  • 1 October 2024: cooling tower owners submit only quarterly Legionella results to NEA.

  • December 2024 and March 2025: PSI notices began for jetties, docks and wharves, then for bridges, underpasses and floating structures.

  • 1 September 2025: Gas Act amendments on Prescribed Persons and Certificates of Fitness took effect.

  • September 2025: MOM updated lifting equipment test and examination requirements.

  • 1 October 2025: the Building Control (Fixed Installations) Regulations 2025 and the Building Control (Reportable Matters) Regulations 2025 took effect.

  • 2 March 2026: BCA circular APPBCA-2026-02 reminded structural engineers to conduct PSI personally and to report unauthorised structures and changes of use.

  • 1 April 2026: Fire Certificate validity became 36 months.

  • 8 May 2026: BCA and URA began a 12-month pilot requiring a usage declaration for shophouses during PSI.

Common mistakes

Most inspection failures are administrative before they are technical. The patterns below come from the agencies' own published observations.

  • Waiting for a reminder. PUB tells owners not to wait for its emails, and MOM no longer sends them for pressure vessels.

  • Treating PSI and PFI as one job. They need separate reports, and BCA accepts one PE for both only when the two notices are served concurrently.

  • Having no drawings. The PSI engineer must work from the approved structural layout plans; see how to buy approved plans from BCA.

  • Appointing an engineer who designed the building, or one without a valid practising certificate; see how to check a Professional Engineer.

  • Leaving unauthorised mezzanines, platforms and changes of use for the inspector to find.

FAQ

Which buildings in Singapore need a periodic structural inspection?

All buildings except detached, semi-detached, terraced and linked houses used solely as residences, and temporary buildings. Residential buildings are inspected every 10 years and all others every 5 years.

How often must lifts be inspected?

Lifts are examined, inspected and tested once a year to renew the Permit to Operate, and most are maintained at least monthly by a BCA-registered contractor.

Is the Fire Certificate still renewed every year?

No. For Fire Certificates with a validity start date on or after 1 April 2026 the validity is 36 months, although SCDF still requires the building's fire protection systems to be inspected annually.

Who can carry out a facade inspection?

A Competent Person: a Professional Engineer in civil or structural engineering or a registered architect who has passed the Certificate in Facade Inspection. Facade Inspectors may assist under supervision.

Do landed houses need any mandatory inspection?

Landed houses used solely as residences are excluded from PSI and PFI and from PUB's annual tank certification. The window retrofitting requirement and the owner's duties for exterior features, slopes and retaining walls still apply.

Who is responsible in a condominium?

For PSI, BCA states that the management corporation takes on the owner's responsibilities in a strata-titled development. The same body is the Prescribed Person for the gas service pipe and normally holds the lift permits and the electrical installation licence for common property.

Can I arrange an inspection before the notice arrives?

Yes for most regimes. For PFI, BCA's FAQ says owners may write in to request an early inspection, considered case by case. A voluntary structural inspection can be commissioned at any time.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including periodic structural inspections and building inspection services. WhatsApp +65 9342 7551. Last reviewed: November 2026.