Dangerous Buildings in Singapore: BCA Orders Closure and Owner Duties

Nov 12
10 min read

When a building in Singapore is assessed to be dangerous, the Building and Construction Authority (BCA) does not wait for the next periodic inspection. Acting under the Building Control Act 1989, the Commissioner of Building Control can serve a Dangerous Building Order and a Closure Order on the owner, have the affected area cordoned off, and require the owner to appoint a Professional Engineer to investigate and to design permanent rectification. The cost and the duty to act fall on the owner, or on the management corporation in a strata development.

What makes a building dangerous in law?

A building is dealt with as dangerous when BCA's engineers assess that its condition puts occupants or the public at risk; the Act leaves this to the Commissioner of Building Control's judgement rather than to a fixed table of crack widths. This article does not reproduce the sections of the Act, which should be read in their current form on Singapore Statutes Online. What BCA does publish is the set of conditions its inspection regimes are designed to catch, and these are the practical indicators:

  • Suspected defects of structural significance, which BCA's Periodic Structural Inspection (PSI) Guidelines say require full structural investigation and immediate action. Examples listed are structural cracks, excessive deflection, connection failure, instability, settlement, tilt, spalling concrete, corrosion of steel and decayed timber.

  • Overloading from misuse or a change of use beyond the design loading.

  • Unauthorised structural works that have altered or overloaded the structure.

  • Any building element at risk of partial or total collapse, including architectural and mechanical fixtures, which the inspecting engineer must report to the owner as soon as possible.

  • Unsafe facade defects, which a Competent Person must report to the Commissioner of Building Control immediately.

Damage from a sudden event is assessed in the same way. Recent published cases have followed a fire and an explosion, not only gradual decay. For the routine regimes that normally find problems first, see our guide to every mandatory building inspection.

What orders can BCA issue?

BCA's two named instruments are the Dangerous Building Order and the Closure Order, and it has used them together. In a written answer to Parliament dated 13 November 2024, the Ministry of National Development stated that after an explosion on 8 October 2024 caused the partial collapse of two commercial shophouses, BCA issued a Dangerous Building Order and a Closure Order to the owners of both. From BCA's published statements, the requirements placed on owners in such cases are:

  • Close the building or the affected part, and keep people out until further investigation is complete.

  • Cordon off the area below or around the hazard, and other parts of the building with the same feature.

  • Appoint a Professional Engineer to investigate the cause and carry out a detailed assessment of the structural condition.

  • Have the engineer recommend immediate safety measures and propose permanent rectification works.

  • Carry out the permanent rectification as the engineer recommends.

Related powers cover specific risks. The Second Reading speech on the Building Control (Amendment) Bill on 6 March 2020 explained that the Commissioner can order an owner to stop operating a lift or escalator until an imminent safety risk is mitigated or removed, and that owners of a building that is not strata-subdivided must jointly appoint a Qualified Person to comply with an order served on several owners. The full range of what an order may require, and the penalties for not complying, are set out in the Act itself; take advice on the current text before responding to an order.

What are the owner's and MCST's duties?

The owner's duty is continuous: to keep the building maintained and safe, not merely to react when BCA writes. BCA's circulars put it directly: owners bear the primary responsibility for adequate maintenance of their buildings, whether or not a periodic inspection applies. In concrete terms the duties are:

  • Arrange the Periodic Structural Inspection when notified (every 5 years for non-residential and every 10 years for residential buildings), give the engineer access, and carry out the recommended rectification. In a strata-titled development the management corporation takes on these responsibilities. See Periodic Structural Inspection: Stage 1, Stage 2 and what happens next.

  • Arrange the Periodic Facade Inspection every 7 years once the building is over 13 m high and over 20 years old. See PSI vs PFI.

  • Keep exterior features maintained and securely fixed. BCA's PFI FAQ cites a fine of up to $10,000, imprisonment of up to 12 months, or both, for a responsible person who fails to do so.

  • Engage a structural engineer whenever defects or deterioration are noticed between inspections. BCA's Owner's Guide says owners should not inspect only when required to.

  • Maintain slopes and retaining walls and rectify defects on detection, engaging a PE in civil, structural or geotechnical engineering when warning signs appear.

  • Report incidents. Under the Building Control (Reportable Matters) Regulations 2025, a fallen exterior feature must be reported by telephone to BCA's Safety Incident Hotline within 6 hours of becoming aware of it, with an incident report submitted within 24 hours.

For how these duties sit with a council and managing agent, see building maintenance duties of MCSTs.

How do unauthorised works make a building dangerous?

Unauthorised works make a building dangerous by adding load or removing strength that the approved design never allowed for. BCA's PSI Guidelines define them as structural works carried out without the prior approval of plans that Part 2 of the Building Control Act requires, and the checklist specifically asks the engineer to look for an additional unauthorised floor within a high-volume space. Three recent developments show how seriously BCA treats the issue:

  • On 28 January 2025 a mezzanine floor and racking collapsed in a warehouse, trapping three people. SCDF found that no Fire Safety Certificate had been issued for the mezzanine and BCA had received no application for it, as reported by The Straits Times and republished by Stomp.

  • On 2 March 2026 BCA's circular APPBCA-2026-02 criticised structural engineers who failed to report unauthorised structures, or failed to detect a change of use that raised the imposed load, such as shophouses converted from residential to commercial use.

  • On 8 May 2026 BCA and URA began a 12-month pilot under which engineers conducting PSI on shophouses must record and declare the observed use of the space, citing various safety incidents involving unauthorised use.

Carrying out building works without approved plans or a permit carries a fine of up to $200,000, imprisonment of up to 2 years, or both. When a PSI engineer finds unauthorised works, the Guidelines require the engineer to state their effect on the structure and to advise the owner to demolish or regularise them. See unauthorised mezzanines and building works, regularisation of unauthorised structures and, for what genuinely needs no approval, insignificant building works.

What should you do if you see cracks or a falling facade?

Keep people away first, then report, then get an engineer. The steps depend on who you are:

  1. If there is immediate danger to life, call the emergency services and keep clear of the area below the hazard.

  2. Members of the public, tenants and neighbours can report unsafe buildings or works to BCA on 1800 342 5222 or through BCA's online feedback form at www2.bca.gov.sg/feedback, giving the location and photographs.

  3. Owners and other persons responsible for a fallen exterior feature must call BCA's Safety Incident Hotline (9789 7847 or 9781 6720) within 6 hours and submit the incident report within 24 hours. BCA states that incidents should not be reported by SMS or WhatsApp.

  4. Tell the owner or the management corporation in writing, with dated photographs, so that there is a record.

  5. The owner should engage a Professional Engineer in civil or structural engineering to assess the defect without waiting for the next PSI.

Not every crack is structural. Hairline cracks in plaster and finishes are common and usually cosmetic, while cracks that are wide, growing, stepped through brickwork or accompanied by sagging, sticking doors or exposed rusting steel deserve prompt assessment. Our guide to spalling concrete and ceiling leaks explains the usual warning signs.

What is the Professional Engineer's role?

The Professional Engineer establishes what is wrong, makes the building safe in the short term, designs the permanent repair and certifies its completion. In the cases BCA has published, the owner was required to appoint a PE for exactly this sequence. The work typically runs as follows:

  • Immediate safety measures: cordons, exclusion zones, load restrictions and temporary propping where needed.

  • Investigation: a review of the approved structural plans, a survey of defects and unauthorised works, and where necessary the kind of work BCA lists for a full structural investigation, namely material tests, checks of structural adequacy by calculation and load tests.

  • Rectification design: repair, strengthening or partial removal. BCA's Guidelines state that major repairs and strengthening works are building works, so plan approval, a permit and supervision apply before work starts.

  • Supervision and certification of the remedial works, and monitoring where the engineer recommends it.

The engineer needs the approved drawings to do this properly. If the owner does not hold them, they can be purchased from BCA; see how to buy approved structural plans and building plans from BCA. Related services are structural strengthening and structural monitoring. The engineer must be registered and hold a valid practising certificate, which you can confirm using how to check a Professional Engineer.

What do verified cases show?

Published cases show a consistent pattern: BCA engineers attend, the area is closed or cordoned, and the owner must appoint a PE and fund the repair. The cases below are described without naming the parties.

  • November 2018, fallen facade feature: a strip of plaster about 4.0 m by 0.3 m fell from the second storey of a building and injured a passer-by. BCA cordoned off the area below and other parts of the facade with the same feature, and instructed the owner to appoint a PE to investigate, inspect the rest of the facade and carry out permanent rectification.

  • August 2020, fallen duct in a cinema: an air-conditioning and mechanical ventilation duct fell. BCA ordered the cinema closed until investigation was complete and directed the owner to appoint a PE to investigate and to assess the other ducts.

  • October 2024, explosion in shophouses: two commercial shophouses partially collapsed, and BCA issued a Dangerous Building Order and a Closure Order to both owners.

  • January 2025, collapsed mezzanine: an unapproved mezzanine floor and racking collapsed in a warehouse, trapping three people.

  • May 2025, fire in a three-storey commercial building: BCA found spalling to columns and slabs and deformed steel roof trusses but no significant deformation of the concrete frame, and said it would order the owner to close the building and appoint a PE for a detailed investigation, immediate safety measures and permanent rectification, as reported by The Straits Times.

The background numbers explain the regulatory attention. BCA's PFI FAQ says that on average more than 20 incidents of fallen facade elements are reported to it every year; in March 2020 Parliament was told that the figure had been almost 30 a year over the preceding three years, mostly from wear and tear of facade materials or their connections.

Which authority governs what?

BCA's Commissioner of Building Control governs the structural safety of existing buildings under the Building Control Act 1989, including periodic inspections, dangerous buildings and unauthorised building works. Other agencies act alongside:

  • SCDF, under the Fire Safety Act 1993, for fire safety works and Fire Certificates; unapproved mezzanines often breach both regimes.

  • URA for planning permission and conserved buildings, and with BCA for the 2026 shophouse usage declaration pilot.

  • MOM for workplace safety where the danger arises in a factory, warehouse or worksite.

Common mistakes

The most damaging mistake is to treat an order or an engineer's warning as negotiable. Others seen repeatedly:

  • Repairing over a defect without finding its cause. BCA's Guidelines warn that incorrect repair of spalling concrete lets deterioration continue undetected beneath the fresh repair.

  • Starting major repair or strengthening without plan approval and a permit.

  • Hiding or ignoring unauthorised works before an inspection instead of regularising or removing them.

  • Assuming the tenant or the managing agent is responsible. The duties and the orders sit with the owner or the management corporation.

  • Assuming a sale ends the obligation. For both PSI and PFI, BCA's answer is that an owner cannot be exempted from recommended repairs because the building is being sold.

FAQ

Who pays for the investigation and repair of a dangerous building?

The owner. In each published case BCA instructed the building owner to appoint the Professional Engineer and to carry out the rectification.

Can BCA close a building that is still structurally safe?

Yes. In the May 2025 fire case, BCA found the building structurally safe but still required it to be closed pending a detailed investigation by the owner's PE.

Who do I call about cracks in a neighbouring building or unsafe works?

BCA on 1800 342 5222, or its online feedback form, with the location and photographs.

Does a clean PSI report mean the building cannot be declared dangerous?

No. A PSI is a periodic snapshot. Fire, impact, explosion, ground movement or later unauthorised works can make a building dangerous at any time.

Are landed houses covered?

Landed houses used solely as residences are excluded from PSI and PFI, but BCA's powers over dangerous buildings and the rules on unauthorised works are not limited to buildings in the periodic regimes. Owners remain responsible for their structures, slopes and retaining walls.

What should I do on receiving a BCA order?

Comply with the closure and safety requirements immediately, appoint a Professional Engineer in civil or structural engineering, and obtain the approved plans. Read the order for its deadlines and take advice on the current provisions of the Act.