TOP and CSC in Singapore: What Building Owners Need to Know

Nov 11
5 min read

Updated: 6 days ago

A Temporary Occupation Permit (TOP) and a Certificate of Statutory Completion (CSC) are the two documents the Building and Construction Authority (BCA) issues to allow a building, or part of one, to be occupied after building works. A CSC is issued when the development has complied with all relevant statutory requirements and obtained every agency clearance. A TOP is issued when the building is suitable for occupation but some matters with technical agencies are still outstanding, and the application for either is made by the project's Qualified Person (QP), not by the owner directly.

What is the difference between a TOP and a CSC?

BCA describes the two documents this way:

  • CSC: issued when a development has complied with all relevant statutory requirements and has all the necessary clearances from the technical agencies.

  • TOP: issued when a development is suitable for occupation but still has outstanding issues with some technical agencies.

Section 12 of the Building Control Act 1989 adds two points owners often miss. First, a TOP is only prima facie evidence that the building is suitable for occupation. It is not evidence that the works comply with the Act or the building regulations. Second, the Commissioner of Building Control may grant a TOP subject to written directions, for example limiting its duration or requiring specified work to be completed within a set period, and may amend, suspend or revoke the permit if those directions are not followed. A TOP is a stage in the process. The CSC is what closes it.

Who applies, and what does the owner do?

BCA states that the application must be made by the project's QP appointed by the developer. Under the Building Control Act, a QP is a registered architect or a professional engineer who holds a valid practising certificate. On an owner-initiated project such as an extension or additions and alterations, the owner is the party who appoints the QP, so the owner's practical role is to appoint the right team early, keep the builder working to the approved plans, and make sure agency conditions are closed out. See QP submission from appointment to CSC for the earlier stages.

What must be in place before applying?

BCA lists three broad requirements: building regulatory compliance, clearances from the relevant technical agencies, and the completion certificates. The documents BCA lists include, where applicable:

  • Certificate of Supervision of Building Works and the QP's declaration

  • Certificates of supervision for structural works and piling works

  • Builder's Certificate of Completion of Building Works

  • As-built plans, test reports and certificate of supervision for the lightning protection system

  • Certificate of supervision for the air-conditioning and mechanical ventilation system

  • QP's declaration that lifts and escalators follow the approved plans and have Permits to Operate

  • Listings of engineered facades and safety barriers

  • Commissioning approval for civil defence shelters

Supervision certificates depend on how the works were supervised on site. See site supervision for structural works for the QP, Resident Engineer and Resident Technical Officer roles.

How does the inspection and application work?

  1. The QP logs on to BCA's TOP/CSC Portal, selects the project and books an inspection date.

  2. The QP submits the certificate of supervision and QP declaration forms at least 3 days before the inspection.

  3. BCA inspects. A standard inspection is carried out on site. An express inspection can be arranged within the next 4 days, depending on project size, for a fee of $3,000. A virtual inspection uses 360-degree captures reviewed remotely, and BCA responds within 3 working days.

  4. The QP addresses BCA's written advice from the inspection and submits the documents and agency clearances.

  5. BCA processes the application. Its stated service standard is 7 working days from complete documents for a TOP and for a CSC, although a CSC application with many unresolved defects may take longer.

BCA also offers an Express TOP, processed within 1 working day of complete documents and payment if BCA accepts the application. The fee is $500 where the building works are up to 3,000 m² and $1,000 above that.

Which authority governs what?

  • BCA (Commissioner of Building Control): issues the TOP and CSC under section 12 of the Building Control Act 1989.

  • SCDF (Fire Safety and Shelter Department): fire safety clearance. See SCDF fire safety submission.

  • URA: planning clearance.

  • PUB: drainage and sewerage.

  • NEA: pollution control and environmental health.

  • LTA and NParks: roads, transport, vehicle parking and greenery matters.

  • EMA: residential developments with 10 or more units.

Only a QP who is a professional engineer in the civil or structural discipline can apply for structural plan approval, so most projects with structural works need both architectural and structural input before a CSC can be reached. Larger or more complex projects may also involve an Accredited Checker.

What happens if a building is occupied without a TOP or CSC?

Section 12 of the Building Control Act provides that a person must not occupy, or permit or cause the occupation of, a building where building works have been carried out unless a CSC has been issued. The two exceptions are occupation of a building covered by a TOP, and occupation solely to prevent damage to the building or theft of property in it.

Contravention is an offence. The penalty on conviction is a fine of up to $20,000, imprisonment of up to 6 months, or both, with a further fine of up to $1,000 for each day the contravention continues.

Common mistakes

  • Treating the TOP as the finish line. Outstanding items remain open until the CSC is issued, and a TOP can be suspended or revoked.

  • Building differently from the approved plans. Deviations found at inspection have to be resolved before a CSC. BCA's published enforcement list records a QP fined $8,000 in March 2025 for a false declaration, made for a CSC, that the works did not deviate from the approved plans.

  • Adding structures after the CSC. A mezzanine, platform or shelter added later is new building works with its own approval path. Our articles on mezzanine floor approval and regularising unauthorised structures explain what is involved.

  • Buying without checking the paperwork. When acquiring an older property, check that later additions were approved and completed properly. A pre-purchase structural assessment can include this.

FAQ

Can I move in with only a TOP?

Yes. Section 12 of the Building Control Act permits occupation of a building that is covered by a TOP. The CSC must still be obtained afterwards.

Is a TOP proof that the works comply with the regulations?

No. The Act states that a TOP is only prima facie evidence that the building is suitable for occupation, not evidence of compliance with the Act or the building regulations.

How long does BCA take to process a TOP or CSC?

BCA's service standard is 7 working days from the submission of complete documents. An Express TOP, if accepted, is processed within 1 working day.

Do minor works need a TOP or CSC?

Works that required BCA plan approval and a permit are closed out through this process. Insignificant building works do not need BCA approval in the first place.