Retaining Walls and Slopes for Landed Houses in Singapore: Rules and Approvals
A retaining wall for a landed house in Singapore needs BCA plan approval once its visible height exceeds 1.5 m in reinforced concrete or structural steel, or 1 m in any other material, and an Accredited Checker once it exceeds 4 m. Separately, URA's planning guidelines generally limit retaining walls to 1 m, boundary walls to 1.8 m and the two combined to 2.8 m. Both sets of rules apply, and the lower limit usually governs the design.
When does a retaining wall need BCA approval?
A retaining wall or earth retaining structure is exempt from BCA plan approval and permit only if it meets all the conditions in paragraph (q) of the First Schedule to the Building Control Regulations 2003. Those conditions are:
It is not founded on piles.
It is not within 3 m horizontally of another retaining wall or earth retaining structure.
Its visible height does not exceed 1.5 m if built of structural steel or reinforced concrete, or 1 m if built of other materials such as brick or blockwork.
Site formation works with excavation or filling not exceeding 1.5 m in depth or height are also on the list, as is a boundary wall, fence or gate that is not load bearing. Anything outside these limits is building work that needs approved plans and a permit before it starts. The wider list is explained in insignificant building works in Singapore.
When is a PE enough, and when is an Accredited Checker required?
Retaining walls and excavations between 1.5 m and 4 m need a Qualified Person only, and above 4 m an Accredited Checker is also required. BCA's ERSS submission requirements (June 2026) set out the bands:
Up to 1.5 m deep (1 m if not reinforced concrete or steel): plan approval is not required.
More than 1.5 m and up to 4 m: QP for structural works, no AC.
More than 4 m and up to 6 m: QP and AC.
More than 6 m and classified as geotechnical building works, such as a basement excavation: QP, AC, PE(Geo) and AC(Geo).
The Fourth Schedule to the Regulations is consistent with this: retaining walls not exceeding a visible height of 4 m, and houses not exceeding 3 storeys, are minor building works that do not need an AC's certificate. Only a PE in the civil or structural discipline can apply for structural plan approval. See ERSS submission thresholds and when your project needs an Accredited Checker.
What height does URA allow for retaining and boundary walls?
URA's development control guidelines for landed housing state that retaining walls, if allowed, shall not be more than 1 m high, and boundary walls shall not exceed 1.8 m. The guidelines for detached houses (last updated 7 June 2026) add:
Outward facing retaining walls are not encouraged, because they mar the streetscape.
Retaining walls higher than 1 m may be considered along common boundaries, suitably tiered and planted, if alternative measures are impractical.
Retaining walls fronting a road or street must be terraced at least 300 mm apart and planted.
The combined height of a retaining wall and boundary wall shall not exceed 2.8 m, of which the solid wall shall not exceed 1.8 m.
Where a boundary wall sits on top of a retaining wall, only porous material such as fencing may be used for the boundary wall.
URA publishes the same section for each landed housing type, so check the page for your house form. Because URA's 1 m is lower than BCA's 1.5 m exemption, a wall can be exempt from BCA approval and still need planning consideration.
How much earthworks can a landed house site have?
URA generally does not allow earthworks within the road buffer or building setback, and where it does, they shall not exceed 1 m. Raising the platform level of the entire site is generally not allowed, precisely to avoid creating new retaining walls. URA may consider earthworks to:
Create a vehicular access of maximum 4 m wide.
Match the platform levels of neighbouring sites.
Build a fully submerged basement, with the setback area reinstated to the original level afterwards.
Low-lying sites are the main exception. PUB determines the Minimum Platform Level, which is the minimum first storey level for the site, and URA assesses earthworks of more than 1 m needed to meet it on their merits. Only the building and the setbacks from common boundaries need to be raised; the road buffer need only be 300 mm above the adjacent road level or not lower than existing ground, whichever is higher.
What about slopes?
Slopes are regulated by height: earthworks to construct or stabilise a slope higher than 6 m are geotechnical building works that need a PE(Geo) and AC(Geo). For alterations or strengthening that materially affect the global stability of an existing slope, BCA's guidance requires a QP and AC where the affected slope height exceeds 4 m, and a PE(Geo) and AC(Geo) where it exceeds 6 m.
BCA's Framework on Risk-Based Slope Design (January 2024) notes that rainfall-induced failure is the most common form of slope failure in Singapore, and requires an onerous design groundwater level for excavated slopes. It also states that soil nails extending beyond the land boundary need a consent letter from the adjacent landowner before the design is submitted. The PE(Geo) role is explained in geotechnical engineering in Singapore.
What must I do before excavating a basement next to neighbours?
The builder must carry out a pre-construction survey of neighbouring buildings before excavation, piling or demolition starts, and for landed development BCA's guidelines set the minimum survey zone for excavation at 15 m from the site boundary. For landed property BCA also requires a communication plan:
The builder notifies neighbours of the works using BCA's notification form.
Written consent is obtained where access is needed, for example for the survey or to install monitoring instruments.
The status of the survey and communication plan is notified to BCA with the permit application.
BCA's Be Good Neighbours guide warns that a basement or sunken pool between intermediate terrace or semi-detached houses can affect the neighbour's party wall, advises a suitable earth retaining and stabilising system, and states that BCA may revoke the permit if the works damage neighbouring property. See impact assessment and pre-construction surveys.
Which authority governs what?
Three agencies are usually involved in a landed house retaining wall or basement.
URA: wall heights, earthworks and platform levels as planning matters.
BCA: structural safety, plan approval, permit, ERSS and slopes under the Building Control Act.
PUB: the Minimum Platform Level and drainage; earth control measures are covered in our ECM submission guide.
Common mistakes
Most landed house wall problems start with measuring the wrong thing.
Reading the 1.5 m exemption as a planning approval. URA's 1 m guideline still applies.
Building in brick or blockwork above 1 m and assuming the 1.5 m limit applies.
Tiering walls closer than 3 m apart to stay under the height limit.
Excavating for a basement before the pre-construction survey is done and distributed.
Starting without approval. Carrying out building works without approved plans or a permit carries a fine of up to $200,000, imprisonment of up to 2 years, or both.
FAQ
Do I need a PE for a 1 m garden retaining wall?
Not for BCA approval, if the wall is not on piles and not within 3 m of another retaining wall.
How high can my boundary wall be?
URA's guideline is 1.8 m, and 2.8 m combined with a retaining wall, with the solid portion not exceeding 1.8 m.
Does a basement in a landed house need an Accredited Checker?
If the excavation is deeper than 4 m, yes. A house of up to 3 storeys otherwise does not need an AC.
Who pays if my excavation cracks the neighbour's house?
BCA's guide says the owner should get the builder to rectify the reported damage. Liability between the parties is a private matter.
Sources
Building Control Regulations 2003, First Schedule and Fourth Schedule (Singapore Statutes Online)
BCA Geotechnical Building Works Submission Requirements, June 2026
URA: Retaining and Boundary Walls, Bungalows (or Detached Houses)
BCA: Pre-construction survey and communication plan for landed development
CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including ERSS submissions and additions and alterations for landed homes. WhatsApp or call +65 9342 7551. Last reviewed: November 2026.