PE Endorsement for Lifting Operations in Singapore: Lifting Plans and Crane Foundations
Updated: Nov 12
A routine lifting plan in Singapore is prepared and carried out by the contractor's lifting team, not signed by a Professional Engineer (PE). A PE becomes necessary at defined points: the foundation and wall ties of a tower crane must be designed and supervised by a PE, lifting equipment must be tested and examined by an Authorised Examiner (a PE in a specialised branch), and complex lifts need engineering design beyond a standard plan.
Is a lifting plan mandatory, and what goes into it?
The Workplace Safety and Health (WSH) Council states that before any lifting operation starts, the following must be prepared:
A lifting plan supported by a risk assessment.
A safe work procedure or method statement.
A permit-to-work.
Supporting documents such as load capacity charts, range diagrams and rigging methods.
The plan covers the load, the lifting equipment and gear, the lifting crew with their roles and competencies, the lifting method, communication, physical and environmental conditions, and a sketch of the lifting zone. The Council's instruction on discipline is direct: never deviate from the approved lifting plan, and if conditions on site do not tally with the plan, stop the operation.
The Code of Practice on Safe Lifting Operations in the Workplaces places overall responsibility on the contractor carrying out the lift, who is the "responsible person" under the Workplace Safety and Health (Operation of Cranes) Regulations 2011. The lifting supervisor must be appointed in writing by the contractor.
When does a lift need engineering input?
The Code of Practice separates routine lifts from non-routine lifts. A non-routine lift is one that is complex, carried out for the first time, or close to the lifting capacity of the crane. Its example is a tandem tilt-up using two or more cranes, which needs a detailed risk assessment and an engineering method, including the number and position of lifting lugs so that a long structure does not buckle.
The Code says frequent or routine lifts may need only a basic lifting plan with an on-site risk assessment and briefing, while high-risk or complex lifts require additional engineering design. It does not prescribe one rule for who provides that design. In practice the questions are structural ones:
Can the ground, slab or temporary platform carry the outrigger or track loads?
Are purpose-made lifting frames, spreader beams and lifting lugs adequate for the load?
Will the lifted element remain stable and unbuckled at every stage?
On ground conditions, the Code states that the ground must be level and have sufficient bearing capacity, that outriggers must be evenly and fully extended, and it recommends steel plates of adequate strength and size under the outriggers of mobile or crawler cranes. Where a crane stands on a suspended floor inside a building, the check is the same one described in our article on machine foundations and floor loading.
What must a PE do for a tower crane?
The Ministry of Manpower (MOM) sets this out in its notification form and requirements for the use of tower cranes. Since 11 August 2023, an occupier who intends to install and use a tower crane must complete the notification form, which the Authorised Examiner uploads through MOM's WSH e-Service. The PE requirements are:
The foundation, and the wall ties where applicable, must be designed by a PE of the relevant discipline, who also supervises their construction.
The foundation design must consider the final height and configuration of the crane and the forces in both in-service and out-of-service conditions, including wind, using the more conservative case.
Wall ties designed by a PE must be installed if the crane exceeds a free-standing height of 40 metres. The occupier or owner must seek the Commissioner's approval to exceed that free-standing height.
The occupier must hold the PE-endorsed drawings and calculations and a letter of undertaking that the PE will supervise construction.
After construction, the PE issues a certificate confirming that the foundation or wall ties were built under his supervision and conform to the design.
The form defines a PE as a person with valid registration with the Professional Engineers Board. Our guide on how to check a Professional Engineer shows how to verify this.
What does the Authorised Examiner do?
An Authorised Examiner (AE) is a different appointment from the civil or structural PE. To be approved by MOM, an AE must be registered with the Professional Engineers Board and hold a practising certificate in a specialised branch: Crane Engineering, Access Platform Engineering or Lift and Escalator Engineering.
The owner of lifting equipment must engage an AE to test, examine and register it with MOM. Registrable equipment includes tower, mobile and gantry cranes, lorry loaders, mobile elevating work platforms, mast climbing work platforms and gondolas.
For a tower crane, the AE checks the load-bearing parts and safety devices before installation, endorses the layout plan, verifies that wall ties are built to the PE's design, and tests the crane before use.
Installation, alteration, dismantling and repair of a tower crane may only be carried out by an approved crane contractor.
Under changes MOM announced in 2025, periodic overload tests after first registration were removed, and hoists carrying materials are examined by an AE at least once every 12 months instead of every 6 months.
Which authority and regulation governs what?
MOM: the Workplace Safety and Health Act, the WSH (Operation of Cranes) Regulations 2011, the WSH (General Provisions) Regulations for examination of lifting equipment, and the WSH (Construction) Regulations 2007.
WSH Council: the Code of Practice on Safe Lifting Operations in the Workplaces and the WSH Guidelines on Lifting Plan Development (published May 2024).
Professional Engineers Board: registration and practising certificates of PEs, including the specialised branches held by AEs.
BCA: MOM's tower crane form covers the crane base as a workplace safety matter. If a crane base or tie loads the permanent building structure, raise it with the project's Qualified Person, whose role is explained in PE endorsement vs QP submission.
What goes wrong
The plan and the site do not match. A different crane, a changed boom length or a changed sequence of operations are all changes that the Code of Practice says must stop the lift for a review of the risk assessment and permit-to-work.
Ground is assumed, not assessed. Backfilled trenches, basement roofs and slabs near excavations are where outrigger loads cause trouble.
Wall ties are fixed where convenient. MOM requires the AE to verify that ties are built as designed by the PE.
Old equipment is brought in. MOM does not permit imported used tower cranes that are 15 or more years old, and no tower crane 20 or more years old may be used.
FAQ
Does a PE have to sign every lifting plan?
No. The published requirement is a lifting plan supported by a risk assessment, method statement and permit-to-work. Engineering design is added for high-risk or complex lifts.
Who can design a tower crane foundation?
A PE of the relevant discipline, who must also supervise its construction and certify it on completion.
Is an Authorised Examiner the same as a civil PE?
No. An AE holds a practising certificate in a specialised branch such as Crane Engineering and deals with the lifting equipment. The foundation and supporting structure are civil and structural matters.
Sources
CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, and provides PE endorsement services for civil and structural works. Related reading: PE endorsement for scaffolds. WhatsApp +65 9342 7551. Last reviewed: November 2026.


Comments