New Home Defects Inspection in Singapore: Defects Liability Period Explained

Nov 12
9 min read

The defects liability period (DLP) for a new home in Singapore is 12 months. For private homes bought from a licensed developer it runs under the standard Sale and Purchase Agreement prescribed by the Housing Developers Rules, and the developer must make good defects at its own cost within one month of the buyer's notice. For new HDB flats it is one year from key collection, with longer HDB warranties of 5 years for ceiling leaks and external wall seepage and 10 years for spalling concrete. A defects inspection at handover is how a buyer finds and records problems while the developer or HDB's contractor is still obliged to fix them.

What is the defects liability period for a new private home?

The DLP for a private residential unit is 12 months. URA's Home Buyers' Guide states that the developer is obliged to rectify any defects in the unit, the common property or the housing project that become apparent within 12 months from the earlier of:

  • the date the developer delivers vacant possession of the unit, or

  • the 15th day after the buyer receives notice that the Temporary Occupation Permit (TOP) has been issued and the infrastructural works serving the project are complete.

URA defines a defect as any fault due to defective workmanship or materials, or to the unit not having been constructed according to the specifications in the Sale and Purchase Agreement (S&PA). Licensed housing developers must use the standard form of S&PA, and no amendment can be made without the prior approval of the Controller of Housing.

URA is also clear about what the DLP is not. BCA regulates construction for compliance with the Building Control Act, which focuses primarily on structural safety, and issues the TOP when those requirements are met. Workmanship defects in the unit are not regulated; they are contractual matters between developer and purchaser under the S&PA. What TOP means is explained in TOP and CSC in Singapore.

What is changing for private homes from 31 December 2026?

From 31 December 2026 the DLP for an individual unit stays at 12 months, but its start date and the DLP for common property change. URA and BCA's circular of 30 October 2026 (URA/COH/Circular-2026-03) on strengthening the Housing Developers Rules sets out:

  • Unit DLP: unchanged at 12 months from vacant possession.

  • Start date: the DLP and the buyer's liability for maintenance charges will start together, on the 35th day after receipt of the notice of TOP payment or on the actual date of vacant possession, whichever is earlier.

  • Common property DLP: extended to 12 months, or six months after the first annual general meeting, whichever is later, so that the management council can oversee defect reporting and rectification.

  • Other protections: units must be built according to the scaled floor and site plans given to buyers, and developers must disclose their CONQUAS track records.

Projects launched for sale on or after 31 December 2026 must use the new Option to Purchase and S&PA. Projects with options issued before that date may continue with the existing prescribed forms for unsold units. The amendments also apply to executive condominiums. Check which form your own agreement uses.

What does HDB provide for new flats?

HDB gives a one-year DLP from the date of key collection, plus longer warranties for three defect types. From HDB's MyNiceHome guides:

  • Defects liability period: 1 year from key collection. Defects covered are rectified by HDB's building contractor.

  • Ceiling leaks and external wall seepage: 5-year warranty. It ceases if floor tiles are changed or the waterproofing system is tampered with.

  • Spalling concrete: 10-year warranty.

  • Reporting window: HDB says all defects must be reported within 30 days of key collection, before renovation starts, because it is otherwise hard to tell whether the building contractor or the renovation contractor caused a problem.

After the first year, owners are responsible for general care, maintenance and wear-and-tear repairs inside the flat, while the Town Council looks after common areas and external walls. Later problems with spalling and leaks are covered in spalling concrete and ceiling leaks.

How do I report defects, and how long does the developer have?

For a private home, you report defects to the developer in writing following the procedure in the S&PA, and the developer must make good the defects at its own cost within one month of receiving your notice. URA's Home Buyers' Guide then gives the buyer a remedy: if the developer fails to rectify within the specified time, the buyer may engage its own contractors and deduct the cost from the sum held by the Singapore Academy of Law as stakeholder, by following the S&PA procedure and serving a notice of deductions on the Academy.

For an HDB flat the steps are:

  1. Inspect each space and mark defects with painter's tape or notes.

  2. Record them on a defects list.

  3. Submit a rectification request using the QR code in the Welcome Kit, or at the Building Service Centre in the precinct, within 30 days of key collection.

  4. Attend the joint inspection, where Building Service Centre staff verify the reported defects.

  5. Allow the contractor to rectify. HDB says repairs typically take under two weeks.

  6. Attend the closing inspection to confirm the defects have been dealt with.

In both cases keep dated photographs, a numbered list keyed to a floor plan, and copies of everything sent. A joint inspection with the developer's or HDB's representative is the point at which each item is agreed as a defect or disputed, so attend it with your list.

What should I check at handover?

Check every room systematically for defects in finishes, fittings, water-tightness and services, and record anything that looks wrong before furniture or renovation hides it. A practical order:

  • Floors: hollow-sounding, cracked, chipped or uneven tiles; scratched or gapped timber; inconsistent joints.

  • Walls and ceilings: cracks, stains, uneven plaster, damp patches.

  • Doors and windows: alignment, smooth operation, locks, gaps, damaged frames and glass, sealant, and signs of water entry after rain.

  • Wet areas: floor gradient towards the floor trap, ponding, and stains on the ceiling of your unit below the unit above.

  • Fittings: cabinets, wardrobes, vanity tops, sanitary ware, shower screens and mirrors.

  • Plumbing and electrics: water pressure, drainage, leaks under sinks, every socket and switch.

  • External areas: balcony and roof terrace drainage, railings, and air-conditioner ledges.

HDB notes that slight colour variations in floor tiles or timber, and variations in tile grout width, are normal and not treated as defects.

BCA's Quality Mark shows which items a formal workmanship assessment looks at: floors, internal walls, ceilings, doors, windows and fixtures, plus a water ponding test for bathrooms and toilets. BCA's May 2026 circular on errant developers gives examples of major defects under its CONQUAS classification: missing or broken accessories for architectural items, cracked or broken glass items such as windowpanes, shower screens and mirrors, and visibly cracked tiles or stones.

What does an engineer add to a defects inspection?

An engineer adds a judgement on whether a defect is cosmetic or structural, and on its cause. A general defects inspector records workmanship items against tolerances: hollow tiles, misaligned doors, paint blemishes. That list is what the DLP process runs on, and for most new homes it is enough.

An engineer is worth involving when the inspection finds:

  • Cracks in beams, columns, slabs or load-bearing walls, as opposed to plaster or partition joints.

  • Persistent water ingress through external walls, windows or the slab above.

  • Noticeable floor slope, slab deflection or ponding that suggests more than a screed problem.

  • Cracking, settlement or retaining wall movement in a new landed house.

  • Differences between what was built and the approved plans or specifications.

  • A dispute where the developer says an item is not a defect and independent technical evidence is needed.

The engineer's role is diagnostic: identifying the element, the likely cause, whether it affects structural adequacy or durability, and what an acceptable repair looks like. The DLP is a contractual period for defects generally; a suspected structural defect should be raised with the developer in writing at once, whatever the date. For condition checks on older or resale property see pre-purchase building inspection.

What are CONQUAS and the BCA Quality Mark?

CONQUAS is BCA's national standard for assessing the workmanship quality of new building projects, introduced in 1989, and the Quality Mark is BCA's unit-by-unit certification for new private homes, launched on 1 July 2002.

  • CONQUAS assesses by sampling. For projects with tenders called from 1 July 2023 it covers internal finishes, installation methods verification and functional tests (bathroom waterproofing, tiling, timber flooring and windows), and external finishes. BCA launched CONQUAS (Private Residential) in November 2025 for private projects with a residential component, focused on workmanship that affects liveability and functionality.

  • The Quality Mark assesses every unit in a project. A unit must score at least 85 out of 100 for internal finishes and be free from major defects and from water seepage in toilets, bathrooms and windows. BCA says adoption is voluntary, except for residential sites sold under the Government Land Sales programme on or after 30 June 2022 and projects under the Built Environment Transformation GFA Incentive Scheme. It does not assess material quality, design or aesthetics.

Both certify condition at the time of BCA's assessment. Neither replaces your own inspection at handover, and neither extends the DLP. They do matter commercially: under the frameworks announced on 22 May 2026, developers with consecutive projects that have major defects may be disqualified from residential land sales or placed on a sales suspension list for up to five years.

What if the developer will not fix a defect?

Start with the S&PA procedure, then negotiation and mediation, before considering legal action. URA's Home Buyers' Guide encourages buyers to resolve disputes by direct negotiation and, failing that, mediation, and lists these avenues:

  • Singapore Mediation Centre, including its Small Case Commercial Mediation Scheme for claims below $60,000 and a neutral evaluation service.

  • Law Society Mediation Scheme.

  • REDAS Conciliation Panel, for disputes with developers who are members of the Real Estate Developers' Association of Singapore.

  • SISV Dispute Resolution Centre.

The self-help remedy under the S&PA, engaging your own contractor and deducting the cost from the stakeholder sum, is available where the developer has missed the one-month period, provided the S&PA steps are followed exactly. Take legal advice before relying on it. For common property, the management corporation is the body that coordinates defect reporting once it is formed; see building maintenance duties of MCSTs.

Buyers from developers of four or fewer units should take extra care. URA notes that such developers need not be licensed and may use their own sales contract, so the buyer should check that it provides for a DLP at all.

What goes wrong during the defects liability period?

The most common mistake is starting renovation before defects are recorded and agreed. Others:

  • Missing HDB's 30-day reporting window.

  • Reporting defects verbally or piecemeal, with no dated list and photographs.

  • Skipping the joint inspection.

  • Changing bathroom floor tiles in an HDB flat and losing the 5-year ceiling leak warranty.

  • Testing wet areas only after cabinets and finishes are installed over them.

  • Assuming the DLP runs from the day you move in. It runs from vacant possession or the date fixed by the notice, whichever is earlier, so a unit left empty still uses up its 12 months.

  • Treating a crack in a structural element as a paint defect.

  • For strata buyers, ignoring common property defects because they are outside the unit.

FAQ

How long is the defects liability period for a new condo in Singapore?

12 months. Under the current prescribed agreement it runs from vacant possession or the 15th day after the TOP notice, whichever is earlier. Agreements under the rules effective 31 December 2026 use the 35th day after the notice of TOP payment or actual vacant possession, whichever is earlier.

How long is the DLP for a BTO flat?

One year from key collection. HDB also gives a 5-year warranty for ceiling leaks and external wall seepage and a 10-year warranty for spalling concrete.

How long does the developer have to fix defects?

URA's Home Buyers' Guide says the developer must make good defects at its own cost within one month of receiving the buyer's notice.

Can I renovate before the defects are fixed?

You can, but you should not. HDB tells flat owners to report all defects within 30 days and before renovation starts. For private homes, renovation over an unrecorded defect makes it hard to show the developer caused it.

Do I need an engineer or a defects inspector?

A defects inspector is suited to finishes and workmanship. An engineer is needed where there are cracks in structural elements, persistent water ingress, deflection, or a dispute needing independent technical evidence. Our building inspection services cover the structural side.

Does the DLP cover common property in a condo?

Yes. URA's guide says the developer's obligation covers defects in the unit, the common property and the housing project. From 31 December 2026 the common property DLP is extended to 12 months or six months after the first annual general meeting, whichever is later.

What happens after the DLP ends?

Maintenance becomes the owner's responsibility, apart from HDB's longer warranties. Defects that existed but were not reported are harder to pursue, and you should take legal advice on any claim outside the DLP. Ongoing inspection duties are set out in our building inspection hub.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly. For an engineer's view on cracks, leaks or movement in a new home, consult a professional engineer. WhatsApp +65 9342 7551. Last reviewed: November 2026.