Demolition in Singapore: The Complete Guide to Rules Process and Engineering
Demolition in Singapore is building works under the Building Control Act 1989: taking down a building, or any structural part of one, needs structural plans approved by the Building and Construction Authority (BCA) and a permit before work starts, unless the work is listed as insignificant building works in the First Schedule of the Building Control Regulations 2003. The plans are prepared by a Qualified Person (QP), who for structural plans must be a Professional Engineer (PE) in the civil or structural discipline. This guide sets out the rules, the process, the engineering and the agencies involved, with links to a detailed article on each part.
What does demolition involve?
Demolition is an engineered sequence of nine linked activities, each with its own rule and its own responsible party.
Pre-demolition survey: A survey of the site, the structure and its surroundings carried out before any work begins. It establishes how the building stands up, what services run through it and what could be affected next door.
Asbestos and hazardous materials: An asbestos survey is required before building work in any building built before 1 January 1991. Asbestos must be removed by an approved asbestos-removal contractor before the building is demolished.
Structural appraisal: The Professional Engineer's inspection of the exposed structural frame. For buildings more than 5 storeys high or more than 40 years old, BCA requires it after soft stripping and before the permit is issued.
Demolition plan and method statement: The drawings and written sequence showing how the structure is taken down stage by stage. A Qualified Person prepares the demolition plan for BCA, and the method statement must be prepared by a Professional Engineer.
BCA plan approval and permit: Structural plan approval followed by a permit to carry out structural works. The permit is applied for jointly by the developer, the QP and the builder.
Protection of neighbours and public: Hoardings, covered walkways, catch platforms, catch fans, exclusion zones and monitoring. These are designed into the plan before work starts.
Sequence and temporary supports: Work proceeds from the top down, and props, shores or braces are installed wherever removing one element would leave another unstable.
Debris and recycling: Debris is limited on each floor, moved through planned routes and sent for recycling. Singapore recycled 99% of its construction and demolition waste in 2025.
Site clearance and records: Disused sewers are sealed with PUB's approval, services are disconnected, and as-built records are submitted.
Is demolition building works that needs BCA approval?
Yes. The Workplace Safety and Health (WSH) Council's advisory of 26 March 2025 states that all demolition works, except those in the First Schedule of the Building Control Regulations 2003, require approval of the structural plans and a permit from BCA before starting work. The Fifth Schedule of the same Regulations sets the performance requirement: demolition works shall be carried out safely and without impairing the stability of any other part of the building or another property.
The exemptions are narrow. The First Schedule covers demolition of a non-load bearing wall (item (p)), an opening in a non-load bearing wall (item (o)), removal of a timber or steel loft (item (w)) and demolition of a suspended lightweight false ceiling (paragraph 4A). Carrying out building works without approved plans or a permit carries a fine of up to $200,000, imprisonment of up to 2 years, or both. Which route applies to which job is set out in types of demolition submission, and the exempt works in insignificant building works and hacking versus demolition.
What survey and structural appraisal are required before demolition?
For a building more than 5 storeys high, or more than 40 years old, the QP must carry out a structural appraisal after soft stripping and submit a declaration and a structural appraisal report with the permit application. This comes from BCA circular APPBCA-2022-12 of 1 September 2022, which applies where the first structural plan is submitted on or after 1 November 2022. Landed houses are excluded from the 40-year rule.
Soft stripping means removing all fixtures and fittings, partitions, ceilings and internal claddings so the structure can be seen. The appraisal report must, among other things:
Identify weaknesses, defects, deterioration or damage in the structural elements.
Address structures without redundancy or in tension, such as cantilevers, hanging columns and transfer structures.
Address timber and masonry structures.
Certify that the demolition works plans remain adequate, or propose additional measures.
For buildings more than 40 years old, or where concrete strength or quality is in doubt, certify that appropriate tests such as core tests have been done.
For other buildings, the circular says the QP should still appraise the structure and confirm that the as-built plans match the actual layout before applying for the permit. The step-by-step sequence is in the demolition process, and surveys of neighbouring buildings in impact assessment and pre-construction surveys.
What are the asbestos rules?
An asbestos survey is required for any building work, including demolition, in a building built before 1 January 1991. The Ministry of Manpower (MOM) states this in its asbestos survey guidance, and the approved asbestos-removal contractor must notify MOM at least 1 week before removal starts, with the plan of work and the survey result. The detail is in asbestos and hazardous materials before demolition.
What are the demolition plan and the method statement?
The demolition plan is the package submitted to BCA; the method statement is the part that fixes the sequence. The WSH Council's March 2025 advisory lists the contents of a demolition plan as the site plan, building layout plan, work scope, machinery and tools, demolition procedure and method, supervision plan and debris management plan. Its alert of 23 June 2023 states that a demolition method statement must be prepared by a Professional Engineer.
BCA's Approved Document requires demolition works to conform to SS 557, the Singapore Standard Code of Practice for Demolition, which calls for a demolition plan based on a detailed survey and supported by a stability report with calculations. See demolition method statement and demolition plan and who can sign a PE endorsement for demolition and hacking.
How do BCA plan approval and the permit work?
A QP who is a PE in the civil or structural discipline applies for structural plan approval, and the developer, QP and builder then apply jointly for the permit. BCA's structural plan submission page gives a processing time of 7 working days for plans without Accredited Checker certification and 7 working days for the permit. Demolition of any building or structure is listed in the Fourth Schedule of the Regulations as not requiring an Accredited Checker's certificate.
Under CORENET X, demolition ahead of a new development is a joint submission to BCA and the Urban Redevelopment Authority (URA), and BCA approves it only where URA has approved the demolition or authorised the redevelopment. CORENET X is mandatory for new projects of 30,000 sqm gross floor area and above since 1 October 2025 and 5,000 sqm and above from 1 October 2026. The submission itself is covered in demolition submission in Singapore.
How are neighbours and the public protected?
Protection is part of the approved plan. Annex C of BCA's 2022 circular says that where debris may fall onto public areas or neighbouring property, protective hoarding or catch fans of adequate strength should be erected, or a temporary closure sought. Where a machine works from the ground outside the building, such as a high-reach machine, it must operate with a minimum clear space of half the remaining building height.
For landed housing projects, BCA's permit page requires the builder to conduct pre-construction surveys and notify neighbours before construction. The National Environment Agency (NEA) prohibits work at sites within 150 m of residential buildings and noise-sensitive premises from 10 pm on Saturday to 7 am on Monday, and from 10 pm on the eve of a public holiday to 7 am on the day after, unless a permit has been issued.
What sequence and temporary supports are required?
Demolition proceeds from the highest floor downwards, floor by floor, with the remaining structure kept stable at every stage. BCA's 2022 circular asks the QP to review, for top-down demolition by machines placed on the building:
The location of openings for the steel ramp.
The number of layers and spacing of steel props.
The demolition sequence for each floor and the method for each structural element.
Safety zones for machines near the building edge and floor openings.
The maximum height of debris allowed on each floor.
Separate method statements for prestressed beams or slabs, precast structures and structures with limited load transfer capability.
The WSH Council adds that horizontal beams should be demolished before structural columns in complex structures, and that temporary supports must be strong enough to prevent an uncontrolled collapse.
What happens to the debris?
Almost all of it is recycled. NEA's waste statistics record 1.15 million tonnes of construction and demolition waste generated in 2025, of which 1.144 million tonnes, or 99%, was recycled. In 2024 the figures were 708,000 tonnes generated and 706,000 tonnes recycled, also 99%. Asbestos waste is handled separately through a licensed toxic industrial waste collector. More figures are in demolition statistics in Singapore, and the direction of travel in the future of demolition.
What does site clearance involve?
Site clearance means removing the substructure and services in a controlled way and recording what is left in the ground. PUB's standard requirements of April 2023 say the QP must submit a plan of the sewerage system to be discontinued, that no sewer, manhole or inspection chamber may be demolished or grouted without PUB's approval, and that the as-built drawings must show how the sewers were abandoned and where the watertight seals are.
Who regulates what in a demolition project?
BCA regulates the structural safety of the demolition; eight other bodies regulate what surrounds it.
BCA: structural plan approval, permit, QP supervision, site supervisors and builder licensing under the Building Control Act 1989.
MOM and the WSH Council: worker safety under the WSH Act, including the permit-to-work system required for demolition under the WSH (Construction) Regulations 2007, and asbestos surveys and removal.
NEA: construction noise limits, the no-work rule on Sundays and public holidays, and asbestos waste disposal.
URA: planning permission for the redevelopment, joint approval of demolition under CORENET X, and Conservation Permission for all works to conserved buildings.
HDB: approval before any wall in a flat is demolished or altered, and renovation applications for HDB shops.
JTC: landowner's consent for works on JTC premises. Its plan consent guide requires a no-objection email from JTC's Customer Engagement Officer for demolition cases.
PUB: approval before sewers and sanitary drain-lines are sealed or abandoned.
LTA: works near rail lines. The railway protection zone extends 40 m from the outermost edge of the railway; see building near MRT lines.
Utilities: JTC's site return guidelines for lessees require checks with PUB, SP PowerGas, SP PowerGrid and IMDA on existing services before demolition, and a licensed cable detection worker to confirm there are no live cables.
Management corporations (MCSTs) control renovation inside strata lots under the Building Maintenance and Strata Management Act.
What changed recently?
The rules have been tightened several times since 2022, and the code of practice has been replaced.
1 November 2022: BCA's enhanced requirements (circular APPBCA-2022-12, issued 1 September 2022) took effect. Soft stripping, a QP's structural appraisal, a declaration and a structural appraisal report became requirements for buildings more than 5 storeys high or more than 40 years old.
1 March 2023: BCA and URA issued a joint circular on works to or near conserved buildings, asking for demolition sequences that use appropriate equipment such as handheld tools to minimise vibration, with shoring where load-bearing walls or key bracing members are removed.
23 June 2023: the WSH Council issued an alert after a wall segment at a demolition site collapsed onto a pedestrian walkway on 15 June 2023.
26 March 2025: the WSH Council issued an advisory after two fatal demolition accidents in the second half of 2024, on 1 November and 5 December. It notes three other fatal demolition-related accidents since June 2022.
22 April 2026: URA announced fines of $250,000 and $150,000 for unauthorised works, including demolition, to a conserved shophouse. URA described it as the first prosecution of its kind since the Planning Act was amended in 2017.
2 June 2026: BCA circular APPBCA-2026-09 adopted SS 557:2026, which supersedes SS 557:2010.
1 December 2026: compliance with SS 557:2026 is expected for demolition plan submissions on projects whose planning permission application is made to URA on or after this date. The new edition adds exclusion zones and safe working spaces, guidance for PPVC, mass engineered timber and marine structures, precautions for prestressed and post-tensioned structures, and real-time dust and vibration monitoring in high-density areas.
We found no demolition-specific BCA circular newer than APPBCA-2026-09 on BCA's circulars page when this guide was reviewed.
When do you need an engineer?
You need a Professional Engineer whenever a structural element is removed, and often before that, to establish that an element is not structural. In practice a PE is involved when:
A building or a structural part of it is demolished: the QP prepares and submits the plans and supervises.
A method statement for demolition is needed: it must be prepared by a PE.
A condominium owner hacks anything other than floor tiles: BCA advises MCSTs to require a PE's certification that no structural works are involved.
An HDB owner demolishes non-load bearing reinforced concrete elements: HDB requires a PE for civil or structural works to supervise.
Machines or debris are placed on suspended floors, or props are needed: these are engineering checks.
Reinforcement bars are exposed during hacking: work stops and a PE assesses.
See PE endorsement for renovation and the main guide to PE endorsement in Singapore. For the reasons buildings come down at all, see why buildings are demolished in Singapore, and for the points owners most often miss, 12 things building owners do not know about demolition.
What goes wrong?
Unplanned collapse is the recurring failure, and it usually follows a sequence that was not engineered or not followed. The WSH Council's 2025 advisory describes a worker hacking a concrete wall alone at a private residence who died when the wall collapsed on him, and an excavator operator killed when part of a reinforced concrete structure toppled onto the cabin. The common threads are no stability check of adjacent elements, demolition from the bottom up, missing props, and workers devising their own procedures. BCA's published enforcement list also records builders warned in 2025 for hacking works carried out without approved plans.
FAQ
Is a permit needed to demolish a building in Singapore?
Yes. Structural plan approval and a permit from BCA are needed before work starts, unless the work is insignificant building works under the First Schedule of the Building Control Regulations 2003.
Who submits the demolition plan to BCA?
A Qualified Person. For structural plans this is a Professional Engineer in the civil or structural discipline with a valid practising certificate.
Does demolition need an Accredited Checker?
No. Demolition of any building or structure is listed in the Fourth Schedule of the Regulations as not requiring an Accredited Checker's certificate.
How long does BCA take to approve demolition plans?
BCA's stated processing time is 7 working days for structural plans without Accredited Checker certification and 7 working days for the permit, after complete documents are submitted.
Which code of practice applies to demolition?
SS 557, the Code of Practice for Demolition. SS 557:2026 supersedes SS 557:2010, and BCA expects compliance for projects whose URA planning application is made on or after 1 December 2026.
Do I need approval to hack a non-load bearing wall?
Not from BCA: it is insignificant building works. HDB approval, MCST approval or a landlord's consent may still be needed, and someone competent must confirm the wall is not structural.
Is an asbestos survey compulsory before demolition?
Yes, for buildings built before 1 January 1991.
Sources
Building Control Regulations 2003, First, Fourth and Fifth Schedules (Singapore Statutes Online)
BCA circular APPBCA-2026-09, 2 June 2026: Adoption of SS 557:2026
BCA and URA circular APPBCA-2026-12, 23 July 2026: CORENET X implementation
BCA and URA joint circular, 1 March 2023: A&A works to or near conserved buildings
URA media release, 22 April 2026: Fines for unauthorised works to a conserved shophouse
WSH Council advisory, 26 March 2025: Demolition workplace fatal injuries in 2H2024
WSH Alert, 23 June 2023: Worker pinned by collapsed structure
PUB: Standard requirements for abandoning of disused sewerage system, April 2023
JTC: Site return guidelines for demolition, earthworks, turfing and as-built survey, July 2020
BCA advisory to MCSTs on control of renovation works, 14 January 2014
CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including demolition plan endorsement and BCA submissions. WhatsApp +65 9342 7551. Last reviewed: November 2026.