Demolition Method Statement and Demolition Plan: What a Professional Engineer Endorses
Updated: Nov 12
A demolition plan is the engineered set of drawings and procedures that shows how a structure will be taken down, stage by stage, without any part collapsing unintentionally. In Singapore, the Workplace Safety and Health (WSH) Council states that a demolition method statement must be prepared by a Professional Engineer (PE), and that a Qualified Person must prepare the detailed demolition plan submitted to the Building and Construction Authority (BCA). What the PE endorses is the stability of the building at every stage of the sequence, not only the end result.
What is the difference between a demolition plan and a method statement?
The demolition plan is the whole package; the method statement is the part of it that sets out the sequence and approach. The WSH Council's March 2025 advisory lists the contents of a demolition plan as:
Site plan and building layout plan.
Work scope.
Machinery and tools required.
Demolition procedure and method.
Supervision plan.
Debris management plan.
The Council's Technical Advisory for Demolition adds that the method statement should clearly indicate the sequence of demolition, the approach to demolition, and the elements that require specialised methods of removal. Singapore Standard SS 557, the Code of Practice for Demolition, covers the demolition plan together with a stability report. How the plan reaches BCA is covered in our guide to the demolition submission.
What does the Professional Engineer assess before writing the plan?
The PE first establishes how the building actually stands up. The WSH Council's alert of 23 June 2023 says the method statement must ensure that, before and during demolition, the stability of the walls, ceilings, slabs, beams and all other structures adjacent to the part being demolished is determined, taking into account the different designs and internal elements of each portion of the structure.
BCA's circular APPBCA-2026-09 of 2 June 2026, which adopts SS 557:2026, describes two steps in that appraisal:
Soft stripping is undertaken to fully expose the structural framework so that the PE can conduct a detailed structural appraisal.
For buildings more than 40 years old, or where there are concerns about the strength or quality of the concrete, suitable tests are carried out to verify structural integrity.
The Technical Advisory also calls for engineering surveys of existing services and of hazardous substances, which is where the asbestos survey fits in.
What sequence should a demolition method statement follow?
The sequence must never leave the remaining structure unstable. The WSH Council's guidance is specific:
Adopt a progressive top-down approach for wall demolition, and hack large wall segments into smaller sections.
For complex structures, demolish horizontal beams before structural columns, in a controlled manner.
Identify the collapse zone, and demolish in a direction that makes each piece land inside it, however many excavators are used.
Check that no person or equipment is in the collapse zone before each stage begins.
After the Tanjong Pagar collapse of 15 June 2023, BCA and MOM said that demolition must be properly planned, with the sequence detailed and the work proceeding from the top down to reduce the risk of large structures collapsing. Partial demolition is harder than total demolition: the part that remains may have relied on the part being removed for support or bracing, so the PE has to check the retained structure as a new structure in its own right.
When are temporary supports and propping needed?
Temporary supports are needed wherever removing one element would leave another unstable. The Technical Advisory says adequate shores or braces should be installed where demolition would render floors, walls and other structural elements unstable, and the 2025 advisory adds that supports must be designed to be strong enough to avoid an uncontrolled collapse if the structure being supported becomes unstable. The advisory's own case study shows the consequence of omitting them: a roof slab resting on brick walls collapsed onto a worker after the walls were largely demolished without props. Propping is a designed temporary structure; see our guide to temporary structure endorsement.
Can excavators and debris be placed on the floor slabs?
Only within a safe working load determined by a PE. The Technical Advisory states that the safe working load of the floors, taking into account debris accumulation, the weight of machinery and other anticipated dead and live loads, should be determined by a Professional Engineer, and that floors must not be loaded beyond it. Its practical controls are:
Limit the accumulation of debris on each floor.
Use properly designed ramps, such as steel ramps, to move machines between floors. Ramps formed from demolition debris may overload the floor.
Lower machines by mobile crane, or by another method proposed by a PE.
The checks are the same in principle as those in our article on machine foundations and floor loading, and crane lifts of demolition machines are covered under lifting plans and crane foundations.
How are the public and adjoining properties protected?
Protection is designed into the plan, not added on site. The Technical Advisory calls for:
Hoardings and covered walkways, provided together with catch platforms, to guide pedestrians and protect them from falling debris.
Catch platforms where exterior walls or roofs are being demolished.
Removal of glass and cladding on external walls before demolition starts.
Capping, diverting or protecting services and utilities before demolition starts.
A debris management system covering movement of debris from floor to floor, the holding area, transport and disposal.
SS 557:2026 adds exclusion zones and safe working spaces (clause 7.2.4) and real-time dust and vibration monitoring in high-density areas. For neighbours, see our guides to pre-construction surveys, instrumentation and monitoring and PE endorsement for hoardings.
Which authority and regulation governs the demolition plan?
Two regimes apply at once: building control and workplace safety.
BCA, Building Control Act and Building Control Regulations 2003: structural plan approval and a permit for demolition involving structural elements, with supervision by a Qualified Person. Demolition does not need an Accredited Checker's certificate (Fourth Schedule, item (l)).
MOM, WSH (Construction) Regulations 2007: Part X covers demolition, and a permit-to-work system is required for demolition work. The Technical Advisory notes that the permit-to-work is typically issued floor by floor.
MOM, WSH (Risk Management) Regulations: the contractor's risk assessment.
SS 557:2026: BCA expects compliance for demolition plan submissions on projects whose planning permission application goes to URA on or after 1 December 2026.
Supervision roles on site are explained in our article on site supervision for structural works.
What goes wrong when the plan is weak or ignored?
Unplanned collapse is the recurring failure. On 15 June 2023 a wall segment on the second storey of a building under demolition in Tanjong Pagar collapsed onto the pedestrian walkway beside the hoarding; The Straits Times reported the reinforced concrete wall as about 10 m long and 3.8 m high. On 5 December 2024, the WSH Council reports, part of a reinforced concrete structure being broken up by two excavators toppled onto one excavator's cabin. The lessons the Council draws are consistent:
No stability check of the elements next to the one being removed.
Demolition from the bottom up, or of supports before the elements they carry.
No props where the sequence needed them.
Workers devising their own procedures instead of following the method statement.
Supervisors not confirming the collapse zone is clear.
Under the WSH Act, the Council notes, first-time corporate offenders face a maximum fine of $500,000, and individuals a maximum fine of $200,000, imprisonment of up to 2 years, or both.
FAQ
Who prepares a demolition method statement in Singapore?
A Professional Engineer. The WSH Council's alert of 23 June 2023 states that a demolition method statement must be prepared by a PE, and the detailed demolition plan submitted to BCA is prepared by a Qualified Person.
Is a contractor's method statement enough?
No. The contractor's safe work procedures and risk assessment sit alongside the engineer's plan; they do not replace the structural appraisal, sequence and temporary works design.
Does a demolition plan need an Accredited Checker?
No. Demolition of any building or structure is listed in the Fourth Schedule of the Building Control Regulations 2003 as not requiring an Accredited Checker's certificate.
Can a mini excavator work on an upper floor during demolition?
Only if a PE has determined that the floor's safe working load covers the machine, the debris and other loads, with propping where needed.
Which code of practice applies to demolition?
SS 557:2026, Code of Practice for Demolition, which supersedes SS 557:2010.
Sources
WSH Council advisory, 26 March 2025: Demolition workplace fatal injuries in 2H2024
WSH Alert, 23 June 2023: Worker pinned by collapsed structure
BCA circular APPBCA-2026-09: Adoption of SS 557:2026 Code of Practice for Demolition
Singapore Standards eShop: SS 557:2026 Code of practice for demolition
Building Control Regulations 2003, Fourth Schedule (Singapore Statutes Online)
BCA advisory on control of renovation works, 14 January 2014
Stomp (The Straits Times): Tanjong Pagar building demolition site collapse
CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including demolition plan endorsement and temporary structure endorsement. To discuss a demolition plan, WhatsApp or call +65 9342 7551. Last reviewed: November 2026.