Demolition in 2027 Under the New Code: What Changes on Site

Nov 12
4 min read

The new code is SS 557:2026, the revised Singapore Standard Code of Practice for Demolition, which BCA adopted on 2 June 2026 and which supersedes SS 557:2010. BCA expects compliance for demolition plan submissions on projects whose planning permission application is made to URA on or after 1 December 2026, so demolition planned for 2027 should be prepared to this edition.

Written in November 2026 from published rules; check the linked official sources for updates.

Which edition applies to your project?

Check the date of the URA planning application, not the date of demolition. BCA's circular APPBCA-2026-09 sets the trigger as a planning application made to URA on or after 1 December 2026 and encourages QPs and builders to use the new edition earlier. We found no published rule on projects that applied before that date, so confirm the position with your Qualified Person (QP) and with BCA. See demolition submission in Singapore.

Change list by site stage

Each item gives what changes, who it affects and the rule or source.

  1. Soft stripping first. SS 557:2026 requires soft stripping, the removal of finishes, fittings and non-structural elements, to fully expose the structural framework. Who: builder and PE. This follows BCA's 1 September 2022 circular (APPBCA-2022-12), under which first structural plan submissions from 1 November 2022 for buildings over 5 storeys, or over 40 years old and not a landed house, include the soft stripping details. See demolition process step by step.

  2. Appraisal before the sequence is fixed. The PE carries out a detailed structural appraisal of what the stripping exposes. For buildings more than 40 years old, or where the strength or quality of the concrete is in doubt, suitable tests verify structural integrity. If the plans do not match the actual layout, the QP submits amendment plans. See demolition method statement and plan.

  3. Machines and buffer zones. The code addresses high-reach machines and their safety buffer zones. The 2022 circular lists what the plan must review for top-down machine demolition: steel ramp openings, layers and spacing of steel props, sequence for each floor, safety zones near edges and openings, and maximum debris height on each floor. A machine on a suspended floor still needs a PE floor loading check.

  4. Exclusion zones. Exclusion zones and safe working spaces are introduced (clause 7.2.4). Who: builder and site supervisors.

  5. Prestressed and post-tensioned structures. The code adds precautions, including for the hazards of tendon de-tensioning. The 2022 circular already asks for separate method statements for prestressed beams or slabs and precast structures.

  6. New structure types. There are specific guidelines for Prefabricated Prefinished Volumetric Construction (PPVC), mass engineered timber (MET) and marine-based structures.

  7. Dust and vibration records. Real-time dust and vibration monitoring is mandatory for demolition in high-density areas. Noise control is aligned with SS 602:2025. See instrumentation and monitoring.

  8. Machines in place of people. The WSH Council's advisory of 26 March 2025 told companies to consider demolition robots or remotely operated machines for high-risk work. This is encouraged, not mandated. See future of demolition.

Numbers that stay the same

  • Neighbour survey zone, measured from the edge of the building: landed 10 m, up to 5 storeys 35 m, more than 5 storeys 50 m (BCA APPBCA-2015-03). The builder carries out the survey before demolition under Regulation 32(1).

  • Noise near homes within 150 m of residential buildings: 75 dBA averaged over 12 hours from 7am to 7pm, and 90 dBA over any 5 minutes (NEA).

  • No-work rule: sites within 150 m of residential or noise-sensitive premises may not work from 10pm on Saturday to 7am on Monday, or from 10pm on the eve of a public holiday to 7am on the day after, without a permit (NEA).

  • Asbestos survey: required for buildings built before 1 January 1991 (MOM). See asbestos before demolition.

What has not changed

Demolition still needs BCA structural plan approval and a permit unless it is a First Schedule exemption, such as a non-load bearing wall under item (p). The plan is prepared and submitted by a QP who is a PE in the civil or structural discipline, not by the contractor. No Accredited Checker is needed, because item (l) of the Fourth Schedule lists demolition of any building or structure. BCA's stated times, as published at November 2026, are 7 working days for structural plans without AC certification and 7 working days for the permit. Under CORENET X, demolition ahead of redevelopment is a joint submission to BCA and URA. See hacking versus demolition and types of demolition submission.

Common mistakes

  • Using the date of demolition instead of the URA application date to decide the edition.

  • Letting the contractor's method statement replace the QP's demolition plan and structural appraisal.

  • Stripping out before the plans show the soft stripping details, where the 2022 circular requires them.

  • Booking a high-reach machine without a buffer zone or a floor loading check.

  • Leaving the asbestos survey until after the contract is awarded.

FAQ

Is SS 557:2026 already in force?

BCA adopted it on 2 June 2026 and expects compliance from 1 December 2026 for projects whose URA planning application is made on or after that date.

Does the new code need an Accredited Checker?

No. Demolition remains in the Fourth Schedule list of minor building works that need no AC certificate.

Are demolition robots now compulsory?

No. The WSH Council advises companies to consider them for high-risk work.

Does a house demolition need the 40-year tests?

The tests apply to buildings more than 40 years old, or where concrete quality is in doubt. Your PE decides the scope.

How much demolition waste is recycled?

NEA reports that 99% of construction and demolition waste was recycled in every year from 2015 to 2025. See demolition statistics.