Types of Demolition Submission in Singapore and Which One Applies to You

Nov 12
8 min read

There is no single "demolition permit" in Singapore. Which submission applies depends on two questions: is a structural element being removed, and who else has a say over the building. Removing structure needs structural plans approved by the Building and Construction Authority (BCA) and a permit, submitted by a Qualified Person (QP); removing a non-load bearing wall needs no BCA approval, but the Urban Redevelopment Authority (URA), HDB, JTC or a management corporation (MCST) may still have to approve. This article covers nine situations: who submits, what approval is needed and which documents are involved.

How do you tell which demolition submission applies?

Start with the element, then the building. Three checks settle most cases:

  1. Is any beam, column, slab, load-bearing wall or other structural element being removed or cut? If yes, BCA structural plan approval and a permit are required.

  2. Is the work on the list of insignificant building works in the First Schedule of the Building Control Regulations 2003? If yes, no BCA plan approval or permit is needed.

  3. Who is the landlord, strata body or planning authority? HDB, JTC, the MCST and URA each have their own approval, which applies whether or not BCA's does.

The Workplace Safety and Health (WSH) Council's advisory of 26 March 2025 puts the first two checks in one sentence: all demolition works, except those in the First Schedule, require approval of the structural plans and a permit from BCA before starting work. The overall picture is in our complete guide to demolition in Singapore.

1. Total demolition of a building: what is submitted?

Total demolition needs demolition works plans approved by BCA and a permit to carry out structural works.

  • Who submits: a QP who is a Professional Engineer (PE) in the civil or structural discipline applies for plan approval. The developer, the QP and the builder apply jointly for the permit.

  • Approval: structural plan approval, then the permit. BCA's stated processing time is 7 working days for plans without Accredited Checker certification and 7 working days for the permit. No Accredited Checker is needed: demolition of any building or structure is listed in the Fourth Schedule of the Regulations.

  • Documents: the demolition works plans with the demolition sequence, supported under SS 557 by a stability report with calculations, and URA's planning permission or authorisation for the site.

  • Extra documents for higher-risk buildings: under BCA circular APPBCA-2022-12, where the building is more than 5 storeys high, or more than 40 years old and not a landed house, the sequence must include details of soft stripping, and the QP must submit a declaration and a structural appraisal report with the permit application.

The contents of the submission are covered in demolition submission in Singapore.

2. Partial demolition within additions and alterations: what changes?

Partial demolition is submitted as part of the structural plans for the additions and alterations (A&A), and the retained structure has to be justified as well as the part removed. BCA's enhanced requirements of 2022 apply to a building "or any part thereof", so they can apply to partial demolition too.

  • Who submits: the QP for structural works, a PE in the civil or structural discipline.

  • Approval: structural plan approval and permit.

  • Accredited Checker: BCA's structural plan page says an Accredited Checker's certificate is needed for A&A if key structural elements are materially affected. Repairs, alterations and additions that do not materially affect key structural elements are exempt under paragraph 2 of the Fourth Schedule.

See our A&A submission guide for the wider process.

3. Demolition of structural elements in a strata unit: who approves?

BCA and the MCST both approve, and the MCST comes first in practice because it controls renovation in each lot. BCA's advisory to MCSTs of 14 January 2014 states that all demolition works involving structural elements require plans approved by the Commissioner of Building Control and a permit, and must be supervised by a Qualified Person, under sections 5, 6 and 8 of the Building Control Act.

  • Who submits: a QP appointed by the subsidiary proprietor.

  • Approval: BCA plan approval and permit, plus MCST approval under the estate's by-laws. BCA's guidance for condo owners says slabs, beams, columns and walls cannot be altered without proper assessment by a Professional Engineer and the approval of the Commissioner of Building Control.

4. Non-structural hacking: is any submission needed?

No BCA submission is needed for work in the First Schedule, but a PE's certification and a landlord's or MCST's approval usually are. The relevant exempt items are demolition of a non-load bearing wall (item (p)), an opening in a non-load bearing wall (item (o)), removal of a timber or steel loft (item (w)) and demolition of a suspended lightweight false ceiling (paragraph 4A).

  • Who approves: the MCST in strata buildings, HDB in flats, the landlord in leased premises.

  • Documents in strata buildings: BCA's 2014 advisory asks MCSTs to require, for demolition of non-structural elements other than floor tiles, renovation plans endorsed by a PE in the civil or structural discipline certifying that no structural works are involved, drawn against the original approved plans, with the work done by contractors whose workers are certified by the BCA Academy.

5. Demolition of unauthorised structures: does removal need approval?

Removal follows the same test as any other demolition: if the structure being removed is outside the First Schedule, taking it down is building works that needs a QP's submission. An unauthorised structure has two lawful exits, regularisation or removal.

  • Exempt removals: a timber or steel loft, a non-load bearing wall or a suspended lightweight false ceiling can be removed without BCA plan approval.

  • Removals that need a QP: reinforced concrete extensions, structural mezzanines, roof structures and anything tied into the building frame should be assessed by a PE before removal, because taking them out can change the loads on the original structure.

  • Who else: URA for the planning position, the Singapore Civil Defence Force where fire safety works were involved, and the landlord or MCST.

BCA's published enforcement list shows the stakes: in February 2025 a renovation contractor was fined $50,000 for works carried out without a permit and approved plans. See regularisation of unauthorised building structures.

6. Demolition ahead of redevelopment under CORENET X: what is the joint submission?

Under CORENET X, demolition submitted before the new development submission is a joint submission to BCA and URA. The CORENET X submission workflows state that:

  • BCA approves the demolition only if URA has also approved the demolition or authorised the redevelopment of the site.

  • The demolition submission can be made after the first Design Gateway or Direct Submission Process submission, but approval is granted only once URA's lodgement or approval is obtained.

  • Agencies have a service level of up to 20 working days to issue written directions or approval.

CORENET X is mandatory for new projects of 30,000 sqm gross floor area and above since 1 October 2025 and 5,000 sqm and above from 1 October 2026; smaller projects may stay on CORENET 2.0 for now (circular APPBCA-2026-12 of 23 July 2026). For projects whose URA planning application is made on or after 1 December 2026, BCA expects the demolition plan to comply with SS 557:2026.

7. Conserved buildings: what does URA require?

All works to a conserved building require Conservation Permission from URA, and structural modifications also require BCA structural plan approval. The BCA and URA joint circular of 1 March 2023 asks QPs to:

  • Submit a structural investigation report endorsed by a PE as part of the planning submission to URA, covering the existing condition and any strengthening.

  • Propose a demolition sequence using appropriate equipment, such as handheld tools, to minimise vibration, with shoring where load-bearing walls or key bracing members are removed.

  • Carry out a comprehensive pre-construction survey, with instrumentation and monitoring, and check during demolition that vibration stays within review levels.

Unauthorised demolition is prosecuted. On 22 April 2026 URA announced fines of $250,000 on an individual and $150,000 on a company for unauthorised works to a conserved shophouse, including demolition of its rear facade and rear service block, with an order to reinstate the building. The maximum penalty under the Planning Act is a fine of $500,000, 12 months' imprisonment, or both.

8. HDB flats and shops: what does HDB require?

HDB's approval is needed before any wall in a flat is demolished or altered, and structural members cannot be removed. HDB's building works guidelines set these conditions:

  • Block, brick, drywall or Ferrolite partition walls may be demolished only up to the underside of the reinforced concrete beam or slab, and block or brick walls from the top down.

  • For non-load bearing reinforced concrete elements such as partition walls, party walls, stiffeners, lintols or hangers, a Professional Engineer for civil or structural works must supervise the demolition and ensure proper repair of affected structural elements.

  • If steel bars are discovered, work stops and HDB is informed immediately.

For HDB shops, HDB's renovation guide for shop tenants and owners requires the renovation application to be made by a QP through CORENET, with clearances from HDB, BCA and the Fire Safety and Shelter Department before work starts. It gives 14 working days for HDB's clearance and requires demolition workers certified by the BCA Academy. See PE endorsement for renovation.

9. JTC premises: what consent is needed?

JTC's consent as landowner is needed in addition to the authority approvals. JTC's plan consent guide says demolition cases must include a no-objection email from JTC's Customer Engagement Officer, and that JTC aims to respond within 10 working days of a complete submission.

For a lessee returning a site, JTC's site return guidelines of July 2020 require the lessee to engage a PE to study the existing structures and propose the method of demolition, to apply to URA and BCA for approval and the permit, and to supervise the works, with a resident engineer or resident technical officer on site full time if the PE cannot be. In multi-tenanted JTC buildings, a JTC fitting-out guide requires JTC's endorsement for demolition and hacking into walls, floors, ceilings and pillars. See JTC factory renovation.

Which authority governs which type?

  • BCA, Building Control Act 1989 and Building Control Regulations 2003: types 1, 2, 3, 5 and 6, and the boundary of type 4.

  • URA, Planning Act 1998: types 6 and 7, and planning permission behind types 1 and 2.

  • HDB: type 8.

  • JTC: type 9.

  • MCSTs, Building Maintenance and Strata Management Act: types 3 and 4 in strata buildings.

  • Ministry of Manpower: the WSH regime, including asbestos surveys, applies to every type.

Common mistakes in choosing the submission

  • Treating a structural wall as a partition because it "sounds hollow". The approved structural plans decide it.

  • Starting total demolition on BCA approval alone when URA has not approved the redevelopment.

  • Forgetting the enhanced requirements for buildings over 5 storeys or over 40 years old until the permit application is rejected for lack of the appraisal report.

  • Demolishing part of a conserved building first and applying for Conservation Permission afterwards.

FAQ

Do I need BCA approval to hack a wall in my condo?

Only if the wall is structural. For non-structural walls BCA advises the MCST to ask for a PE's certification that no structural works are involved.

Does partial demolition need an Accredited Checker?

Only where the A&A works materially affect key structural elements. Total demolition does not need one.

Can I demolish before URA approves my redevelopment?

Under CORENET X, BCA approves the demolition only if URA has approved the demolition or authorised the redevelopment.

Who submits for an HDB shop?

A Qualified Person, meaning a registered architect or Professional Engineer, through CORENET.

What extra documents apply to old or tall buildings?

For buildings more than 5 storeys high, or more than 40 years old and not landed houses, the QP's declaration and a structural appraisal report after soft stripping.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including demolition plan endorsement and additions and alterations. WhatsApp +65 9342 7551. Last reviewed: November 2026.