Insignificant Building Works in Singapore: What Needs No BCA Approval

Nov 11
6 min read

Updated: Nov 12

Insignificant building works are the works listed in the First Schedule of the Building Control Regulations 2003. They need neither BCA plan approval nor a permit to carry out structural works. The list was expanded with effect from 1 April 2025, but every entry carries its own size limits and conditions, and the exemption covers BCA plan approval only. URA, SCDF, the MCST or a landlord may still have a say.

What does "insignificant building works" mean in law?

The Building Control Act excludes prescribed insignificant building works from its plan approval and permit regime, and regulation 3A of the Building Control Regulations points to the First Schedule for the list. BCA puts the practical effect this way: a permit is required for all building works except insignificant building works. Works that are not on the list go through a QP submission, however minor they seem to the owner.

What is on the First Schedule list?

The entries below are taken from the current First Schedule, including those amended or added by the Building Control (Amendment No. 3) Regulations 2024 for works carried out on or after 1 April 2025. Most entries carry further conditions, so read the Schedule itself before relying on one.

Homes and interiors:

  • Creating an opening in a non-load bearing wall, sealing up a wall opening, and demolishing, restoring or reinstating a non-load bearing wall.

  • Enclosing the sides of a balcony, yard or terrace with windows and glass panels in a residential building.

  • A suspended false ceiling of lightweight material that is purely aesthetic, not accessible to any person, and whose supporting system spans not more than 6 m, and the demolition of such a ceiling.

  • Partitions up to 10 m high, subject to conditions. Outside landed houses, the partition must be of lightweight material.

  • A loft that has only timber flooring and does not exceed 5 sqm, and the removal of a timber or steel loft.

  • One-to-one replacement of a timber roof or roof covering that does not involve the roof trusses.

  • An awning, windowhood or cantilevered roof projecting not more than 1,400 mm if tiled, or not more than 3,000 mm if of lightweight material or of glass not more than 13 mm thick.

  • A single-storey shelter on the ground or on an existing reinforced concrete roof, up to 10 sqm if it has no safety barriers. In a private space within a residential building the limit is 50 sqm, subject to conditions that include beam spans of not more than 6 m, cantilevers of not more than 3 m, and sides and roof of lightweight material.

  • A single-storey lean-to extension with a roof of tiles or lighter material in a bungalow, semi-detached, terrace or linked house.

  • Boundary walls, fences and gates that are not load bearing, and any trellis.

Industrial and commercial premises:

  • A single-level platform used solely for storing goods in an industrial building, not accessible to the public, not more than 4 m high and 50 sqm in area, with no beam or slab span above 6 m and no cantilever above 3 m. The staircase or ladder serving it is also covered.

  • A plinth or base not more than 2.5 m high and not on piled foundations, used solely to support plant, tanks, equipment or machinery not more than 2.5 m high, where the space on or below it is accessible only for maintenance.

  • A pipe rack or support not more than 2,000 mm high.

  • A single-storey shed or hut of not more than 10 sqm for housing fuel tanks or mechanical or electrical equipment, and a single-storey detached booth, covered walkway, kiosk, guardhouse or bin centre at ground level of not more than 10 sqm.

  • An opening for building services in a slab, other than a cantilever slab, flat slab or prestressed element. For a slab that is not a ground slab the opening may not exceed 150 mm in diameter or on any side, and must be at least 450 mm from the edge of any existing opening.

  • Cladding, a screen wall supporting lightweight material, or a green wall, where the framing is not more than 6 m above the adjoining ground or floor, or the aggregate area on the building face is not more than 10 sqm.

Site and external works:

  • Site formation works involving excavation or filling of not more than 1,500 mm in depth or height.

  • A retaining wall or earth retaining structure that is not on piled foundations and not within 3 m of another one, with a visible height of not more than 1.5 m if built of structural steel or reinforced concrete, or 1 m for other materials.

  • Lighting masts, lattice towers and similar structures not more than 15 m high.

What do owners assume is exempt but is not?

  • Hacking a wall that carries load. The Schedule refers to non-load bearing walls, defined as walls that support no load other than their own weight. Deciding which walls those are is an engineering judgement, covered in our guide to hacking walls in HDB, condo and landed homes.

  • A mezzanine used as an office, production or retail area. The platform entry is limited to storage of goods in industrial buildings and to 4 m and 50 sqm. Anything else needs plans. See mezzanine floor approval and warehouse racking and storage platforms.

  • A retaining wall that is slightly too high, on piles, or within 3 m of another retaining wall.

  • Solid brick or concrete partitions in commercial and industrial units, which fall outside the Schedule's definition of lightweight material.

  • A new heavy machine on an existing floor. A plinth may be exempt, but the capacity of the floor beneath it is a separate question, discussed in machine foundations and floor loading.

Do other approvals still apply?

Yes. BCA states that although plan submission is not needed for insignificant building works, owners must still observe safety and good practice and check whether other authorities need to give clearance.

  • URA: planning permission or plan lodgment for changes that affect use, floor area or external form.

  • SCDF: plan approval under the Fire Safety Act 1993 for fire safety works, such as changes affecting escape routes, fire compartments or sprinklers. A partition can be exempt from BCA approval and still be fire safety works.

  • MCST: approval under the by-laws of strata developments.

  • Landlords such as JTC or HDB, where the lease or tenancy requires consent. See JTC factory renovation.

Which authority governs what?

  • BCA: the Building Control Act and the Building Control Regulations 2003, including the First Schedule.

  • URA: the Planning Act.

  • SCDF: the Fire Safety Act 1993 and the Fire Code.

  • MCST: the by-laws of the strata development.

Common mistakes

  • Reading only the headline of an entry. Most entries have several conditions that must all be met.

  • Treating the exemption as permission to skip engineering. An exempt storage platform or plinth still has to be safe for its load.

  • Building first and checking later. Carrying out building works that need approval without it is an offence under the Building Control Act, with a fine of up to $200,000, imprisonment of up to two years, or both.

  • Buying or leasing premises with existing additions and assuming they were approved. BCA advises comparing the as-built condition with the approved plans. To keep unauthorised works, the owner must engage a QP to submit plans for approval, a process described in our article on regularisation of unauthorised structures.

FAQ

Do I need BCA approval to remove a wall in my unit?

Not if the wall is non-load bearing, meaning it supports nothing but its own weight. If it carries load, plans and a permit are required. MCST or HDB rules apply separately.

Is a storage mezzanine in a factory exempt?

Only if it meets every condition of the storage platform entry, including the 4 m height and 50 sqm area limits, the span limits and no public access. SCDF, URA and landlord requirements still need to be checked.

Does a false ceiling need approval?

A suspended, lightweight, non-accessible ceiling used for aesthetic purposes, with supporting spans of not more than 6 m, is on the list. A ceiling designed to be walked on or to carry equipment is not.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, from a Professional Engineer consultation on whether works are exempt to regularisation of unauthorised works. WhatsApp +65 9342 7551. Last reviewed: November 2026.

Recent Posts

See All
Singapore Building Compliance Handbook 2027

A map of Singapore building compliance rules for 2027: PE endorsement, QP submissions, geotechnical, demolition, inspection, factories, landed houses, procurement and a dated 2027 at-a-glance list, wi

 
 
 

Comments


© 2024 CVC Engineers. All rights reserved.

bottom of page