12 Things Building Owners Do Not Know About Demolition in Singapore

Nov 12
8 min read

Demolition in Singapore is regulated building works: outside a short list of exempt items, it needs BCA approval of a demolition plan, a permit, and a Professional Engineer behind the method. Most owners find this out late, after a contractor has quoted for "hacking". The twelve facts below are the ones owners, MCSTs and tenants most often miss, each checked against the regulation, circular or advisory that states it. For the full picture, start with our complete guide to demolition in Singapore.

1. Demolition is building works and needs BCA approval and a permit

All demolition works, except those listed in the First Schedule of the Building Control Regulations 2003, require approval of structural plans and a permit from BCA before work starts. A Qualified Person (QP), meaning a registered architect or a Professional Engineer with a practising certificate, must prepare the plans, including the detailed demolition plan. The WSH Council restated this in its advisory of 26 March 2025. The permit is applied for jointly by the developer, the QP and the builder. See demolition submission in Singapore and types of demolition submission.

2. Hacking a non-load-bearing wall is exempt from BCA approval, but not from HDB or MCST approval

Demolishing a non-load bearing wall, or creating an opening in one, is insignificant building works under the First Schedule, items (o) and (p), so no BCA plan approval or permit is needed. That exemption does not remove the landlord's or the building's rules.

  • HDB flats: all demolition or alteration of walls can only be carried out after obtaining HDB's approval. Demolition of non-load bearing reinforced concrete elements must be supervised by a PE in civil or structural engineering.

  • Strata buildings: BCA's advisory of 14 January 2014 asks MCSTs to require renovation plans endorsed by a civil or structural PE certifying that no structural works are involved, before approving demolition of non-structural elements other than floor tiles.

The practical problem is knowing whether a wall is load bearing. See hacking vs demolition and insignificant building works.

3. No Accredited Checker is required for demolition

Demolition of any building or structure is listed in the Fourth Schedule of the Building Control Regulations 2003, item (l), as minor building works that do not need an Accredited Checker's certificate. This holds whatever the size of the building. It does not mean no engineer is needed: the QP still prepares and submits the demolition plan, and the engineering responsibility sits with that QP. Our article on who can sign for demolition and hacking works explains the roles.

4. The demolition method statement must be prepared by a Professional Engineer

A demolition method statement must be prepared by a Professional Engineer, as the WSH Council stated in its alert of 23 June 2023 after a wall collapsed onto a public walkway. The method statement must establish, before and during demolition, the stability of the walls, slabs, beams and other structures adjacent to the part being removed. A permit-to-work system is also required for demolition under the WSH (Construction) Regulations 2007. What the PE actually checks is set out in demolition method statement and demolition plan.

5. The neighbours' buildings must be surveyed first: 10 m, 35 m or 50 m

Regulation 32(1) of the Building Control Regulations requires the builder to carry out a pre-construction survey of adjacent buildings and structures before starting demolition. BCA's guidelines (circular APPBCA-2015-03, 30 January 2015) set the minimum survey zone, measured from the edge of the building to be demolished:

  • Demolition for landed development: not less than 10 metres

  • Demolition of a building up to 5 storeys: not less than 35 metres

  • Demolition of a building more than 5 storeys: not less than 50 metres

The builder carries out the survey in consultation with the QP, who decides whether its extent is adequate and reviews the report for pre-existing defects. If a neighbour refuses entry, the builder must survey the exterior and keep records of the attempts and the refusal. Demolition of substructure below ground water level is classified under earth retaining works. More detail is in impact assessment and pre-construction surveys.

6. Buildings built before 1 January 1991 need an asbestos survey

An asbestos survey is required for any building work, including demolition, alteration, addition or repair, in buildings built before 1 January 1991, according to MOM. The employer or principal must appoint a competent person for the survey and ensure asbestos-containing materials are removed before the building is demolished, and the occupier must ensure removal is done by an approved asbestos removal contractor. See asbestos and hazardous materials before demolition.

7. A machine on an upper floor needs a floor loading check

A floor slab was designed for its original use, not for an excavator standing on it with a pile of rubble. The WSH Council's Technical Advisory for Demolition states that the safe working load of the floors, taking into account debris accumulation and the weight of machinery, should be determined by a Professional Engineer, and that floors must not be loaded beyond it. The advisory also warns that using demolition debris to form ramps between floors may overload them; properly designed ramps, such as steel ramps, should be used. Where demolition would leave floors or walls unstable, shores or braces are needed. Temporary propping of this kind is a temporary structure in its own right.

8. Old buildings must be stripped and tested before they are taken down

Under SS 557:2026, soft stripping must be done to fully expose the structural frame so the Professional Engineer can carry out a detailed structural appraisal, and for buildings over 40 years old, or where the strength or quality of the concrete is in doubt, suitable tests must verify structural integrity. This is from BCA circular APPBCA-2026-09 of 2 June 2026, which adopted SS 557:2026 in place of SS 557:2010. Compliance is expected for demolition plan submissions where the URA planning application is made on or after 1 December 2026. The new edition also adds provisions for exclusion zones, prestressed and post-tensioned structures, and real-time dust and vibration monitoring in high-density areas.

9. A conserved building cannot be demolished without URA permission

Owners of conserved buildings must obtain conservation permission from URA before any works start, and unauthorised works can attract a fine of up to $500,000, imprisonment of up to 12 months, or both, under the Planning Act 1998. In a case URA announced on 22 April 2026, an individual and a company were fined $250,000 and $150,000 for demolishing parts of a conserved pre-war shophouse without permission, and the owner had to reinstate the building at its own cost. Over 7,200 buildings and structures are conserved, so check status before you buy or plan.

10. Noise and working hours are controlled by NEA

Construction sites, including demolition sites, must keep within NEA's permissible noise limits, and most sites near homes cannot work on Sundays and public holidays. For residential buildings less than 150 m from the site, the limits on Mondays to Saturdays are:

  • 7am to 7pm: 75 dBA averaged over 12 hours, and 90 dBA over any 5 minutes

  • 7pm to 10pm: 65 dBA averaged over 1 hour, and 70 dBA over 5 minutes

  • 10pm to 7am: 55 dBA averaged over 1 hour, and 55 dBA over 5 minutes

Under the no-work rule, sites within 150 m of residential buildings and noise sensitive premises may not work from 10pm on Saturday to 7am on Monday, or from 10pm on the eve of a public holiday to 7am on the day after, unless NEA has issued a permit. Breaching the noise regulations carries a fine of up to $40,000. Renovation noise inside HDB flats and condominiums is handled by HDB and the MCST respectively.

11. The penalties for unauthorised demolition are criminal

Carrying out building works without approved plans or a permit is an offence under the Building Control Act 1989, with a fine of up to $200,000, imprisonment of up to 2 years, or both. Safety breaches are separate: under the WSH Act, first-time corporate offenders can be fined up to $500,000, and individuals up to $200,000, jailed for up to 2 years, or both. If unauthorised works have already been done, the route back is regularisation, not silence.

12. Hiring a contractor does not transfer the owner's responsibility

Responsibility for a demolition is shared, and the owner stays in it. The BCA permit is a joint application by developer, QP and builder. BCA's survey guidelines say that where properties in the survey zone are damaged, the developer and QP should facilitate rectification before the next stage of work. In the 2026 conservation case, URA stressed that owners of conserved buildings bear responsibility for works to their buildings, and that a builder who carried out unauthorised works would also be held accountable. Strata owners should note that Dangerous Building Orders after unauthorised hacking have been served on the management corporation.

Which authority governs what in a demolition?

Six bodies have a say, and none of them covers the others' ground.

  • BCA: demolition plan approval, permit, pre-construction survey guidelines and SS 557, under the Building Control Act 1989 and Building Control Regulations 2003.

  • MOM and the WSH Council: worker and public safety, permit-to-work and asbestos, under the WSH Act and its regulations.

  • NEA: construction noise, working hours and waste.

  • URA: planning permission and conservation permission.

  • HDB: approval of works in HDB flats.

  • The MCST: approval of renovation in strata lots under the Building Maintenance and Strata Management Act.

Common mistakes

Most problems start with the word "hacking" being used for work that is really demolition.

  • Treating a wall as non-load bearing without checking the approved structural plans.

  • Starting soft strip or hacking before the permit, the neighbour survey or the asbestos survey.

  • Letting the contractor write the method statement without a PE.

  • Putting machines on suspended slabs with no floor loading check.

  • Assuming BCA exemption means HDB or the MCST need not approve.

  • Working outside NEA hours to catch up.

The correct order of steps is in the demolition process step by step.

FAQ

Do I need BCA approval to demolish a house?

Yes. Demolition of a building is building works that needs approved plans and a permit, and a QP must prepare the demolition plan.

Can I hack a wall in my HDB flat or condominium without a PE?

HDB's approval is always needed, and HDB requires a PE to supervise demolition of non-load bearing reinforced concrete elements. In strata buildings, BCA advises MCSTs to require a PE's certification that no structural element is affected.

Does demolition need an Accredited Checker?

No. Demolition is in the Fourth Schedule list of works that do not need an Accredited Checker's certificate.

How far must the pre-construction survey extend for demolition?

At least 10 m for landed development, 35 m for buildings up to 5 storeys and 50 m for buildings above 5 storeys, measured from the edge of the building to be demolished.

Is an asbestos survey compulsory before demolition?

Yes, if the building was built before 1 January 1991.

Can demolition work be done on Sunday?

Generally not for sites within 150 m of homes, unless NEA has issued a permit or the work is exempted.

When does SS 557:2026 apply?

BCA expects compliance for demolition plan submissions where the URA planning application is made on or after 1 December 2026, and encourages its use before then.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including demolition plan endorsement. WhatsApp +65 9342 7551. Last reviewed: November 2026.