Demolition Submission in Singapore: BCA Approval Demolition Plan and PE Requirements
Updated: 7 days ago
Demolishing a building, or any structural part of one, in Singapore needs structural plan approval and a permit from the Building and Construction Authority (BCA) before work starts, unless the work is listed as insignificant building works in the First Schedule of the Building Control Regulations 2003. The plans, including the detailed demolition plan, must be prepared by a Qualified Person (QP), and for structural plans that QP must be a Professional Engineer (PE) in the civil or structural discipline. This guide explains who submits, what the submission contains and which other agencies are involved.
Does demolition need BCA approval in Singapore?
Yes. The Workplace Safety and Health (WSH) Council's March 2025 advisory on demolition states that all demolition works, except those in the First Schedule of the Building Control Regulations 2003, require approval of the structural plans and a permit from BCA before starting work.
The First Schedule exemptions that concern demolition are narrow:
Demolition, restoration or reinstatement of any non-load bearing wall, item (p).
Creating an opening in a non-load bearing wall, or sealing up a wall opening, item (o).
Removal of any loft of timber or steel construction, item (w).
Demolition of a suspended lightweight false ceiling, paragraph 4A.
Anything that removes or alters a structural element is outside these exemptions. BCA's 2014 advisory to management corporations puts it plainly: all demolition works involving structural elements require plans approved by the Commissioner of Building Control and a permit, and must be supervised by a Qualified Person, under sections 5, 6 and 8 of the Building Control Act. Carrying out building works without approved plans or a permit carries a fine of up to $200,000, up to 2 years' imprisonment, or both. Our guides to insignificant building works and hacking versus demolition cover the boundary in detail.
Who submits a demolition plan to BCA?
A Qualified Person submits it, not the demolition contractor. Under the Building Control Act a QP is a registered architect or a professional engineer with a valid practising certificate, and BCA's structural plan submission page states that only a QP who is a PE in the civil or structural discipline can apply for structural plan approval.
Three parties then apply for the permit together. BCA's permit page says the application must be made jointly by the developer, the QP and the builder who will carry out the works. BCA's builder licensing page says builders carrying out building works where plans require BCA approval need a builder's licence: a Class 1 general builder may take projects of any value, and a Class 2 general builder projects of $6 million or less. See our step-by-step QP submission guide and how to check a PE's registration.
What does a demolition submission contain?
The submission is a set of demolition structural plans with a detailed demolition plan prepared by the QP. The WSH Council advisory lists what a demolition plan includes:
Site plan and building layout plan.
Work scope.
Machinery and tools required.
Demolition procedure and method.
Supervision plan.
Debris management plan.
Singapore Standard SS 557, the Code of Practice for Demolition, covers the preparation of the demolition plan and a stability report, the use of temporary supports to keep structures stable, and the control of deliberate collapse. What the engineer actually designs and checks is explained in our article on the demolition method statement and demolition plan.
Does demolition need an Accredited Checker?
No. Item (l) of the Fourth Schedule of the Building Control Regulations 2003 lists "demolition of any building or structure" among the minor building works that do not require an Accredited Checker's certificate. BCA's stated processing time for structural plans without Accredited Checker certification is 7 working days, and the permit takes a further 7 working days. Our Accredited Checker guide lists the works that do need one.
Which standard applies: SS 557:2010 or SS 557:2026?
SS 557:2026 has superseded SS 557:2010. BCA's circular APPBCA-2026-09 dated 2 June 2026 says compliance with SS 557:2026 is expected for demolition plan submissions on projects whose planning permission application is submitted to URA on or after 1 December 2026, and encourages QPs and builders to use it earlier. The circular highlights these changes:
Soft stripping to fully expose the structural framework so the PE can carry out a detailed structural appraisal, in line with a BCA circular issued on 1 September 2022.
Suitable tests to verify structural integrity for buildings more than 40 years old, or where the strength or quality of the concrete is in doubt.
Guidance for PPVC, mass engineered timber and marine structures, and for high-reach machines.
Specific precautions for prestressed and post-tensioned structures, including tendon de-tensioning.
Exclusion zones and safe working spaces (clause 7.2.4), and real-time dust and vibration monitoring in high-density areas.
Which authority governs what in a demolition project?
BCA controls the structural safety of the demolition; several other agencies control everything around it.
BCA: structural plan approval, permit, QP supervision and builder licensing under the Building Control Act.
URA: under CORENET X, demolition ahead of the new development is a joint submission to BCA and URA, and BCA approves only where URA also approves the demolition or has authorised or approved the redevelopment. Works to conserved buildings need URA's approval first; in July 2025 URA charged an owner and an individual over unauthorised demolition works at a conserved shophouse, an offence carrying a fine of up to $500,000, up to 12 months' imprisonment, or both.
MOM: Part X of the WSH (Construction) Regulations 2007 covers demolition, and a permit-to-work system is required for demolition work. The WSH (Asbestos) Regulations require an asbestos survey before demolition of buildings built before 1 January 1991.
NEA: sites within 150 m of residential buildings or noise-sensitive premises may not work from 10 pm on Saturday to 7 am on Monday, or from 10 pm on the eve of a public holiday to 7 am on the day after, without a permit. NEA also sets maximum noise levels and regulates asbestos waste disposal.
HDB and MCSTs: landlord and strata approvals for works inside flats and strata lots.
Our articles on technical agency clearances and the order of authority submissions show how these fit together.
What surveys are needed before demolition starts?
Three kinds of survey come before demolition. The WSH Council's Technical Advisory for Demolition says engineering surveys should cover structural stability, existing services and the presence of hazardous substances. An asbestos survey is required for buildings built before 1 January 1991. For landed development projects, BCA's permit page says the builder shall conduct pre-construction surveys and notify neighbours before construction; see our guide to impact assessment and pre-construction surveys.
What goes wrong in demolition submissions and works?
Most failures come from treating demolition as a contractor's activity instead of an engineered sequence. The WSH Council has recorded fatal demolition accidents on 10 June 2022, 15 June 2023, 6 December 2023, 1 November 2024 and 5 December 2024. In the 15 June 2023 case, a second-storey wall segment of a building under demolition in Tanjong Pagar collapsed onto the pedestrian walkway beside the hoarding, and BCA halted the works and said it would revoke the permit. Common mistakes are:
Starting to hack structural elements before plan approval and the permit are in hand.
Assuming a contractor's method statement replaces the QP's demolition plan.
Skipping the structural appraisal, so the sequence is designed on assumed rather than actual framing.
Forgetting URA, particularly for conserved buildings.
Leaving the asbestos survey until after the demolition contract is awarded.
FAQ
Do I need BCA approval to demolish a house?
Yes. Demolishing a house involves structural elements, so structural plan approval and a permit are needed before work starts. No Accredited Checker is required.
Can the demolition contractor submit the demolition plan?
No. The plan is prepared and submitted by a Qualified Person, and the permit is applied for jointly by the developer, the QP and the builder.
How long does BCA take to approve a demolition submission?
BCA's stated processing time is 7 working days for structural plans without Accredited Checker certification and 7 working days for the permit.
Is URA approval needed to demolish a building?
Under CORENET X, a demolition submission made before the new development submission goes jointly to BCA and URA, and BCA approves it only where URA also approves the demolition or the redevelopment.
Does hacking a non-load bearing wall count as demolition needing a permit?
No. It is insignificant building works under item (p) of the First Schedule, although HDB or MCST conditions still apply.
Sources
Building Control Regulations 2003, First Schedule and Fourth Schedule (Singapore Statutes Online)
BCA circular APPBCA-2026-09: Adoption of SS 557:2026 Code of Practice for Demolition
Singapore Standards eShop: SS 557:2026 Code of practice for demolition
WSH Council advisory: Demolition workplace fatal injuries in 2H2024
WSH Alert, 23 June 2023: Worker pinned by collapsed structure
Stomp (The Straits Times): Tanjong Pagar building demolition site collapse
URA media release, 15 July 2025: Unauthorised works to a conserved building