Asbestos and Hazardous Materials Before Demolition in Singapore: What the Law Requires
Updated: Nov 12
Before any demolition, alteration, addition or repair work in a Singapore building built before 1 January 1991, an asbestos survey is required under the Workplace Safety and Health (Asbestos) Regulations. If asbestos-containing materials are found, they must be removed before the building is demolished, by an asbestos-removal contractor approved by the Ministry of Manpower (MOM), who must notify MOM at least 1 week before removal starts. The waste then goes through a licensed toxic industrial waste collector to Semakau Landfill under National Environment Agency (NEA) rules.
Is an asbestos survey required before demolition in Singapore?
Yes, for any building built before 1 January 1991. MOM's guidance states that asbestos surveys are required for any building work, meaning demolition, alteration, addition or repair, carried out in such buildings. A survey is also required, whatever the building's age, when work involves certain materials listed in the Regulations, unless there is documented proof that the material contains no asbestos:
Cable penetration insulation.
Fire protection boards, panels, walls and doors.
Gaskets.
Refractory lining.
Sprayed insulation.
Thermal insulation of pipes, boilers, and pressure or process vessels.
The rule covers homes as well as workplaces. MOM says a homeowner renovating a house built before 1 January 1991 must carry out an asbestos survey covering all the areas undergoing renovation; areas not affected may be excluded.
Why is 1 January 1991 the cut-off date?
Because asbestos was banned in building materials shortly before that date. The WSH Council states that asbestos use in buildings was banned in 1989, and MOM says a building completed after 1 January 1991 is unlikely to contain asbestos-containing materials. Typical examples of asbestos-containing building materials named by MOM are asbestos corrugated roof sheets, ceiling boards, pipeline insulation and gaskets. There is no public register to consult: in a written parliamentary reply dated 4 February 2026, the Minister for Sustainability and the Environment said there is no central register of asbestos in buildings and that building owners are responsible for complying with the asbestos rules for their own buildings.
Who can carry out the asbestos survey?
A competent person appointed by the employer or principal. MOM describes a competent person as someone with sufficient experience and training who has completed the courses required for the work; asbestos surveyors must complete the WSQ Survey Asbestos and Other Fibres Risk Course, and MOM publishes a list of asbestos survey service providers. For a survey, the competent person must:
Collect samples for laboratory analysis.
Ensure the samples are tested by a recognised testing body.
Prepare and submit the survey report.
A walk-through is not enough before demolition. MOM states that for a refurbishment or demolition survey the surveyor must sample suspected materials throughout the building and have them laboratory tested, and that visual inspection can only rule out non-composite materials such as glass, metal or wood.
Who is allowed to remove asbestos, and what must MOM be told?
Only an MOM-approved asbestos-removal contractor may remove it. MOM lists the duties by role: the employer or principal must ensure that asbestos-containing materials are removed before buildings are demolished, and the occupier must ensure that any asbestos-removal work is undertaken by an approved asbestos-removal contractor. The notification steps are:
The approved contractor notifies MOM at least 1 week before the start of asbestos-removal work.
The notification includes the plan of work for removal of asbestos and the asbestos survey result.
The contractor's competent person prepares the plan of work, supervises the removal, and ensures that only trained personnel carry it out.
After the work, the contractor submits the asbestos waste disposal certificate and the air monitoring report to MOM.
MOM does not need to inspect the site before removal begins, but it may inspect at any time during the notified work period.
How must asbestos waste be disposed of?
Through a licensed toxic industrial waste collector, to Semakau Landfill. NEA's asbestos waste requirements are:
Asbestos materials must be securely placed in a sealed container or bag, together with contaminated disposables such as plastic sheets, tapes, clothing and vacuum filter bags.
Each container must carry a prominent label identifying the contents and warning of the hazard, for example "Asbestos - Do not inhale dust".
The outside of the container must not be contaminated with asbestos.
Vehicles must have enclosed compartments or canvas covers, and compactors must not be used.
The contractor must engage a licensed toxic industrial waste collector capable of handling asbestos waste; NEA publishes a list of approved collectors.
Containers are barged directly to Semakau Landfill, and the disposal contractor needs NEA's written permission before disposing of asbestos waste there.
Which authority governs what?
Three agencies cover three different stages of the same job.
MOM, Workplace Safety and Health (Asbestos) Regulations: the survey, the competent person, approval of asbestos-removal contractors, notification, and air monitoring.
NEA, Environmental Public Health Act and Environmental Public Health (Toxic Industrial Waste) Regulations: licensing of toxic industrial waste collectors and the packaging, transport and disposal of asbestos waste.
BCA, Building Control Act: approval of the demolition itself. The asbestos regime is separate from, and additional to, the demolition submission made by the Qualified Person.
How NEA sits among the other agencies on a development is covered in our guide to technical agency clearances.
What other hazardous materials should be checked before demolition?
Any hazardous substance left in the building should be identified before the structure is touched. The WSH Council's Technical Advisory for Demolition says the pre-demolition engineering surveys should cover structural stability, existing services and the presence of hazardous substances, and that services and utilities should be capped, diverted or protected before demolition starts. For chemical residues and other toxic industrial waste, typically in factories and laboratories, NEA requires generators to engage a licensed toxic industrial waste collector unless they treat the waste in an approved in-house process. We have not listed other substances by name here because the official sources we reviewed do not set demolition-specific rules for them.
These surveys feed directly into the engineer's demolition method statement and demolition plan: asbestos removal comes before soft stripping and structural demolition in the sequence.
What goes wrong with asbestos on demolition and renovation jobs?
Problems usually start with the survey being skipped, rushed or done unsafely. The WSH Council's Technical Advisory records a worker who went onto a roof to survey asbestos roofing before demolition and fell through a skylight when the plastic sheets gave way. Common mistakes are:
Treating a pre-1991 building as asbestos-free because nothing looks suspicious. Visual inspection is not accepted for a demolition survey.
Letting the demolition or renovation contractor take down asbestos roof sheets or ceiling boards. That is asbestos-removal work, reserved for approved contractors.
Starting demolition before the asbestos has been removed.
Notifying MOM late. The contractor must notify at least 1 week before removal starts, so the survey has to be done well before the demolition date.
Surveying only part of the building when the whole building is coming down.
Sending asbestos waste out with general demolition debris instead of sealed, labelled and through a licensed collector.
On older factories this often surfaces during JTC renovation or change of use projects, and on older homes during the works described in hacking versus demolition.
FAQ
Do I need an asbestos survey to renovate an old house?
Yes, if the house was built before 1 January 1991. MOM says the survey must cover all areas undergoing renovation.
Does asbestos have to be removed as soon as it is found?
No. MOM says intact and undisturbed asbestos-containing materials pose a very low exposure risk, but damaged materials should be removed, and materials must be removed before a building is demolished.
Can my renovation contractor remove an asbestos roof?
Not unless it is an MOM-approved asbestos-removal contractor. Taking down asbestos corrugated roof sheets is asbestos-removal work.
How much notice does MOM need before asbestos removal?
The approved asbestos-removal contractor must notify MOM at least 1 week before the start of work, with the plan of work and the survey result.
Is there a register of buildings with asbestos in Singapore?
No. The Minister for Sustainability and the Environment told Parliament in February 2026 that there is no central register; building owners are responsible for their own buildings.
Sources
MOM: Do I need to carry out an asbestos survey if I am renovating my house?
MOM: Duties of employer, principal and occupier in asbestos-related work
MOM: If I suspect asbestos materials in my house or workplace
MSE: Written reply to Parliamentary Question on asbestos in older buildings, 4 February 2026
Workplace Safety and Health (Asbestos) Regulations (Singapore Statutes Online)
CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including demolition plan endorsement and building inspections. To discuss a demolition or renovation project in an older building, WhatsApp or call +65 9342 7551. Last reviewed: November 2026.