Impact Assessment and Pre Construction Surveys for Excavation Works in Singapore

Nov 11
6 min read

Before excavation, piling, demolition or tunnelling starts in Singapore, two things must exist: a pre-construction survey recording the condition of neighbouring buildings, carried out by the builder under Regulation 32(1) of the Building Control Regulations, and an impact assessment by the Qualified Person under Regulation 33 showing that the works will not damage those buildings. BCA's guidelines set the minimum survey zone at 15 m for landed excavations and up to 90 m or nine times the excavation depth in the worst soils.

What is an impact assessment report?

An impact assessment report is the Qualified Person's assessment of how the proposed works will affect adjacent buildings, with the measures needed to prevent damage specified on the plans. BCA's framework circular describes the purpose of Regulation 33 as preventing any settlement or other movement that may impair the stability of, or cause damage to, any premises or building adjacent or in close proximity to the works.

BCA's Framework on Performance Based Impact Assessment (6 March 2024) requires the report to include:

  • The checklist for impact assessment.

  • Recommendations for measures to minimise movement or prevent damage, specified on plan at plan submission.

  • Consideration of the existing condition of the buildings as revealed by the pre-construction survey.

For how this sits within the wider submission, see ERSS submission thresholds and deep excavation in Singapore.

What is a pre-construction survey, and who must do it?

A pre-construction survey is a record of the existing condition of buildings and structures adjacent or in close proximity to the site, and the builder must carry it out before starting. Regulation 32(1), as set out in BCA's circular of 30 January 2015, applies to:

  • Demolition of any building.

  • Piling or foundation works.

  • Tunnelling works.

  • Site formation works, including excavation.

BCA's guidelines say the builder should carry out the survey in consultation with the QP. The QP decides whether the extent and scope are adequate, including whether the pre-existing tilt of buildings needs to be surveyed, then reviews the report and identifies any pre-existing structural defect.

How far must the pre-construction survey extend?

BCA's guidelines set minimum survey zones by type of work, and where two values are given the larger applies.

Excavation works, measured from the project site boundary:

  • Landed development: 15 m.

  • Non-landed development with basement, good soils: 30 m or 3 times the maximum excavation depth.

  • Soft soils such as marine clay, without fluvial sand, peat or peaty clay: 60 m or 6 times the depth.

  • Soft soils with fluvial sand, peat or peaty clay: 90 m or 9 times the depth.

Piling works, measured from the project site boundary:

  • Landed, non-displacement or small displacement piles: 10 m. Displacement piles: 20 m.

  • Non-landed, non-displacement or small displacement piles: 40 m. Displacement piles: 60 m.

Demolition works, measured from the edge of the building to be demolished:

  • Landed development: 10 m.

  • Building up to 5 storeys: 35 m.

  • Building more than 5 storeys: 50 m.

Where one site has demolition, piling and excavation, the survey covers the largest of the applicable zones. See also demolition submission in Singapore and foundation design and pile types.

How is the impact on neighbouring buildings assessed?

BCA's framework provides a default Deemed-to-Satisfy Approach for all projects and an alternative Rigorous Approach that is available only for geotechnical building works. Under the default approach the assessed building settlement must stay within these allowable values, with relative movement limited to 1:500:

  • Up to 10 mm: conserved buildings, buildings that are badly dilapidated or have pre-existing damage, buildings on mixed foundations and structures sensitive to ground movement.

  • Up to 15 mm: buildings on pile foundations or without as-built information, MRT and other major tunnels, bridges and viaducts.

  • Up to 20 mm: minor structures on driven or jacked-in piles, such as drains and single-storey substations.

  • Up to 25 mm: buildings or minor structures on shallow foundations.

The Rigorous Approach uses comprehensive numerical analysis with a structural capacity check and allows larger settlements with enhanced monitoring. It is not available for conserved buildings, buildings with pre-existing damage unless repaired first, buildings on mixed foundations, or buildings of 30 storeys or more.

What counts as damage?

BCA treats the impact categories "Negligible" and "Very Slight", with non-structural crack width below 1 mm, as equivalent to no damage. Under the default approach the QP must demonstrate that the impact category is no worse than "Very Slight".

During construction, the monitoring regime uses a Work Suspension Level set at the design value that satisfies the impact assessment, and an Alert Level at 70% of it. In the framework's workflow for the Rigorous Approach, a non-structural crack wider than 1 mm or any structural crack requires the supervising QP to stop the relevant works and inform the Commissioner of Building Control. The instruments are explained in instrumentation and monitoring for excavation works.

What are the duties of the builder and the Qualified Person?

The builder surveys and communicates; the QP assesses, specifies and monitors.

Builder:

  • Carry out the survey before works start and give neighbouring owners a copy of the report.

  • If entry is not possible, survey the exterior face of the property and keep records of the attempts to contact the owner, such as registered mail, or of the owner's refusal.

  • For landed projects, notify neighbours, obtain written consent for access, and report the status of the survey to BCA with the permit application.

Qualified Person:

  • Review the survey and identify pre-existing structural defects.

  • Specify on plan the preventive and protective measures.

  • Substantiate that affected buildings are safe and will not likely be damaged, whichever approach is used.

Where different builders carry out demolition, piling and excavation, the main project QP instructs the first builder on site to survey the largest zone. If damage occurs within one builder's scope, the developer and main project QP should agree the rectification before the next type of work begins.

Which regulation and authority governs what?

BCA administers both requirements under the Building Control Regulations 2003.

  • Regulation 32(1): pre-construction survey by the builder.

  • Regulation 33: impact assessment.

  • LTA: a separate pre-condition survey and engineering evaluation report where rail or road structures are affected; see building near MRT lines.

What can neighbours do?

A neighbour's strongest protection is the survey itself. BCA's Be Good Neighbours guide says the report can be used as a reference for any future disputes or damage claims. Practical steps:

  • Allow the survey, check that existing cracks and tilt are recorded, and keep your copy.

  • Report new damage to the builder and owner promptly. BCA's guide says the owner should get the builder to rectify reported damage, and that BCA may revoke the permit for the works.

  • If it is not resolved, BCA states that it cannot intervene in or advise on private disputes, and points owners to the Community Mediation Centre and the Singapore Mediation Centre.

An independent assessment of your own building before works begin can be arranged through a building inspection.

What goes wrong

BCA introduced the minimum zones because feedback on damage showed that some cases extended beyond the survey zone builders had adopted. The recurring problems:

  • A survey zone drawn to the immediate neighbours only.

  • External photographs only, with no attempt to gain entry and no record of the attempts.

  • Pre-existing tilt not measured, so later tilt cannot be attributed.

FAQ

Is a pre-construction survey mandatory in Singapore?

Yes, for demolition, piling or foundation works, tunnelling and site formation works including excavation.

Can I refuse the survey of my home?

Yes, but the builder will then record only the exterior, which leaves you with less evidence.

How much settlement is allowed for my house?

Under BCA's default approach, up to 25 mm for a building on shallow foundations and up to 15 mm for one on piles, and less for sensitive buildings.

Are hairline cracks counted as damage?

BCA's framework treats non-structural cracks below 1 mm as equivalent to no damage.