Demolition Process in Singapore Step by Step: From Survey to Site Clearance
Demolishing a building in Singapore follows a fixed order: appoint the Qualified Person (QP) and builder, survey the building and its surroundings, deal with asbestos, obtain planning clearance, get the demolition plans approved by the Building and Construction Authority (BCA), obtain the permit, then demolish from the top down under supervision and clear the site. BCA's stated processing time is 7 working days for structural plans without Accredited Checker certification and 7 working days for the permit, but the surveys, asbestos removal and structural appraisal that come first have lead times of their own. The twelve steps, and who does each, are set out below.
Step 1: Who does the owner appoint first?
The owner appoints a QP for the structural works and a licensed builder before anything else. BCA's structural plan submission page states that only a QP who is a Professional Engineer (PE) in the civil or structural discipline can apply for structural plan approval, and that the permit is applied for jointly by the developer, the QP and the builder.
Owner or developer: appoints the team and is a joint applicant for the permit.
QP: prepares the demolition works plans, carries out the structural appraisal and supervises.
Builder: under BCA's Builders Licensing Scheme, builders carrying out building works that require plan approval need a licence. A Class 1 general builder may take projects of any value, and a Class 2 general builder projects of $6 million or less.
How to check the engineer is covered in who can sign a PE endorsement for demolition.
Step 2: What does the pre-demolition survey cover?
The pre-demolition survey covers the structure, the services and the surroundings. The Workplace Safety and Health (WSH) Council's advisory of 26 March 2025 calls for a site survey, a structural survey and a comprehensive risk assessment to ensure the structural integrity of the remaining structure at any stage of demolition.
Records: the approved structural plans are obtained and compared with what is built. See how to buy approved structural plans from BCA.
Structure: framing, spans, transfer structures, cantilevers, prestressed or precast elements and any earlier alterations.
Surroundings: party walls, adjoining buildings, public footpaths and roads.
Step 3: When is the asbestos survey done?
The asbestos survey is done before the demolition plan is finalised, because asbestos has to be removed before the building is demolished. The Ministry of Manpower (MOM) requires an asbestos survey for any building work in buildings built before 1 January 1991.
Asbestos surveyor: a competent person samples suspect materials and has them tested.
Approved asbestos-removal contractor: notifies MOM at least 1 week before removal starts, with the plan of work and the survey result, and afterwards submits the asbestos waste disposal certificate and the air monitoring report.
Step 4: What planning clearance is needed?
BCA's structural plan submission needs URA's planning permission or lodgement behind it, and under CORENET X demolition ahead of redevelopment is submitted jointly to BCA and the Urban Redevelopment Authority (URA). The CORENET X submission workflows state that BCA approves the demolition only if URA has approved it or authorised the redevelopment of the site, and that agencies have up to 20 working days to respond.
Other consents are obtained at this stage where they apply: URA's Conservation Permission, HDB's approval, the management corporation's approval and JTC's landowner consent, for which JTC aims to respond within 10 working days. The routes are compared in types of demolition submission.
Step 5: What goes into the demolition works plans?
The QP prepares demolition works plans showing the sequence, the method for each structural element, the temporary supports and the protection measures. For top-down demolition by machines on the building, BCA's circular APPBCA-2022-12 lists what must be thoroughly reviewed:
Location of openings for the steel ramp.
Number of layers and spacing of steel props.
Demolition sequence for each floor.
Safety zones for machines near the building edge or floor openings.
Maximum height of debris allowed on each floor and the location for debris removal.
Separate method statements for prestressed beams or slabs, precast structures and structures with limited load transfer capability.
Where the building is more than 5 storeys high, or more than 40 years old and not a landed house, the sequence must also include details of the soft stripping. See demolition method statement and demolition plan.
Step 6: How long does BCA plan approval take?
BCA's stated processing time is 7 working days after complete documents are submitted, for structural plans without Accredited Checker certification. Demolition of any building or structure is listed in the Fourth Schedule of the Building Control Regulations 2003 as not needing an Accredited Checker's certificate, so the shorter time applies. BCA notes that complex applications, or submissions that attract many written directions, can take longer. The submission contents are in demolition submission in Singapore.
Step 7: What are soft stripping and the structural appraisal?
Soft stripping is the removal of all fixtures and fittings, partitions, ceilings and internal claddings, and the structural appraisal is the QP's detailed inspection of the structure it exposes. For buildings covered by BCA's enhanced requirements, in force for first structural plan submissions on or after 1 November 2022, the order is:
The demolition works plans submitted to BCA include the soft stripping details.
The builder carries out the soft stripping.
The QP inspects and appraises the structural elements.
For buildings more than 40 years old, or where concrete strength or quality is in doubt, tests such as core tests are carried out.
The QP prepares the structural appraisal report and signs the declaration in Annex A of the circular.
If the plans do not tally with the actual structural layout, or are inadequate, the QP submits amendment plans for approval.
For buildings outside the enhanced requirements, the circular says the QP should nevertheless carry out a structural appraisal before applying for the permit.
Step 8: Which utilities and services are disconnected?
Services are capped, diverted or disconnected before structural demolition begins, and sewers are sealed only with PUB's approval. PUB's standard requirements of April 2023 require the QP to confirm there are no other lateral connections to the lines being abandoned, to submit a plan of the system to be closed up, and to arrange for PUB to witness the sealing or grouting.
JTC's site return guidelines for its lessees show the practical list: check with PUB, SP PowerGas, SP PowerGrid and IMDA on existing services, obtain SP PowerGrid's consent before a substation is decommissioned and demolished, arrange disconnection and removal of electricity, water and gas meters, and engage a licensed cable detection worker to confirm there are no live cables.
Step 9: How are neighbours notified and protected?
For landed housing projects, the builder must conduct pre-construction surveys and notify neighbours before construction starts. BCA's permit page lists a communication plan form for landed projects, covering notification of neighbours of the building works and the status of the pre-construction survey.
Before demolition begins, the site supervision guide published by BCA, the Institution of Engineers Singapore and the Association of Consulting Engineers Singapore asks supervisors to check that:
The existing structure is as shown in the approved plans, with discrepancies reported to the QP.
The approved demolition works plan and method statements are on site.
Protective hoarding, safety screens or netting, covered walkway, catch platform and catch fan are provided.
Sound barriers and dust screens are installed at least one storey higher than the floor being demolished.
Instrumentation and monitoring are in place.
Step 10: When is the permit issued and what is the permit-to-work?
The BCA permit is applied for jointly by the developer, the QP and the builder, and BCA's stated processing time is 7 working days. For buildings under the enhanced requirements, the QP's declaration and structural appraisal report go in with the permit application, so the permit cannot be applied for until soft stripping and the appraisal are done.
The BCA permit is not the same as the permit-to-work. Under the WSH (Construction) Regulations 2007, a permit-to-work system is required for high-risk construction works including demolition. It is the contractor's own control on site, confirming that risk controls are in place before each stage begins.
Step 11: How is demolition carried out and supervised?
Demolition begins from the highest floor and proceeds downwards, floor by floor, with supervision throughout. The WSH Council's 2025 advisory sets out the working rules:
Adopt a progressive top-down approach for walls, and hack large wall segments into smaller sections.
For complex structures, demolish horizontal beams before structural columns.
Identify the collapse zone and demolish in a direction that lands each piece inside it.
Erect temporary supports strong enough to prevent an uncontrolled collapse.
Check that no person or equipment is in the collapse zone before each stage.
Deploy only contractors, supervisors and workers who have completed suitable demolition training.
Supervision under the Building Control Act depends on project value. BCA's site supervisor requirements provide for immediate supervision by the QP, a resident engineer or a resident technical officer for building works up to $7.5 million, and full-time supervision by accredited site supervisors above that. Roles are explained in site supervision for structural works.
Step 12: What happens at site clearance and completion?
Site clearance ends with the substructure dealt with, debris removed and records submitted. PUB requires the developer or QP to show the actual manner of abandoning sewers, pipes, manholes and chambers in the as-built drawings, including the locations of all watertight seals.
Debris goes for recycling: the National Environment Agency's statistics record that 99% of Singapore's construction and demolition waste was recycled in 2025, 1.144 million tonnes out of 1.15 million tonnes generated. More data is in demolition statistics in Singapore.
Which authority governs which step?
BCA, Building Control Act 1989: steps 1, 5, 6, 7, 10 and 11.
MOM, WSH Act and its Asbestos and Construction Regulations: steps 3, 10 and 11.
URA, Planning Act 1998: step 4.
PUB and the utility licensees: steps 8 and 12.
National Environment Agency: construction noise during step 11 and waste in step 12.
HDB, JTC and management corporations: consent in step 4 for their own premises.
What goes wrong in the process?
Most delays and accidents trace back to steps done out of order.
Asbestos discovered after the demolition contractor has mobilised, because the survey was left late.
The permit application made without the structural appraisal report on a building more than 5 storeys high or more than 40 years old.
Demolition started on BCA plan approval alone, before the permit.
Workers improvising a sequence. The WSH Council's 2025 advisory followed two fatal demolition accidents in the second half of 2024.
Points owners often overlook are collected in 12 things building owners do not know about demolition, and the wider context is in our complete guide to demolition in Singapore.
FAQ
How long does it take to get approval to demolish a building?
BCA's stated processing times are 7 working days for structural plans without Accredited Checker certification and 7 working days for the permit, after complete documents. Surveys, asbestos removal, URA clearance and the structural appraisal add to this.
Can demolition start once the plans are approved?
No. A permit to carry out structural works is also required, and for buildings under the enhanced requirements the permit application needs the QP's declaration and structural appraisal report.
Who notifies the neighbours?
For landed housing projects, the builder conducts the pre-construction surveys and notifies neighbours before construction.
Who disconnects the utilities?
The owner's team arranges it with each utility. Sewers may not be sealed or abandoned without PUB's approval.
Does a small demolition job follow the same steps?
The steps scale down but the order stays. Hacking a non-load bearing wall needs no BCA approval, yet the asbestos rule, the landlord's or management corporation's approval and safe top-down working still apply.
Sources
Building Control Regulations 2003, First and Fourth Schedules (Singapore Statutes Online)
WSH Council advisory, 26 March 2025: Demolition workplace fatal injuries in 2H2024
PUB: Standard requirements for abandoning of disused sewerage system, April 2023
JTC: Site return guidelines for demolition, earthworks, turfing and as-built survey, July 2020