JTC Factory Renovation: What Consent and Submissions Are Needed

Nov 11
2 min read

Updated: 7 days ago

Most factory alterations change both the layout and the structure: a new opening in a wall, a machine on a suspended slab, an extension, a canopy, a mezzanine. On JTC land and buildings there is one more party to satisfy before any of it starts.

When JTC consent is required

JTC's consent is required for development or renovation works on JTC land and buildings, including new erection, additions and alterations, and amendments to approved works. It is required even though other authorities may also need to approve the works. Where the authorities require QP endorsement for the project, the submission must be made by a Qualified Person, who is a registered architect or engineer.

What a JTC submission contains

  • A cover letter summarising the proposed works

  • The JTC self-declaration form

  • A letter of declaration for the QP to submit on the tenant's behalf, stamped and signed by the tenant

  • An authorisation letter from the JTC tenant or lessee, if the tenant did not commission the works

  • Drawings in CAD or BIM format: site, unit, section and elevation plans, with a GFA table

Land Betterment Charge

Since 1 August 2022, Land Betterment Charge has replaced Differential Premium, Development Charge and Temporary Development Levy. Where a proposal triggers it, SLA issues a Liability Order, payable within one month of its date. Added floor area is the usual trigger, so check the GFA position before committing to a design.

The other authorities

  • URA: planning permission or plan lodgment.

  • BCA: building and structural plans, and the permit to carry out structural works. Structural plans without Accredited Checker certification are processed within 7 working days of a complete submission.

  • SCDF: fire safety works.

CORENET X has been mandatory for new projects of 30,000 sqm GFA and above since 1 October 2025, and for new projects of 5,000 sqm GFA and above from 1 October 2026. Projects below 5,000 sqm can continue to use CORENET 2.0 for now, under the BCA and URA circular of 23 July 2026.

Works with extra JTC requirements

JTC lists additional requirements for workers' dormitory conversion, diesel and flammable material storage, solar PV deployment and EV chargers.

Why architectural and structural scope should move together

The GFA table sent to JTC, the building plans sent to BCA and the structural plans have to describe the same building. When the scopes are run separately, the drawings go out of step and submissions are returned. CVC Engineers has a dedicated team to help resolve this properly. See our additions and alterations service and SCDF fire safety submission, or WhatsApp +65 9342 7551.