Deep Excavation Checklist 2027 Singapore: Every Current BCA Requirement
A deep excavation in Singapore is geotechnical building works (GBW) once it is more than 6 m deep, and then BCA requires a QP(ST), an Accredited Checker (AC), a QP(Geo) and an AC(Geo) for the plan submission. This checklist runs in the order a project meets the rules, using BCA's June 2026 geotechnical submission requirements and the ERSS requirements as updated in August 2026, where the thresholds are unchanged.
Written in November 2026 from published rules; check the linked official sources for updates.
A. Is it in scope? Depth bands
Up to 1.5 m deep: no plan approval. The limit is 1 m if the retaining structure is not reinforced concrete or steel. A pit for a pile cap, footing, sump, lift pit or trench is also exempt if it does not exceed 10 sqm in area and 2 m in depth. See insignificant building works.
More than 1.5 m and up to 4 m: a QP(ST), who must be a PE in the civil or structural discipline. No AC.
More than 4 m and up to 6 m: a QP(ST) and an AC.
More than 6 m and classified as GBW, such as a basement: add a QP(Geo) and an AC(Geo). A shaft or trench with a plan area not exceeding 10 sqm is exempt from GBW but not from the ERSS requirements.
Measure depth from where the excavation started to the final formation level. On sloping ground the heights add (H = h1 + h2). Local pits inside a basement go into the main plan. See ERSS submission thresholds.
B. Appointments
The QP(Geo) is a PE registered as a specialist in geotechnical engineering. See what a PE(Geo) does.
The AC and AC(Geo) must have no financial or professional interest in the project, and the developer appoints them and the instrumentation contractor.
The supervising QP and team must not be partners, officers or employees of the developer or builder.
Appoint a single design QP and a single supervising QP for all building works in the project, including the ERSS (BCA circular of October 2026). See site supervision roles and accredited checker.
C. Ground information
The design QP plans the investigation under Regulation 31 to Eurocode 7 and the Geotechnical Society of Singapore (GeoSS) guide. An inspection body accredited by the Singapore Accreditation Council (SAC) carries out the fieldwork.
For an ERSS deeper than 6 m, the GeoSS guide recommends one borehole every 10 to 30 m along the alignment.
The SI report follows BCA's guideline for new projects applying to URA on or after 1 March 2026: a standalone PDF plus AGS(SG) data, PE certification, SPT hammer calibration certificates and the SPT energy ratio in the log. See soil investigation.
D. Design checks
Wall deflection under Advisory Note 1/09: 0.5% of H where structures lie within H, 0.7% between H and 2H, and beyond that 0.7% (Ground Type A) or 1.0% (Ground Type B, soft clays). Alert level 70% of the limit, check level 50% in Zones 2 and 3.
Seepage cut-off in every ERSS and recharge wells where appropriate. See groundwater control.
Ground improvement may be used for soil improvement only, not as part of the retaining wall, especially a cantilever wall. The August 2026 update adds an accidental basal heave check with a factor of safety of at least 1.1 where ground improvement is used and the wall toe ends in soft soil.
Sheet pile walls: BCA's circular APPBCA-2025-29 applies from 1 June 2026. For GBW deeper than 6 m the plans must specify inspection of exposed interlocks and contingency measures. See ERSS wall types.
Diaphragm walls: the BCA and LTA circular of 9 October 2026 recommends tremie concrete with slump flow of 400 mm to 550 mm, 0.30 mm design crack width, 75 mm minimum cover and at most three layers of reinforcement.
Shafts for utility works: the circular of 19 October 2026 makes a physical retaining wall installed before excavation the default for shafts close to buildings.
E. Neighbours
Builder's pre-construction survey (Regulation 32(1)), measured from the site boundary: landed 15 m; non-landed with basement 30 m or 3 times the depth; soft soils 60 m or 6 times; soft soils with fluvial sand or peat 90 m or 9 times. The larger value applies.
Impact assessment (Regulation 33): deemed-to-satisfy settlements of 10, 15, 20 or 25 mm depending on the structure, with relative movement limited to 1:500. See impact assessment.
F. Submission and start
Submit the ERSS plans, ERSS_Annex A and the PE-certified SI report. Plan approval covers both temporary and permanent stages.
A site supervision plan goes with the permit application for works valued above S$7.5 million; smaller works keep a copy on site.
Obtain the permit and notify BCA of commencement. If you want the observational method, pre-consult BCA first (APPBCA-2019-12). See the observational method.
G. During construction
Implement ERSS_Annex C on site. The builder obtains the QP's approval before excavating past each strut level.
Monitor wall and ground deformation, strut or anchor loads and piezometric pressures, inside and outside the excavation. For sheet pile walls, place a cluster of inclinometer and piezometer every 30 to 40 m. See instrumentation and monitoring.
Submit ERSS_Annex E by e-form through CORENET by the 7th of each month, and inform BCA immediately when the alert or work suspension level is exceeded.
Stop excavation and take remedial measures if critical instruments exceed the design limit.
Treat silty water to PUB's limit of 50 mg/L total suspended solids before discharge to a public drain.
H. Completion
Submit record plans for permanent and temporary ERSS with forms C1, C2 and C3, endorsed by the QPs and ACs of the approved plans.
What has not changed
BCA's June 2026 and August 2026 reissues of its submission requirements left the 1.5 m, 4 m and 6 m thresholds unchanged. Near rail, LTA's rules sit on top; see building near MRT lines. The context is in deep excavation in Singapore and the Singapore Building Compliance Handbook 2027.
Common mistakes
Treating a 5 m basement as GBW. It needs a QP(ST) and an AC, not a QP(Geo) or AC(Geo).
Too few boreholes along the wall.
Monitoring that is read but not acted on.
Gaps in sheet pile walls and utility gaps in the wall.
Letting the contractor appoint the AC or instrumentation contractor.
FAQ
At what depth is an excavation deep?
BCA's GBW threshold is more than 6 m; an AC is already required above 4 m.
Who appoints the AC(Geo)?
The developer.
How often is monitoring reported to BCA?
Annex E is submitted through CORENET by the 7th of each month.
Does a small footing excavation need approval?
Not if the retaining structure does not exceed 10 sqm in area and 2 m in depth. BCA's example: a 6 sqm footing excavated 1.8 m deep is exempt, but one 2.1 m deep needs a submission.
Is ground improvement allowed as the wall?
No. BCA limits it to soil improvement and not as part of the retaining wall.
Sources