Instrumentation and Monitoring for Excavation Works in Singapore
Instrumentation and monitoring is the system of instruments and scheduled readings that shows whether an excavation and the buildings around it are behaving as the design predicted. In Singapore, BCA's Advisory Note 1/09 requires, as a minimum, monitoring of wall and ground deformation, strut or anchor loads and piezometric pressures, with an alert level at 70% of the allowable limit and a work suspension level at which work must stop. The Qualified Person reports the results to BCA every month and immediately when either level is exceeded.
What must be monitored during an excavation in Singapore?
BCA's Advisory Note 1/09 on Earth Retaining or Stabilising Structures (ERSS) sets the minimum: wall and ground deformation, anchor or strut loads, and piezometric pressures, monitored both within and outside the excavation.
The same note adds three specific cautions:
Strain gauges for member forces must be properly installed, calibrated and checked, because readings are affected by temperature, joints, non-uniform stresses, strut installation and preloading.
Strut forces evaluated by hydraulic jacking must be independently confirmed by a calibrated load cell.
Movement of the adjacent ground must be monitored during the installation of jet grout piles, deep soil mixing and diaphragm wall trenching, not only during bulk excavation.
Where a ground improvement layer is used as a base shear plug below formation level, the note calls for continuous monitoring of deformation. For how these requirements fit into the wider submission, see our guides to ERSS in Singapore and deep excavation and geotechnical building works.
Which instruments are used, and what does each one measure?
A typical Singapore excavation uses a combination of ground, structural and building instruments, each answering a different question about the works.
Inclinometers: lateral movement of the retaining wall or the soil behind it, measured over depth. This is the reading compared against the wall deflection limits.
Settlement markers: vertical movement of the ground surface, roads, utilities and neighbouring buildings.
Piezometers: pore water pressure in the soil, which shows drawdown or pressure build-up.
Water standpipes: the groundwater level outside and inside the excavation.
Strain gauges and load cells: forces in struts, walers and ground anchors.
Tiltmeters: rotation of adjacent buildings and structures.
Vibration meters: peak particle velocity from piling, demolition and other vibrating activities.
Crack meters: opening or closing of existing cracks recorded in the pre-construction survey.
What are the alert level and work suspension level?
Under Advisory Note 1/09, the work suspension level is the allowable maximum wall deflection, and the alert level is 70% of it. For excavations where buildings, structures or critical utilities lie in Zone 2 or Zone 3, there is also a check level at 50%.
The allowable maximum wall deflection in Table 1 of the note depends on how close existing structures are to the excavation, where H is the excavation depth:
Zone 1 (structures within H of the excavation): 0.5% of H.
Zone 2 (structures between H and 2H away): 0.7% of H.
Zone 3 (structures more than 2H away): 0.7% of H in Ground Type A (stiff clays and silts, residual soils, medium to dense sands) and 1.0% of H in Ground Type B (soft clays, silts or organic soils such as Kallang Formation, and loose fills).
The note is explicit that the limit must in any case also be set to prevent structural damage to neighbouring buildings. What each level triggers:
Check level: the designer confirms or recalibrates the design assumptions.
Alert level: updated predictions of future performance are made, to decide whether the remaining excavation needs to be re-engineered.
Work suspension level: work must be stopped and immediate measures implemented to remove any danger of injury or damage to adjoining properties. A comprehensive design review follows, and construction does not resume until remedial actions are in place.
What limits apply to neighbouring buildings?
BCA's Framework on Performance Based Impact Assessment (circular dated 6 March 2024) sets deemed-to-satisfy allowable building settlements of 10 mm to 25 mm depending on the building, with relative movement limited to 1:500. The table gives up to 10 mm for conserved buildings, badly dilapidated buildings, buildings on mixed foundations and structures sensitive to ground movement; up to 15 mm for buildings on piles or without as-built information; up to 20 mm for minor structures on driven or jacked-in piles; and up to 25 mm for buildings or minor structures on shallow foundations.
For building monitoring, the framework sets the work suspension level at the design value that satisfies the impact assessment, capped by the allowable settlement, and the alert level at 70% of the work suspension level. We explain the assessment itself in impact assessment and pre-construction surveys.
Who reviews the readings, and how often are they reported to BCA?
The Qualified Person must inform BCA of the monitoring results monthly using the ERSS Annex E form, and immediately when the alert level or work suspension level is exceeded. BCA's June 2026 ERSS submission requirements state that Annex E is submitted by e-form through CORENET by the 7th of each month, and that the Annex C site inspection and approval record is implemented on site.
On site, the Guide Book for Site Supervision Plan published by BCA, IES and ACES sets out what the supervision team does:
Witness the recording of readings by the instrumentation specialist.
Ensure readings are taken at the frequency stated in the approved plans.
Inspect ERSS works at least once a day.
Supervise excavation at least daily while readings are within the alert level, and continuously once readings have exceeded the alert level.
Under Advisory Note 1/09 the builder must also obtain the QP's approval before excavating past each strut level, using the Annex C and Annex D ground movement records. The division of duties between the QP, resident engineer and technical officers is covered in our article on site supervision for structural works.
Which authority governs monitoring?
BCA governs monitoring for building works under the Building Control Act and Regulations, and LTA adds its own requirements near rail and road structures.
BCA: Advisory Note 1/09, the ERSS and geotechnical building works submission requirements, and the impact assessment framework. Excavations deeper than 4 m need an Accredited Checker and those deeper than 6 m classified as geotechnical building works need a PE(Geo) and AC(Geo); see ERSS submission thresholds.
LTA: within the 40 m railway protection zone, the Code of Practice for Railway Protection requires an instrumentation proposal with alert and work suspension levels, weekly submission of readings, an automatic tunnel monitoring system where cumulative movement of the rail structure is expected to exceed 5 mm, and a vibration limit of 15 mm/s peak particle velocity at rail structures. See building near MRT lines.
What goes wrong with monitoring on site?
Most monitoring failures are failures of response, not of instruments. The patterns the rules are written to prevent:
Baseline readings taken too late, after wall installation or dewatering has already moved the ground.
Instruments damaged by plant and not replaced, leaving a blind section of wall.
Readings collected on schedule but not compared with the predicted value for that construction stage. Advisory Note 1/09 requires pre-determined values for each stage and strut level, not only a final limit.
Strut loads inferred from jack pressure alone, without a calibrated load cell.
Excavation continuing past the alert level without updated predictions.
FAQ
Is instrumentation and monitoring mandatory for every excavation?
Advisory Note 1/09 applies to ERSS that require plan approval. Excavations up to 1.5 m deep are generally insignificant building works that need no plan approval, as explained in insignificant building works.
What happens when the work suspension level is reached?
Work must stop, the excavation must be made safe, BCA must be informed immediately, and a comprehensive design review is carried out before construction resumes.
Who takes the readings?
An instrumentation specialist takes them, the site supervisors witness the recording, and the QP reviews and reports them.
Can a neighbour refuse access for instruments?
Yes. BCA's landed housing forms provide for the builder to request the owner's written consent for access to install monitoring instruments.
Sources
BCA Advisory Note 1/09 on Earth Retaining or Stabilising Structures
BCA Geotechnical Building Works Submission Requirements, June 2026
BCA Framework on Performance Based Impact Assessment associated with ERSS and Tunnelling Works
BCA pre-construction survey and communication plan forms for landed development
CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including ERSS submissions and structural monitoring. WhatsApp or call +65 9342 7551. Last reviewed: November 2026.