An Accredited Checker (AC) is a senior professional engineer registered with BCA who independently checks the structural design of a project and certifies it before BCA approves the structural plans. Your project needs one unless the works are minor building works listed in the Fourth Schedule of the Building Control Regulations. Works with deep excavations, tunnels or tall-building foundations also need a specialist geotechnical checker, the AC(Geo).

What does an Accredited Checker do?

Under the Building Control (Accredited Checkers and Accredited Checking Organisations) Regulations, as published by BCA, the AC must:

  • Evaluate, analyse and review the structural design in the plans, and perform original calculations to determine the adequacy of the key structural elements.

  • Verify that the key structural elements are consistent with the layout in the architectural plans.

  • Carry out a prescribed list of tasks, including checks on design loadings, software assumptions, stability and robustness, foundations, transfer beams, connections and detailing.

  • Submit a certificate and an evaluation report, with the analysis and calculations performed, to the Commissioner of Building Control.

  • Declare that the checker has no professional or financial interest in the building works.

The AC does not replace the project's Qualified Person (QP). The QP designs and submits. The AC is a second, independent engineer who re-derives the critical parts of that design. For where this sits in the wider approval sequence, see QP submission step by step.

When is an Accredited Checker required?

Regulation 12 of the Building Control Regulations provides that plans of the building works listed in the Fourth Schedule do not require an AC's certificate. Everything else does. The main entries in the current Schedule, with related BCA guidance, are:

  • Additions and alterations that materially affect key structural elements, such as strengthening works, require an AC certificate. This is stated on BCA's structural plan submission page.

  • Structural repairs, alterations and additions to an existing building that do not materially affect its key structural elements are on the Fourth Schedule list, so they do not need an AC.

  • Earth retaining and stabilising structures follow a depth scale in BCA's June 2026 guidance. Up to 1.5 m deep, no plan approval is required (1 m if the structure is not reinforced concrete or steel). Above 1.5 m and up to 4 m, a structural QP is required but not an AC. Above 4 m, an AC is required.

  • Detached, semi-detached, terraced or linked houses for residential purposes not exceeding 3 storeys, where the works involve only structures that are not covered by the other entries.

  • Shophouses not exceeding 3 storeys, counting an attic or basement floor of more than 100 sqm as a storey.

  • Single-storey buildings, sheds, covered walkways and the like where beam or roof truss spans are not more than 15 m or cantilever spans are not more than 6 m.

  • 2-storey buildings where no beam or slab span exceeds 15 m, no cantilever span exceeds 6 m, and the works involve no pre-stressed or post-tensioned construction.

  • Retaining walls and earth stabilising structures not exceeding a visible height of 4 m, and underground tanks, swimming pools and the like not exceeding a depth of 4 m.

  • Demolition of any building or structure.

  • The supporting structure of a mechanised car parking system not exceeding 10 m in height and 15 m in span, added from 1 April 2025.

The Schedule has further entries and conditions, so the structural QP should confirm the wording for any borderline case. In practice, most additions and alterations that add a floor, remove a column or transfer load to existing members, and most structural strengthening, need an AC. For a new mezzanine floor in an existing building, the answer turns on whether the existing key structural elements are materially affected. That judgement belongs to the QP and is open to challenge by BCA.

What is an AC(Geo) and when is one needed?

An AC(Geo), or specialist accredited checker, is registered to check the geotechnical aspects of geotechnical building works. BCA's guidance describes these works as:

  • Tunnelling works with a diameter, width or height of more than 2 m.

  • Excavations, and earth retaining structures for them, with a depth of more than 6 m.

  • Earthworks or other works to construct or stabilise a slope more than 6 m high.

  • Foundation works for buildings of 30 or more storeys.

For these works the submission carries four appointments: the structural QP, a geotechnical QP who is a PE(Geo), the AC and the AC(Geo). A basement excavation deeper than 6 m is BCA's own example.

Individual AC or Accredited Checking Organisation?

BCA keeps two registers. The Register of Individual Accredited Checkers states that an individual AC can only make structural plan submissions for a project of total value not exceeding $15 million. Above that value the checker must come from an Accredited Checking Organisation, which under the regulations is a firm with an AC supported by a team of professional engineers. Both registers are published by BCA and should be checked before appointment, in the same way that you would check a Professional Engineer's registration.

How long does approval take with an AC?

BCA's published service standards, counted from a complete submission, are:

  • Structural plans without AC certification: 7 working days.

  • Structural plans with AC certification: 10 days for the first submission and 14 working days for subsequent submissions.

  • Plans submitted through the CORENET X Construction Gateway: 20 working days.

These figures exclude the AC's own review, which happens before submission and depends on the size and complexity of the structure. BCA also notes that complex applications and QPs with a poor submission record take longer. See our CORENET X guide for how the gateways affect timing.

Which authority governs what?

  • Building Control Act: requires the AC's certificate for plan approval and provides for the registration of ACs, specialist ACs and Accredited Checking Organisations.

  • Building Control Regulations 2003: regulation 12 and the Fourth Schedule define the minor building works that need no AC.

  • Building Control (Accredited Checkers and Accredited Checking Organisations) Regulations: qualifications, duties and the certificate.

  • BCA: keeps the registers and processes the plans.

  • Professional Engineers Board: registers the professional engineers and PE(Geo) specialists from whom checkers are drawn.

What goes wrong

The clearest lesson comes from the viaduct collapse at Upper Changi Road East on 14 July 2017, in which one worker died and ten were injured. In Leong Sow Hon v Public Prosecutor [2020] SGHC 228, the project's accredited checker pleaded guilty under the Building Control Act to failing to evaluate, analyse and review the structural design of key structural elements. He had performed no independent calculations for the permanent corbels. The corbels were not the cause of the collapse, but the investigation exposed the missing check. He was sentenced to six months' imprisonment and the High Court dismissed his appeal, describing the checker's duty as personal and non-delegable.

More routine problems include:

  • Appointing the AC late, so that design changes arising from the check land after tender or fabrication.

  • Choosing a checker with a professional or financial link to the project, which the independence declaration rules out.

  • Appointing an individual AC on a project worth more than $15 million.

  • Assuming an addition or alteration is minor when it materially affects key structural elements.

  • Overlooking the AC(Geo) when a basement or shaft goes deeper than 6 m.

FAQ

Is an Accredited Checker the same as the QP?

No. The QP prepares and submits the design. The AC is a separate, independent engineer who checks it and certifies to BCA.

Does a landed house need an Accredited Checker?

The Fourth Schedule lists detached, semi-detached, terraced and linked houses not exceeding 3 storeys as minor building works that need no AC, provided the works involve only structures not covered by its other entries. Deep basements and retaining walls above 4 m can change the answer.

Who appoints the Accredited Checker?

Under the Building Control Act the developer appoints the AC. The AC must declare that there is no professional or financial interest in the building works.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, and also offers structural plan checking. WhatsApp +65 9342 7551 to discuss whether your works need an Accredited Checker. Last reviewed: November 2026.

Recent Posts

See All
Singapore Building Compliance Handbook 2027

A map of Singapore building compliance rules for 2027: PE endorsement, QP submissions, geotechnical, demolition, inspection, factories, landed houses, procurement and a dated 2027 at-a-glance list, wi

 
 
 

Comments


© 2024 CVC Engineers. All rights reserved.

bottom of page