ERSS Submission Thresholds in Singapore: When You Need a QP an AC or a PE Geo
The ERSS submission thresholds in Singapore are 1.5 m, 4 m and 6 m. Under BCA's June 2026 submission requirements, an excavation or earth retaining or stabilising structure (ERSS) up to 1.5 m deep needs no plan approval, one deeper than 1.5 m and up to 4 m needs a qualified person, QP(ST), one deeper than 4 m also needs an accredited checker (AC), and one deeper than 6 m that is classified as geotechnical building works also needs a QP(Geo) and an AC(Geo). The same bands apply to temporary and permanent works.
What are the ERSS depth thresholds?
There are five bands, set out in BCA's ERSS: Submission Requirements dated June 2026, which applies to all permanent or temporary building works that involve excavation or ERSS:
Up to 1.5 m deep: plan approval is not required. If the structure that retains earth is not reinforced concrete or steel, the limit is 1 m.
More than 1.5 m and up to 4 m: QP(ST). An AC is not required.
More than 4 m and up to 6 m: QP(ST) and an AC.
More than 6 m and not classified as geotechnical building works (GBW), for example excavation for a sewer manhole associated with a pipe of 2 m diameter or less: QP(ST) and an AC.
More than 6 m and classified as GBW, for example basement excavation: QP(ST) and an AC, plus QP(Geo) and AC(Geo).
BCA defines an earth retaining structure as any structure, structural system or other means used to maintain the shape of excavation during construction, earth filling or cutting. For background on wall types, see our ERSS overview.
When is no BCA plan approval needed?
No plan approval is needed for an excavation or ERSS up to 1.5 m deep, or 1 m if the retaining structure is not reinforced concrete or steel. This reflects the First Schedule of the Building Control Regulations 2003, which lists as insignificant building works a retaining wall or earth retaining structure that is not on piled foundations, is not within 3 m horizontally of another, and has a visible height not exceeding 1.5 m in structural steel or reinforced concrete, or 1 m in other materials. Site formation works with excavation or filling not exceeding 1,500 mm are also listed. More examples are in insignificant building works in Singapore.
There is one further relief for localised pits. BCA states that approval is not required for a retaining structure supporting the face of an excavation made to construct a pile cap, footing, sump, lift pit or trench, provided the structure does not exceed 10 square metres in area and 2 m in depth. BCA's worked examples show how strictly this is read:
Footing of 6 square metres, excavation 1.8 m deep: plan submission not required.
Footing of 6 square metres, excavation 2.1 m deep: plan submission required.
Footing of 12 square metres, excavation 1.8 m deep: plan submission required.
No plan approval does not mean no engineering: an exempt excavation still has to be made stable.
When is a QP enough without an accredited checker?
A QP(ST) alone is enough for an excavation or ERSS deeper than 1.5 m and up to 4 m. This matches the Fourth Schedule of the Building Control Regulations 2003, under which retaining walls and earth stabilising structures not exceeding a visible height of 4 metres are minor building works that do not need an accredited checker's certificate.
A QP(ST) here is a professional engineer in the civil or structural discipline. BCA's structural plan submission page states that only such a QP can apply for structural plan approval. The wider process is described in QP submission in Singapore.
When is an accredited checker required?
An accredited checker is required once the excavation or ERSS is deeper than 4 m. BCA's guidance puts it in one line: where the depth exceeds 4 m, a QP and an AC are required for plan submission. The AC carries out an independent check of the QP's design before submission. BCA's guidance also states that the AC shall not have any financial or professional interest in the project and shall be appointed by the developer. See accredited checker in Singapore.
When are a QP(Geo) and an AC(Geo) required?
A QP(Geo) and an AC(Geo) are required when the excavation or ERSS is deeper than 6 m and the works are classified as GBW. BCA's GBW submission requirements list GBW as tunnels more than 2 m in diameter, width or height, excavations and earth retaining structures more than 6 m deep, slopes more than 6 m high, and foundations for buildings of 30 or more storeys.
Not every excavation deeper than 6 m is GBW. BCA exempts an excavation for a shaft or trench with a plan area not exceeding 10 square metres, such as a diaphragm wall trench or a bored pile excavation, although the ERSS submission requirements still apply to it. The roles are explained in what a PE(Geo) does and the process in deep excavation in Singapore.
How is the depth measured?
Depth is measured from where the excavation starts to the final formation level. BCA's guidance adds several points that often change the band:
On sloping ground the heights are added, so H = h1 + h2.
Localised pits, such as lift pits within a basement excavation, are submitted as part of the main excavation ERSS plan.
Do temporary and permanent ERSS follow the same rules?
Yes. BCA's table applies to all permanent or temporary building works. For GBW, plan submission is required for both the temporary and the permanent stages. Where a temporary retaining wall also serves as the permanent basement wall, BCA requires the temporary wall and the permanent basement structure to be submitted under the same structural submission as GBW, not as piling. A basement structure or box culvert built inside a separate temporary support system is not itself GBW. Other temporary works are covered in temporary structure endorsement.
What does an ERSS submission contain?
An ERSS submission contains the ERSS plans and design, BCA's ERSS_Annex A, and the site investigation report certified by a PE. BCA's June 2026 requirements then set out the following steps:
Obtain plan approval for the ERSS.
Obtain the permit to carry out the works, and notify BCA of commencement.
Implement ERSS_Annex C at site during construction.
Submit ERSS_Annex E by e-form through CORENET by the 7th of each month.
On completion, submit record plans for permanent and temporary ERSS with forms C1, C2 and C3, endorsed by the QPs and ACs of the approved plans.
The design QP must ensure that all site investigation works are carried out by an inspection body accredited by the Singapore Accreditation Council. See soil investigation in Singapore.
Which authority and regulation governs ERSS?
BCA governs ERSS under the Building Control Act 1989 and the Building Control Regulations 2003. The First Schedule sets the insignificant works exemption and the Fourth Schedule sets the 4 m accredited checker threshold. Carrying out building works without approved plans or a permit is an offence under the Building Control Act, with a fine of up to $200,000, imprisonment of up to 2 years, or both.
Common mistakes with ERSS thresholds
The common mistakes are misreadings of the bands:
Using the 1.5 m exemption for a timber or other non-steel, non-concrete system, where the limit is 1 m.
Applying the 2 m pit relief to a pit larger than 10 square metres.
Ignoring a slope or surcharge above the wall when working out the height.
Building two low walls within 3 m of each other and treating each as exempt.
Using ground improvement as the retaining wall. BCA states that ground improvement shall be limited to soil improvement work only and shall not be used as part of the retaining wall.
FAQ
At what depth does an excavation need BCA approval in Singapore?
More than 1.5 m in general, or more than 2 m for a localised pit for a pile cap, footing, sump, lift pit or trench not exceeding 10 square metres.
Does a 3 m retaining wall need an accredited checker?
No. Between 1.5 m and 4 m a QP(ST) submits without an AC.
Does every excavation deeper than 6 m need a PE(Geo)?
No. Only those classified as GBW. BCA's example of a non-GBW case is excavation for a sewer manhole associated with a pipe of 2 m diameter or less.
Does a low garden retaining wall need approval?
Not if it meets the First Schedule conditions. See retaining walls and slopes for landed houses.