BP Submission and ST Submission in Singapore: What Is the Difference
A BP submission is the building plan submission and an ST submission is the structural plan submission, both made to the Building and Construction Authority (BCA) under the Building Control Act. The BP shows that the building's layout and design comply with the building regulations and can be submitted by a Qualified Person (QP) who is a registered architect or a professional engineer. The ST contains the structural drawings and calculations, and only a QP who is a professional engineer in the civil or structural discipline can apply for it.
What is a BP submission?
A BP submission is the application to BCA for approval of the building plans, made through a QP before building works start. BCA states that the QP must be an architect registered with the Board of Architects or a professional engineer registered with the Professional Engineers Board, holding a valid practising certificate.
The building plans must show compliance with:
the objectives and performance requirements in the Fifth Schedule of the Building Control Regulations, usually through the acceptable solutions in the Approved Document
the Code on Accessibility
the technical requirements for household shelters and storey shelters, where they apply
Since 1 April 2023, the relevant aspects of civil defence shelter plans have been incorporated into the BP and ST submissions. Before applying for BP approval, the QP must first obtain written permission from the Urban Redevelopment Authority (URA).
What is an ST submission?
An ST submission is the application to BCA for approval of the structural plans, and only a QP who is a professional engineer in the civil or structural discipline can make it. The standard package listed by BCA is:
the application form for structural plan approval
one set of signed detailed structural plans
one set of building plans for reference, signed by the person who prepared them
one set of structural design calculations, signed and endorsed
a valid planning permission, lodgement receipt or no-objection letter from URA
the plan fee computation and buildability score calculations, where applicable
An Accredited Checker certificate and evaluation report are needed unless the works are minor building works. Geotechnical building works need certification by a geotechnical QP and an AC(Geo). A site investigation report must be endorsed by a professional engineer.
Who submits BP and who submits ST?
The architect or engineer appointed as QP for the building works submits the BP, and a civil or structural professional engineer submits the ST. On most building projects that means two different QPs working from the same design: one responsible for the architectural plans and one for the structure. On some engineering-led works a professional engineer may be the QP for both, within what the Third Schedule allows.
Our guide to QP submission from appointment to CSC explains the appointments in order.
What comes first: URA, BP or ST?
Planning permission from URA comes first, then the BP and ST approvals, then the permit to carry out structural works. BCA requires URA's written permission before a BP application, and requires a valid planning permission, lodgement receipt or no-objection letter with the ST application. The usual sequence is:
URA planning permission. See the order of authority submissions.
BP submission to BCA, with clearances from the technical agencies.
ST submission to BCA. BCA allows structural plans to be approved in phases, such as piling, basement and superstructure.
Permit to carry out structural works, applied for jointly by the developer, the QP and the builder. It can be applied for together with the ST or after approval.
Construction under the QP's supervision, then the TOP or CSC application.
ST approval on its own is not permission to build. BCA states that once the structural plan is approved, a permit must still be obtained before structural works can start.
How long do BP and ST approvals take?
BCA's published service standard for structural plans is 7 working days without an Accredited Checker's certification, and with one, 10 days for a first submission and 14 working days for subsequent submissions. The permit to carry out structural works is processed within 7 working days.
BCA also states that it requires a longer response time when the appointed QP has shown poor submission quality in previous structural plan submissions, such as a high number of Written Directions. BCA's building plan submission page does not publish a processing time for BP approval, so we do not quote one here.
How does CORENET X change BP and ST submissions?
Under CORENET X, BP and ST approvals are issued together at the Construction Gateway as part of one joint submission reviewed by several agencies. BCA states that this joint review takes 20 working days. The CORENET X process has three main gateways:
Design Gateway: URA provisional permission and the development control clearances from LTA, NEA, PUB and NParks.
Piling Gateway, which is optional: BCA ST approval for permanent piling works.
Construction Gateway: URA written permission, BCA BP and ST approvals, SCDF building plan approval and the other agencies' clearances.
Completion Gateway: the TOP and CSC application.
Works with no cross-agency dependency go as independent submissions. For BCA these include the structural design of demolition, temporary ERSS, cladding and barriers, with a stated response time of 15 working days. Simpler projects, such as a single landed house or qualifying additions and alterations, use the Direct Submission Process, a single-stage approval before TOP or CSC.
CORENET X has been mandatory since 1 October 2025 for new projects of 30,000 sqm gross floor area or more, and from 1 October 2026 for new projects of 5,000 sqm or more. Under the BCA and URA circular of 23 July 2026 (APPBCA-2026-12), projects below 5,000 sqm can continue to use CORENET 2.0 for now. See our CORENET X guide.
Which authority and regulation governs BP and ST?
Both submissions are governed by the Building Control Act 1989 and the Building Control Regulations 2003, administered by BCA's Commissioner of Building Control.
First Schedule: insignificant building works that need no plan approval or permit.
Second Schedule: plan fees, payable at the first plan submission and based on Statistical Gross Floor Area.
Third Schedule: which QP may prepare which plans.
Fourth Schedule: minor building works that need no Accredited Checker.
Fifth Schedule: the performance requirements the building plans must meet.
Ninth Schedule: works eligible for BCA's Lodgment Scheme, under which lodged plans are deemed approved.
Fire safety plans are a separate submission to SCDF under the Fire Safety Act 1993, even though they are also called building plans.
What goes wrong with BP and ST submissions?
Most problems come from treating one approval as if it covered the other. The common mistakes are:
Starting structural works on BP approval alone. Carrying out building works without approved plans or a permit is an offence under the Building Control Act, with a fine of up to $200,000, imprisonment of up to 2 years, or both.
Mixing up BCA's BP with SCDF's BP. Under CORENET X, BCA, SCDF, LTA, NEA and PUB each issue their own building plan approval or clearance.
Changing the structure on site without telling the QP. Material changes that need a redesign of key structural elements must be approved before the change is made.
Submitting ST plans that do not match the BP. The ST package includes a set of the building plans for reference, and mismatches between the two sets can lead to Written Directions.
FAQ
Can an architect submit ST plans?
No. BCA states that only a QP who is a registered professional engineer in the civil or structural discipline can apply for structural plan approval.
Can a professional engineer submit BP plans?
A professional engineer with a valid practising certificate is a QP. Whether an engineer may prepare the building plans for a given type of works depends on the Third Schedule of the Building Control Regulations.
Do I need both BP and ST for additions and alterations?
It depends on the works. Structural changes need an ST submission and layout changes may need a BP submission, unless the works are insignificant building works. See our A&A guide.
What do BP and ST mean in the glossary of submission terms?
BP is building plan and ST is structural plan. Our submission glossary defines the other abbreviations.