QP Submission in Singapore Step by Step: From Appointment to CSC

Nov 11
5 min read

Updated: Nov 12

A QP submission in Singapore follows a fixed regulatory order. The developer appoints a Qualified Person (QP), obtains planning permission from URA, obtains BCA approval of the building and structural plans and a permit to carry out structural works, clears SCDF fire safety plan approval, builds under QP supervision, and closes the project with a Temporary Occupation Permit (TOP) and a Certificate of Statutory Completion (CSC).

Who is a Qualified Person and who appoints one?

BCA defines a QP as an architect registered with the Board of Architects or a professional engineer registered with the Professional Engineers Board, in either case holding a valid practising certificate. Under the Building Control Act the developer appoints a QP to prepare the plans and a QP to supervise the works. Two limits matter in practice:

  • Only a QP who is a professional engineer in the civil or structural discipline can apply for structural plan approval.

  • The Third Schedule of the Building Control Regulations sets out which QP may prepare or sign which type of building works.

If you are unsure whether your job needs a full submission or only a design endorsement, see PE endorsement vs QP submission. To confirm that an engineer is registered and holds a current practising certificate, see how to check a Professional Engineer in Singapore.

What are the steps from appointment to CSC?

  1. Appoint the QP who prepares the plans, the QP who supervises the works, and a builder.

  2. Obtain planning permission from URA. BCA states that the QP must obtain URA written permission before applying for building plan approval. Certain works, including additions and alterations to landed houses and some industrial and warehouse developments, can instead be lodged with URA under the plan lodgment scheme on a QP's self-declaration.

  3. Submit building plans to BCA. The plans must meet the performance requirements in the Fifth Schedule of the Building Control Regulations, the Approved Document, the Code on Accessibility and the technical requirements for household and storey shelters.

  4. Submit structural plans to BCA through the structural QP. Where the works are not minor works under the Fourth Schedule, an Accredited Checker must certify the design first.

  5. Apply for the permit to carry out structural works. The developer, the QP and the builder apply jointly, either together with the structural plan submission or after the plans are approved. The QP appoints the site supervisors at this stage.

  6. Obtain SCDF approval of plans for any fire safety works. Under the Fire Safety Act 1993 this approval is needed before fire safety works start, unless the works are exempt or qualify for a Minor Additions and Alterations lodgement.

  7. Build under supervision. Structural works are supervised by the QP and, depending on project value, by Resident Engineers and Resident Technical Officers. A change that requires redesign of key structural elements needs BCA approval before it is built. Immaterial changes may proceed but must be recorded and included in later plan submissions.

  8. Complete and certify. The owner engages a Registered Inspector to inspect and certify the fire safety works, and the QP applies to SCDF for a Fire Safety Certificate, which must be obtained before the premises are used or occupied. A Temporary Fire Permit may be issued where only very minor items remain. The QP also applies to BCA for TOP and CSC with the Certificate of Supervision, the Builder's Certificate of Completion and clearances from the technical agencies.

Works listed as insignificant building works in the First Schedule of the Building Control Regulations sit outside steps 3 to 5, although other agencies' approvals can still apply.

How does CORENET X change the sequence?

CORENET X replaces separate agency submissions with coordinated gateways at which the agencies respond together:

  • Design Gateway: resolves parameters that shape the design, such as land use, intensity, massing and site layout, before detailed design.

  • Piling Gateway (optional): covers piling and foundation works so that these can start ahead of the main structure.

  • Construction Gateway: resolves design details before the main structural works start. It carries URA written permission and the BCA and SCDF building plan clearances, among others.

  • Completion Gateway: covers as-built documents and the TOP and CSC stage.

Simpler development types, such as single-unit residential works and racking systems, can use a single-stage Direct Submission Process. According to BCA, CORENET X became mandatory from 1 October 2025 for new projects with a gross floor area of 30,000 sqm or more, and from 1 October 2026 for new projects of 5,000 sqm or more. Projects below 5,000 sqm can continue to use CORENET 2.0 for now. More detail is in our CORENET X guide.

Which authority governs what?

  • URA, under the Planning Act: use, intensity and form of development, through written permission or plan lodgment.

  • BCA, under the Building Control Act and Building Control Regulations 2003: building plans, structural plans, the permit to carry out structural works, site supervision, TOP and CSC.

  • SCDF, under the Fire Safety Act 1993 and the Fire Code: fire safety plan approval, Fire Safety Certificate and Temporary Fire Permit.

  • LTA, NParks, PUB and NEA: technical clearances that BCA lists as requirements for TOP and CSC.

  • Board of Architects and Professional Engineers Board: registration and practising certificates of the QPs themselves.

How long does each approval take?

These are the agencies' published service standards, counted from a complete submission. They do not include design time, the Accredited Checker's own review or resubmissions.

  • Structural plans without Accredited Checker certification: 7 working days.

  • Structural plans with Accredited Checker certification: 10 days for the first submission and 14 working days for subsequent submissions.

  • Plans under the CORENET X Construction Gateway: 20 working days.

  • Permit to carry out structural works: 7 working days.

  • TOP: 7 working days. CSC: 7 working days.

  • URA written permission is valid for 2 years from the date of grant, and provisional permission for 6 months. URA asks for extension applications at least 2 months before expiry.

What goes wrong in QP submissions?

  • Starting work before the permit is issued. Carrying out building works without approved plans or a permit is an offence under the Building Control Act, with a fine of up to $200,000, imprisonment of up to two years, or both.

  • Assuming the works are insignificant. The First Schedule limits are specific, and works just outside them need the full process. Our review of recent enforcement on unauthorised mezzanines shows how this ends.

  • Treating BCA approval as the only approval. A mezzanine floor, for example, usually raises URA, SCDF and landlord questions as well.

  • Building material structural changes first and seeking approval later.

  • Letting URA written permission lapse while the technical submissions are still in progress.

  • Reaching completion without the documents or agency clearances needed for TOP or CSC.

FAQ

Who can make a QP submission in Singapore?

A registered architect or a professional engineer with a valid practising certificate. Structural plans can only be submitted by a professional engineer in the civil or structural discipline.

Can structural works start once the plans are approved?

No. A separate permit to carry out structural works is required. It is applied for jointly by the developer, the QP and the builder, and BCA's service standard is 7 working days.

What is the difference between TOP and CSC?

BCA issues a CSC when all statutory requirements and agency clearances are met. A TOP allows occupation when the building is suitable for occupation but some matters with other technical agencies remain outstanding.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including BCA submissions and CORENET X submissions. WhatsApp +65 9342 7551 to discuss a project. Last reviewed: November 2026.

Recent Posts

See All
Singapore Building Compliance Handbook 2027

A map of Singapore building compliance rules for 2027: PE endorsement, QP submissions, geotechnical, demolition, inspection, factories, landed houses, procurement and a dated 2027 at-a-glance list, wi

 
 
 

Comments