CORENET X in 2027: Who Must Use It and How to Prepare
CORENET X is the joint submission system in which BCA, URA, SCDF, LTA, NEA, PUB and NParks review a building project together at set gateways. In 2027 it is mandatory for new projects of 5,000 sqm gross floor area (GFA) and above, after being mandatory for projects of 30,000 sqm and above since 1 October 2025, while smaller projects may stay on CORENET 2.0 for now.
Written in November 2026 from published rules; check the linked official sources for updates.
Decision steps: does your project have to use CORENET X?
Work through these five steps in order and stop at the first one that applies. Ask your Qualified Person (QP) to confirm the answer, because the agencies decide how a project is classified.
Is it a new project? The mandatory dates apply to new projects, so start by confirming with your QP how the agencies classify yours.
Is the GFA 30,000 sqm or more? CORENET X has been mandatory since 1 October 2025.
Is the GFA 5,000 sqm or more? CORENET X is mandatory from 1 October 2026, so it applies to anything submitted in 2027.
Is the GFA below 5,000 sqm? A joint BCA and URA circular of 23 July 2026 (APPBCA-2026-12) says such projects are not required to onboard and may continue to use CORENET 2.0 for now. The sources we reviewed give no end date for this.
Is it a single landed house, qualifying additions and alterations, racking or a simple structure such as a linkway? CORENET X offers these a single-stage Direct Submission Process. A single landed house is also below 5,000 sqm, so it can stay on CORENET 2.0 for now. See landed house rebuild timeline.
Preparation list: gateway by gateway
Each item gives what the gateway covers, who is involved and the stated response time. Agencies issue written directions or approvals within up to 20 working days. URA notes this extends to 30 working days if a further Design Advisory Panel session is needed.
Design Gateway. Covers URA's provisional permission, the development control clearances of LTA, NEA and PUB, and NParks development control approval. Who: the lead QP and design team. Prepare: land use, intensity, massing and site layout. See order of authority submissions and URA written and provisional permission.
Piling Gateway (optional). Covers BCA structural approval for permanent piling and, where relevant, LTA's approval in principle for piles in a railway protection zone. Who: the structural PE. Use it only if you want piling to start before the Construction Gateway is approved.
Construction Gateway. Covers URA written permission, BCA building plan (BP) and structural plan (ST) approvals, SCDF building plan approval, LTA street plan, parking and rail clearances, and NEA and PUB building plan clearance. BCA states the joint review takes 20 working days. See BP and ST submissions and technical agency clearances.
Completion Gateway. Covers as-built plans and the application for the Temporary Occupation Permit (TOP) and Certificate of Statutory Completion (CSC). BCA processes TOP and CSC within 7 working days of complete documents. See TOP and CSC.
Independent submissions. Matters with no cross-agency effect, such as NParks tree felling approval or PUB earth control measures approval, go separately and in parallel. For BCA, the structural design of demolition, temporary ERSS, cladding and barriers are independent, with a stated response time of 15 working days.
Demolition ahead of redevelopment. This is a joint submission to BCA and URA, and BCA approves only where URA has also approved the demolition or authorised the redevelopment. See types of demolition submission.
Checklist: what to line up before the first submission
Appoint the QP early. Under CORENET X the disciplines submit coordinated models, so late appointments leave gaps. See QP submission step by step.
Confirm whether an Accredited Checker is needed, because the AC's review happens before submission. See accredited checker.
Check the federated model. BCA's CORENET X Good Practices Guidebook (December 2025) gives avoidable errors such as a roof missing because a file was not attached, a drain left floating above the ground and tower and podium models that appear disjointed.
Plan for resubmission. Where agencies have comments, only they respond and the others hold their approval until the resubmission on which all can approve.
Prepare a specific reply to every comment, with the sheet or model location of each change. See written directions.
What has not changed
CORENET X does not change which approvals are needed. The same Acts apply, the same professionals sign and each agency still issues its own approval letter, so joint approvals are individual agency letters. Works still cannot start without approved plans and a permit, and a building still cannot be occupied without a TOP or CSC. The CORENET X Code of Practice states that agencies' mandates and the QP's statutory responsibilities are unchanged. Our CORENET X guide explains the model requirements. For the wider list of 2027 changes see the PE endorsement guide 2027 and the Singapore Building Compliance Handbook 2027.
Common mistakes
Assuming CORENET 2.0 is permanent. The circular says "for now".
Sending an incomplete or badly federated model, which produces a written direction and another review round.
Replying "complied with" or "noted". BCA's guidebook says generic replies often lead to additional queries.
Treating BP as one approval. BCA, SCDF, LTA, NEA and PUB each issue their own building plan approval or clearance.
Uploading outdated models or plans in a resubmission.
FAQ
Do I need CORENET X for a house or a small A&A in 2027?
Not as the rules stand. Projects below 5,000 sqm GFA may continue on CORENET 2.0 for now under the 23 July 2026 circular.
Does CORENET X change who must sign?
No. A QP who is a registered architect or a PE with a valid practising certificate still submits, and structural plans still need a PE in the civil or structural discipline.
How long do agencies take under CORENET X?
Up to 20 working days per gateway submission for a written direction or approval. BCA's CORENET 2.0 times are 7 working days without Accredited Checker certification and 10 days for a first submission with one, then 14 working days.
How are comments given on a model submission?
Written directions on model submissions include BIM Collaboration Format (BCF) files that tag each comment to the relevant part of the model.
Is there a tool to check a model before submission?
CORENET X has soft-launched a model checker for quality checks before submission; see the CORENET X portal for its current status.
Sources