Written Direction in Singapore Building Submissions: What a WD Means and How to Clear It
A Written Direction (WD) is an agency's written response to a plan submission that it is not yet ready to approve. It lists the non-compliances, missing documents or clarifications that the Qualified Person (QP) must address in a resubmission. A WD is not a rejection and not an approval: the application stays open, and it is cleared when the QP resubmits and the agency issues its approval or clearance.
What is a Written Direction?
A Written Direction is the formal list of comments an agency issues on a submission that does not yet meet its requirements. The term is used across Singapore's building agencies:
BCA's guide for fixed installation design plans describes a resubmission as an amendment to the original submission in response to written directions, and lists Written Directions, Notices of Approval and Notices of Disapproval as the three kinds of correspondence an applicant may receive.
The CORENET X Code of Practice states that the relevant agencies will provide Written Directions or approvals on a submission.
URA has explained that its planners used Written Directions to require QPs to comply with minor plan presentation requirements.
JTC's plan consent guide lists a written direction as one possible outcome of a submission, alongside JTC's consent as landowner.
SCDF's public pages describe the same loop in different words. For a Fire Safety Certificate application, SCDF says that if problems are found the QP must make the changes and resubmit. For what the other abbreviations mean, see our submission glossary.
Where does a WD appear in the submission process?
A WD appears after the agency has reviewed a submission and before approval, at any stage where plans are processed. In a typical project that means the planning application to URA, the BP and ST submissions to BCA, the technical agencies' clearances, and landlord consent from JTC.
The cycle is the same each time:
The QP submits plans, forms and calculations.
The agency reviews them within its service standard.
If the submission is in order, the agency approves. If not, it issues a WD.
The QP amends the plans, answers each comment and resubmits.
The agency reviews the resubmission and either approves or issues a further WD.
Under CORENET X, the Code of Practice states that agencies provide Written Directions or approvals within a service level of up to a maximum of 20 working days. For a joint submission to several agencies, only the agencies that have Written Directions respond. Agencies that are ready to approve hold their response until the resubmission on which all relevant agencies can approve. Our CORENET X guide explains the gateways.
What does a WD usually contain?
A WD contains the agency's specific comments on what is missing, unclear or non-compliant. For submissions made as building information models, the CORENET X Code of Practice states that the WD also includes BIM Collaboration Format (BCF) files, which tag each comment to the relevant part of the model and can be opened in the modelling software with free plugins.
BCA's CORENET X Good Practices Guidebook gives examples of avoidable errors that typically result in WDs:
incomplete models, such as a missing roof because a file was not attached
federation errors that leave a component, such as a drain, floating above the ground
tower blocks and podiums that appear disjointed when the models are combined
For structural submissions, BCA's service standard applies only once complete documents are submitted, and its structural plan page lists them, including the calculations, the Accredited Checker's certificate and evaluation report where required, and the endorsed site investigation report. Our QP submission guide lists what goes into each package.
How should a QP respond to a WD?
The QP should address every comment specifically, amend the plans and resubmit a complete package. BCA's Good Practices Guidebook is direct on this point: avoid generic replies such as "complied with" or "noted", because they often lead to additional queries. Instead, explain how each issue was resolved and where the supporting change can be found.
Practical steps drawn from the Code of Practice and the Guidebook:
Read the whole WD and list every comment, including comments from each agency on a joint submission.
Decide which comments need a design change and which need only a clarification or a missing document.
Amend the drawings, model and calculations. Do not upload outdated documents, models or plans in the resubmission.
Write a response against each comment stating what was changed and on which sheet or in which model.
How does a WD affect processing time?
Each WD adds at least one more review cycle, so the published service standards apply again to the resubmission. For structural plans with an Accredited Checker's certification, BCA's standard is 10 days for a first submission and 14 working days for subsequent submissions. Under CORENET X, the Code of Practice gives agencies a service level of up to 20 working days to respond.
WDs also have a longer-term effect. BCA states on its structural plan submission page that it requires a longer response time when the appointed QP has demonstrated poor submission quality in previous structural plan submissions, such as having a high number of Written Directions.
URA has made the same point from the planning side. Before it introduced EDARAD (Electronic Development Application Replacement and Addition of Documents) in 2001, a WD for minor amendments meant a resubmission and a further three to four weeks of waiting for Written Permission. With EDARAD, QPs are expected to follow up on minor amendments within three to five working days.
Is a WD the same as a Written Permission, a Notice or an Order?
No. These are four different documents.
Written Direction (WD): comments on a submission that is still being processed. It asks for corrections.
Written Permission (WP): URA's planning approval, which lapses after 2 years. See WP and PP timelines.
Notice of Approval or Notice of Disapproval: the agency's decision at the end of processing.
Enforcement notices and orders: issued to owners or occupiers about a contravention in an existing building or on site. One example is SCDF's Notice of Offence, which can require an area to be reinstated to its approved use. These are not part of plan processing. See regularisation of unauthorised works.
Which authority governs Written Directions?
No single law governs Written Directions. Each agency processes submissions under its own legislation, such as the Building Control Act 1989 for BCA and the Fire Safety Act 1993 for SCDF, and issues its own comments. The CORENET X Code of Practice states that the agencies' mandates and the QP's statutory responsibilities are unchanged by the new platform. See technical agency clearances for which agency checks what.
What goes wrong when clearing a WD?
Most delays come from incomplete or vague responses. BCA's Good Practices Guidebook records that some project teams fail to fully address agency comments even after two submission rounds, which has led to additional working sessions and extended processing timelines.
Replying "noted" without changing the plans.
Answering one agency's comments and overlooking another's on a joint submission.
Resubmitting with an outdated drawing or model still in the package.
Starting work on site while the WD is outstanding. Works need approved plans and a permit. Carrying out building works without them is an offence under the Building Control Act, with a fine of up to $200,000, imprisonment of up to 2 years, or both.
FAQ
Does a WD mean my application has been rejected?
No. A WD keeps the application open and tells the QP what to correct. BCA's fixed installation guide, for example, treats a Notice of Disapproval as a separate outcome.
Who replies to a Written Direction?
The QP who made the submission replies. On a joint submission each appointed QP answers the comments within their own scope.
How many WDs are normal?
There is no fixed number. A complete first submission may be approved with none. BCA treats a high number of WDs on a QP's previous structural submissions as a sign of poor submission quality.
Can work start once the WD reply is submitted?
No. Work can start only after plan approval and, for structural works, the permit to carry out structural works.
Sources
CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, so Written Directions on the building, structural and geotechnical plans are answered together. See our BCA submission service and CORENET X BIM submission, or WhatsApp or call +65 9342 7551. Last reviewed: November 2026.