Authority Submission Timeline Planner 2027 Singapore
The published authority clocks for a Singapore building project are short, but they only start once a submission is complete: BCA's structural plan service standard is 7 working days without an Accredited Checker and 10 days (first submission) or 14 working days (later submissions) with one, the permit takes 7 working days, and TOP and CSC take 7 working days each. URA permissions have validity periods rather than a single processing time, and under CORENET X agencies respond within up to 20 working days per gateway submission. Use this planner to lay the stages in order and work backwards from the date you need to occupy.
Written in November 2026 from published rules; check the linked official sources for updates.
How to use this planner
Each stage below states what it is, who it applies to, the official clock or validity period, and where to read more. The clocks are the agencies' service standards counted from a complete submission. They exclude design time, the Accredited Checker's own review and any resubmission after a Written Direction. Add your own buffer for those. The order itself is explained in URA first, then technical agencies, then BCA.
The planner, stage by stage
Landowner or lessor consent (leased land only). What: consent from the landowner, for example JTC, HDB or SLA, where the land is leased. Applies to: any project on leased land. Clock: set by the landowner, not by a regulator. Read: JTC factory renovation consent.
URA planning permission. What: provisional permission (PP), written permission (WP) or plan lodgment. Applies to: development, building works and changes of use. Clock: PP lapses 6 months from the day it is granted and WP lapses 2 years from the day it is granted; an outline application is generally assessed in 20 working days, a change of use in 10 working days and an extension in 15 working days. Plan lodgment authorisation is valid for 2 years and may be extended twice, for 2 years each time. Read: URA written permission and provisional permission.
Technical agency development control clearances. What: PUB, LTA, NParks and NEA clear the broad layout. Applies to: most new developments; small works may use lodgment or self-declaration routes. Clock: LTA states 20 working days for straightforward cases with complete information; PUB states that DC and Detailed Plan clearance is needed before sewerage, sanitary and drainage works commence. Read: technical agency clearances.
BCA building plan (BP) approval. What: approval that the building's layout and design comply with the building regulations. Applies to: new building works not listed as insignificant. Clock: starts only after URA written permission is in hand, because BCA requires it before a building plan application. Read: BP and ST submissions.
BCA structural plan (ST) approval. What: approval of structural drawings and calculations, which only a QP who is a PE in the civil or structural discipline can apply for. Applies to: structural works. Clock: 7 working days without Accredited Checker certification; 10 days for a first submission and 14 working days for later submissions with it. Read: Accredited Checker.
Permit to carry out structural works. What: the permit applied for jointly by the developer, the QP and the builder, together with the ST or after approval. Applies to: all building works except insignificant building works. Clock: 7 working days. Read: QP submission step by step.
SCDF fire safety plan approval. What: approval of fire safety works before they start. Applies to: fire protection systems, escape routes, compartments, ventilation and relevant changes of use; minor additions and alterations may be lodged by a QP. Clock: not quoted here; check SCDF's plan submission pages. Read: SCDF fire safety submission.
Construction under supervision. What: works built to approved plans under QP supervision. Clock: none set by any authority; a material structural change needs BCA approval before it is built. Read: site supervision roles.
Fire Safety Certificate. What: SCDF's certificate after a Registered Inspector has inspected the works. Applies to: premises with fire safety works. Clock: SCDF responds within 3 working days; the FSC must be obtained before the premises are used or occupied.
TOP and CSC. What: Temporary Occupation Permit and Certificate of Statutory Completion, applied for by the project QP. Clock: 7 working days each from complete documents; a CSC needs all agency clearances. Read: TOP and CSC.
How does CORENET X change the clocks?
CORENET X groups the same approvals into Design, Piling (optional), Construction and Completion gateways, and agencies issue written directions or approvals within a service level of up to 20 working days per gateway submission; URA notes this extends to 30 working days if a further Design Advisory Panel session is needed. It is mandatory for new projects of 30,000 sqm GFA and above since 1 October 2025 and 5,000 sqm and above from 1 October 2026; smaller projects may stay on CORENET 2.0 for now. Single-unit landed houses and simple structures can use a single-stage Direct Submission Process. See the CORENET X guide.
Dates to put in a 2027 plan
Validity dates: note the day each PP (6 months) and WP (2 years) was granted. URA asks for extension applications 2 months before expiry, and generally takes 15 working days to assess one.
1 December 2026: SS 557:2026, the revised demolition code, is expected for projects whose URA planning application is made on or after this date (BCA circular APPBCA-2026-09). See demolition in Singapore.
1 October 2026 onward: projects of 5,000 sqm GFA and above go through CORENET X from the start.
Working back: for a target TOP date, subtract 7 working days for TOP, then the construction period in your contract, then 7 working days for the permit, then the structural plan clock, then URA and agency clocks, and finally your own design and resubmission buffer.
What has not changed
URA written permission is still required before BCA building plan approval.
Only a PE in the civil or structural discipline can apply for structural plan approval.
Works still need approved plans and a permit; carrying them out without both carries a fine of up to $200,000, imprisonment of up to 2 years, or both under the Building Control Act 1989.
Each agency still issues its own approval letter, including under CORENET X. See the hub.
Common mistakes
Treating the 7 working day clocks as the project programme. They exclude design, checking and resubmissions.
Submitting to BCA on a provisional permission alone.
Letting a PP or WP lapse while technical submissions are still running.
Leaving agency completion clearances to the end, which holds up the CSC.
Assuming BCA's stated times apply when previous submissions drew many Written Directions: BCA states it needs longer for a QP with poor submission quality. See Written Directions.
Starting works that look minor without checking insignificant building works first.
FAQ
How long does BCA take to approve structural plans?
BCA states 7 working days without Accredited Checker certification, and 10 days for a first submission and 14 working days for later submissions with it, counted from complete documents.
How long does a URA written permission last?
It lapses 2 years from the day it is granted; a provisional permission lapses after 6 months.
Can agency submissions run in parallel?
Yes. Technical agency submissions are commonly made in parallel, and under CORENET X they are made jointly at each gateway.
Do I need a permit as well as plan approval?
Yes. A separate permit to carry out structural works is required for all building works except insignificant building works, applied for jointly by the developer, the QP and the builder.
Is CORENET X compulsory for my project?
Only for new projects of 5,000 sqm GFA and above from 1 October 2026; smaller projects may use CORENET 2.0 for now.