PE Endorsement vs QP Submission: Which One Does Your Project Need?
Updated: Nov 12
The two terms are used as if they mean the same thing. They do not. A PE endorsement is an engineer's signature on a design. A QP submission is the statutory process of getting building works approved and supervised. Some jobs need only the first. Many need both.
What is a PE endorsement?
A Professional Engineer registered with the Professional Engineers Board, holding a valid practising certificate, signs and stamps drawings and calculations to confirm the design complies with the relevant codes. The engineer who signs takes personal responsibility for it.
What is a Qualified Person?
Under the Building Control Act, a Qualified Person is a registered architect or a professional engineer who holds a valid practising certificate. The developer or owner appoints a QP to prepare the plans and a QP to supervise the works. PE is a registration. QP is a role on a specific project.
When is a QP submission required?
BCA requires a permit for all building works except those classified as insignificant building works. If your works are not on that list, plans are prepared and submitted by a QP, and the works are supervised by a QP. For structural plans, only a PE in the civil or structural discipline can apply. The permit to carry out structural works is applied for jointly by the developer, the QP and the builder.
When is a PE endorsement alone enough?
Where a contractor, landlord or main contractor needs an engineer's certification on file, and the item is not building work that needs plan approval. Temporary works such as scaffolds, formwork and lifting supports are common examples. See temporary structure endorsement.
A quick way to tell
Does it add floor area, change the structure, or change the use of the space? Expect a QP submission.
Is it temporary, or equipment sitting on a structure that can already carry it? An endorsement may be enough.
Is it already built without approval? That is regularisation, which is a QP submission for existing works.
How long does BCA take?
BCA's stated processing times for structural plans are 7 working days without Accredited Checker certification; with certification, 10 days for the first submission and 14 working days for later ones; and 20 working days for projects under CORENET X. The permit to carry out structural works takes 7 working days after complete documents.
CVC Engineers has a dedicated team to help resolve this properly, whether it is endorsement only or a structural QP submission. Read more on PE endorsement services and BCA submission services.