Mezzanine Floor Approval in Singapore: BCA, SCDF, URA and JTC Explained
A mezzanine adds floor area, load and occupants to a building that was approved without them. Three questions decide whether it can be built, or stay: can the existing structure carry it, does the added floor area fit the site's planning limits, and can people get out in a fire. Each question belongs to a different authority.
Do you need approval for a mezzanine floor?
Yes, in most cases. A mezzanine is building work. BCA requires a permit for all building works except those listed as insignificant building works in the Building Control Regulations. The structural plans must be approved, and the permit obtained, before construction starts.
There is one narrow exemption. Under the First Schedule of the Building Control Regulations, a single-level platform in an industrial building is insignificant building works if it is used solely for storing goods, is not accessible to the public, is no more than 4 m high and 50 sqm in area, has no beam or slab span over 6 m and no cantilever over 3 m. A mezzanine used as office or work space, or larger than those limits, needs approval. Fire safety, GFA and landlord consent are separate questions and still apply.
Which authority checks what
BCA: structural plans and the permit to carry out structural works. Only a Professional Engineer in the civil or structural discipline can apply for structural plan approval.
SCDF: fire safety works. Anyone carrying out addition or alteration works must first obtain SCDF approval for the fire safety works involved, with plans prepared and submitted by a qualified professional.
URA: gross floor area. URA counts all covered floor area as GFA unless it is specifically exempted, so a mezzanine should be planned on the basis that it counts.
JTC or your landlord: consent. On JTC land and buildings, JTC's consent is required for additions and alterations even where other authorities also approve the works.
What the structural check covers
Whether the existing slab and foundations can take the new column loads
A design floor loading that matches the real use: storage, office or plant
Connections to the existing structure, and lateral stability
Steel member and deck design, supported by calculations
Factory unit used for storage
A mezzanine is often added to gain storage. SCDF has stated that using factory space as storage is deemed a change of use from factory to storage. Declare the real use at the start, because it changes the fire safety provisions and the floor loading the engineer designs for.
What if the mezzanine is already built without approval?
On 28 January 2025 a mezzanine floor and racking collapsed in a warehouse at Toa Payoh Industrial Park, trapping three people. The authorities stated it had been installed without approval from SCDF or BCA. Carrying out building works without plan approval or a permit carries a fine of up to $200,000, imprisonment of up to two years, or both.
An existing mezzanine can be assessed by a Professional Engineer and submitted for approval through regularisation of unauthorised works. Where the structure does not comply, it is strengthened or removed.
How long does approval take?
BCA states that structural plans without Accredited Checker certification are processed within 7 working days of a complete submission. The overall programme depends on how many authorities are involved and on how complete the record drawings of the existing building are.
One appointment for architectural and structural scope
CVC Engineers designs, endorses and submits mezzanine floors for factories, warehouses and shops, taking the architectural and structural submissions together so the drawings sent to each authority agree. See our PE endorsement services or send your drawings and photos on WhatsApp at +65 9342 7551.