Landed House Rebuild Guide 2027: Rules to Know Before You Start
Rebuilding a landed house in Singapore is governed by twelve rules that you can check before you appoint anyone: URA's storey, envelope, plot and setback controls, the A&A versus reconstruction test, the lodgment route, BCA's plan and permit sequence, and the demolition, survey and completion rules. A single house can usually be lodged with URA rather than applied for, BCA's 7 working day clocks apply to structural plans, the permit, TOP and CSC, and design and construction durations are not set by any authority.
Written in November 2026 from published rules; check the linked official sources for updates.
The checklist: twelve rules in the order you meet them
Know your storey control. What: a landed house may not exceed the 2-storey or 3-storey control, or the storey height shown for the area in the Designated Landed Housing Area Plan, whichever is lower. Applies to: every plot. Rule: landed houses outside Designated Landed Housing Areas and not guided by street block plans are subject to a 3-storey control (URA locational criteria, last updated 6 November 2026). Read: URA envelope control.
Fit inside the envelope. Applies to: all landed housing since 11 May 2015. Rule: overall height is capped at 12.0 m in a 2-storey area and 15.5 m in a 3-storey area, each including a 3.5 m attic zone within a 45-degree line, measured from the external platform level or, in low-lying areas, from PUB's Minimum Platform Level.
Check plot size, width and site coverage. Applies to: your housing type. Rule: Good Class Bungalow 1,400 sqm and 18.5 m wide; bungalow outside GCBA 400 sqm and 10 m; semi-detached 200 sqm and 8 m (side-to-side) or 10 m (back-to-back); terrace Type I intermediate 150 sqm and 6 m, corner 200 sqm and 8 m. Bungalow site coverage is 50% with a 40% sub-control outside GCBA, and 45% with 35% within; terrace houses have no site coverage control.
Decide whether it is A&A or reconstruction. Rule: A&A stays within three 50% limits (added GFA, replaced external walls, structural floor changes) with no added storey and no change of housing form. Anything beyond is reconstruction, which must meet all current guidelines. Read: A&A vs reconstruction vs rebuild.
Understand what you may keep. Rule: URA may allow approved non-conforming parts to stay if at least 25% of the floor plate is retained as an integrated wing, a PE certifies the retained structure is sound, and, where the front setback is deficient, a minimum absolute 2.4 m setback is provided. Unauthorised parts cannot be retained under lodgment.
Respect setbacks. Rule: the road buffer is 24 m on Category 1 roads, 12 m on Category 2 and 7.5 m on Category 3, 4, slip and Category 5 roads; common boundary setbacks are 2 m outside GCBA and 3 m within or abutting it (URA setback pages, last updated 6 November 2026).
Choose lodgment or application. Rule: a QP can lodge a single landed house on residential land outside Conservation Areas, GCBAs and Special Control Areas, and planning approval is deemed granted on URA's acknowledgement, valid for 2 years and extendable twice. Other cases need a development application, where written permission is valid for 2 years. Read: URA written permission.
Investigate the ground before designing. Rule: Building Control Regulations 2003, regulation 31, requires the QP for structural works to carry out proper and adequate site investigation where foundations or excavations are proposed. Read: soil investigation.
Plan any basement against the excavation thresholds. Rule: excavation up to 1.5 m needs no plan approval, 1.5 m to 4 m needs a QP, above 4 m a QP and an Accredited Checker, and over 6 m it is geotechnical building works (BCA ERSS requirements, June 2026). Read: basements in landed houses and ERSS thresholds.
Follow BCA's sequence with one QP. Rule: URA written permission comes before building plan approval; structural plans without an Accredited Checker take 7 working days and the permit 7 working days; houses not exceeding 3 storeys need no Accredited Checker under the Fourth Schedule. BCA has advised since 2017 that landed developments adopt a single QP for all works (APPBCA-2017-05). A single house can stay on CORENET 2.0. Read: QP submission step by step.
Prepare demolition and neighbours. Rule: BCA requires a pre-construction survey within at least 10 m of a landed building being demolished, 10 m or 20 m for piling depending on pile type, and at least 15 m for excavation; MOM requires an asbestos survey where the building was built before 1 January 1991; the revised code SS 557:2026 is expected for projects whose URA planning application is made on or after 1 December 2026. For terrace and semi-detached houses, the builder must notify BCA before concreting any new RC wall abutting a party or boundary wall. Read: demolition guide, asbestos before demolition and party walls.
Close with TOP and CSC. Rule: BCA processes TOP and CSC in 7 working days each from complete documents; for owner-built landed houses the QP submits an inspection report or checklist; occupying without TOP or CSC is an offence under section 12 of the Building Control Act 1989. Read: TOP and CSC.
Which dated changes affect a rebuild?
1 December 2024: URA moved bungalows to a two-tier site coverage control (circular URA/PB/2024/05-DCG), for applications from 1 March 2025.
1 April 2025: lodgment widened to any existing landed house on residential land outside Conservation Areas and GCBAs (URA/PB/2025/05-DCG).
2 June 2026: BCA adopted SS 557:2026 for demolition (APPBCA-2026-09).
23 July 2026: CORENET X mandatory for new projects of 5,000 sqm GFA and above from 1 October 2026; smaller projects can stay on CORENET 2.0 for now.
6 November 2026: URA updated its setback and locational criteria pages; ask your QP to check the live pages.
What about timeline and cost?
No authority sets durations for design, tender or construction, so see the landed house rebuild timeline for the official clocks and typical delay causes. For cost, read what drives the budget. These are indicative points for context, not a benchmark or a quotation. Every project is different, so ask for a written quotation based on your drawings and scope. Also see who you need to rebuild.
What has not changed
Reconstruction, an added storey or a change of housing form must comply with every prevailing guideline.
Only a PE in the civil or structural discipline can apply for structural plan approval.
Works need approved plans and a permit; unauthorised building works carry a fine of up to $200,000, imprisonment of up to 2 years, or both.
The full process is in the landed house rebuild guide and the handbook hub.
Common mistakes
Starting as A&A and replacing slabs and walls until the 50% limits are crossed without a fresh submission.
Assuming a non-conforming setback can stay without the 25% wing and PE certification.
Adding a roof terrace or attic that becomes an additional storey.
Designing a basement before the ground is known. See buying an old landed house to rebuild.
Retaining a party wall without checking its condition, since it is part of the neighbour's structure too.
FAQ
Do I need URA approval to rebuild my landed house?
Yes, but for a single house on residential land outside Conservation Areas and GCBAs a QP can usually lodge the plans and planning approval is deemed granted on URA's acknowledgement.
Does a landed rebuild need an Accredited Checker?
Not for a house of up to 3 storeys, but a basement excavation or ERSS deeper than 4 m needs one.
Can I rebuild my terrace house into three storeys?
Only if your plot is in a 3-storey area on URA's Designated Landed Housing Area Plan or outside designated areas and street block plans.
Is CORENET X compulsory for a landed house?
No. It is mandatory only for new projects of 5,000 sqm GFA and above from 1 October 2026.
Do I have to tell my neighbours?
BCA requires a communication plan for landed developments, including notifying neighbours and requesting consent for access where necessary, plus a pre-construction survey.