To rebuild a landed house in Singapore you need, at minimum, a Qualified Person to submit plans (a registered architect or a Professional Engineer with a practising certificate), a Professional Engineer in the civil or structural discipline for the structural plans, and a builder licensed by BCA. As the owner you are the "developer" under the Building Control Act 1989, which means you apply for the BCA permit jointly with the QP and the builder and carry legal duties of your own. Most projects also involve a registered surveyor, M&E engineers and often a quantity surveyor; an Accredited Checker is needed only in specific cases, such as excavations deeper than 4 m.

This article explains each role, when it is mandatory, and how to verify each party. It is part of our landed house rebuild guide.

What is the owner's role as "developer"?

The owner of a private house who carries out building works is the developer for the purposes of the Building Control Act, and BCA expects developers to take an active part. BCA's permit to carry out structural works must be applied for jointly by the developer, the QP and the builder (BCA permit page, last updated 21 October 2026). Section 8(3) of the Act requires the developer to notify the Commissioner of Building Control of any contravention relating to the building works that the developer knows or ought reasonably to know of (quoted in BCA advisory APPBCA-2024-21, 2 December 2024). BCA advises developers to stay informed of progress, attend site meetings, check that the site is ready before requesting TOP or CSC inspection, and keep proper records. Carrying out building works without approved plans or a permit carries a fine of up to $200,000 and/or up to 2 years' imprisonment.

What does the architect do as QP?

The architect usually designs the house and acts as the QP for planning and building plan submissions. A QP must be registered with the Board of Architects as an architect, or with the Professional Engineers Board as a PE, and hold a valid practising certificate (BCA building plan page, last updated 6 July 2026). The QP lodges or applies to URA, which for a single landed house is often a lodgment with deemed planning approval, prepares building plans for BCA, coordinates the technical agencies, and applies for TOP and CSC on behalf of the developer. URA's lodgment pages state that a registered architect or engineer may submit, and that a QP must be appointed for the works (last updated 13 July 2026).

What does the structural engineer do?

The civil or structural PE designs the structure, foundations and any earth retaining system, and is the only person who may apply to BCA for structural plan approval. BCA states that only a QP who is a registered PE in the civil or structural discipline can apply for structural plan approval (BCA structural plan page, last updated 20 August 2026). For a landed rebuild that includes demolition plans, piling or footings, the basement ERSS if any, retaining walls, and the frame. The engineer also commissions site investigation, which regulation 31 of the Building Control Regulations 2003 requires where foundations or excavations are proposed, and certifies retained structure where URA's rules require PE certification.

BCA has advised since 2017 that landed property developments adopt a single QP for all works, including permanent structures, ERSS, barriers and any other works needing PE endorsement, because separate QPs for each element created safety gaps at the interfaces and could delay TOP (BCA circular APPBCA-2017-05). See PE endorsement explained.

Do I need M&E engineers?

M&E engineering covers electrical, plumbing and sanitary, air-conditioning and mechanical ventilation, lifts and lightning protection. PEB registers Professional Engineers in the civil, electrical, mechanical and chemical branches. BCA's TOP and CSC document list includes certificates of supervision for the lightning protection system and for air-conditioning and mechanical ventilation systems where installed, and a QP declaration that any lift has its Permit to Operate. How M&E design is procured for a landed house varies; agree in writing who designs and certifies each system.

What do the quantity surveyor and registered surveyor do?

A quantity surveyor prepares cost estimates, tender documents, bills of quantities and valuations, and has no statutory role, so appointing one is the owner's choice. A registered surveyor is different: URA requires the lodgment proposal plan to be a true cadastral and topographical representation of the land, and boundary and level information comes from a land survey. The Land Surveyors Board publishes the list of practising registered surveyors and licensed survey firms under the Land Surveyors Act 1991 (LSB, last updated 16 April 2026).

What licence does the builder need?

The main contractor must hold a BCA general builder licence for building works whose plans require approval by the Commissioner of Building Control. BCA's Builders Licensing Scheme (last updated 27 March 2026) sets:

  • Class 1 General Builder: projects of any value; minimum paid-up capital of $300,000 for corporations.

  • Class 2 General Builder: projects of $6 million or less; minimum paid-up capital of $25,000.

  • Specialist builder licences for piling, ground support and stabilisation, instrumentation and monitoring, structural steelwork, precast concrete and in-situ post-tensioning, required for those works of any value.

Each licensed builder must appoint an Approved Person to manage the building works and a Technical Controller to oversee their execution. Licences are valid for up to three years.

Who supervises the works on site?

The QP appoints site supervisors during the permit application, and for a typical landed house the appropriate QP, a resident engineer or a resident technical officer provides immediate supervision. BCA's rule is that works valued up to $7.5 million need immediate supervision by the appropriate QP, an RE or an RTO, while larger works need full-time REs and RTOs (BCA site supervisor requirements, last updated 12 March 2026). Site supervisors must be accredited by the Joint Accreditation Committee of the Institution of Engineers Singapore and the Association of Consulting Engineers Singapore. See site supervision roles.

When is an Accredited Checker needed for a landed house?

A house of up to 3 storeys does not need an Accredited Checker for its structural design, but certain elements of a landed rebuild do. Under the Building Control Regulations 2003, Fourth Schedule, houses not exceeding 3 storeys and retaining walls or earth stabilising structures not exceeding a visible height of 4 m are exempt from AC checking. An AC is required where:

  • A basement excavation or ERSS is deeper than 4 m (and above 6 m it is geotechnical building works needing a QP(Geo) and AC(Geo)) (BCA ERSS submission requirements, June 2026).

  • A retaining wall exceeds a visible height of 4 m.

  • A&A works materially affect key structural elements, for example strengthening works (BCA structural plan page).

With an AC, BCA processes structural plans in 10 days for the first submission and 14 working days for later ones, against 7 working days without. See Accredited Checker requirements and ERSS thresholds.

Design and build or traditional for a landed home?

Both are used for landed houses, and the statutory roles stay the same in either: the owner remains the developer, and the QPs remain personally responsible for their plans. In the traditional model the owner appoints the architect and engineers, who design and tender to builders; the consultants work for the owner and check the builder. In design and build, one contractor provides design and construction and employs or appoints the QPs, which can be simpler but puts the design team on the builder's side of the contract. See design and build vs traditional and roles of the QP, builder and developer in design and build.

How do I verify each party?

Every regulated party can be checked on an official public register before you sign:

  • Architects: the Board of Architects' register of architects, with registration numbers and firms (last updated 23 September 2026).

  • Professional Engineers: PEB's directories of PEs with practising certificates, specialist PEs, licensed corporations and partnerships, and suspended or deregistered PEs (last updated 2 April 2026). See how to check a PE.

  • Builders: BCA's e-directory, which lists all licensed builders.

  • Accredited Checkers: BCA's registers of individual ACs, ACs in accredited checking organisations, and specialist ACs (geotechnical).

  • Surveyors: the Land Surveyors Board's list of practising registered surveyors.

Check that the PE's practising certificate is current and in the civil or structural discipline, that the builder's class covers your contract value, and that any piling subcontractor holds the specialist piling licence. See also costs and how fees are structured.

FAQ

Do I need an architect to rebuild a landed house in Singapore?

You need a QP, who may be a registered architect or a PE with a practising certificate. In practice most landed rebuilds use an architect for planning and building plans and a civil or structural PE for structural plans.

Can a contractor submit plans to BCA?

No. Plans are submitted by QPs. The builder joins the permit application and must be BCA-licensed.

Does my landed house need an Accredited Checker?

Not for a house up to 3 storeys, unless the project includes excavation or ERSS deeper than 4 m, a retaining wall over 4 m visible height, or A&A that materially affects key structural elements.

What builder licence is needed for a landed rebuild?

A BCA general builder licence: Class 2 for projects up to $6 million, Class 1 for any value. Piling and other specialist works need the relevant specialist licence.

Who is responsible if something goes wrong on site?

The QP, the builder and the developer each have duties under the Building Control Act. The owner as developer must notify BCA of contraventions they know or ought reasonably to know of.

Who applies for TOP and CSC?

The project's QP appointed by the developer applies to BCA, with clearances from URA, LTA, NParks, SCDF, PUB and NEA.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly. See our PE endorsement services or WhatsApp +65 9342 7551. Last reviewed: November 2026.