PE Endorsement for Hoarding and Signboards in Singapore
Updated: Nov 12
A hoarding, signboard or advertising structure in Singapore needs a Professional Engineer (PE) when it is large enough to require a Permit to Use (PTU) as a temporary building from the Building and Construction Authority (BCA). For a free-standing frame, panel, hoarding or board, that point is reached when any part is 4 metres or more above the surface it stands on, or its largest side exceeds 10 square metres. Large banners need PE certification too. Smaller signs may need only a BCA advertisement licence, or nothing at all if they fall within the 5 square metre signboard exemption.
Two separate BCA controls: the licence and the structure
The advertisement licence controls the display itself: what is shown, where, and how large. It is applied for through BCA's Advertisement Licensing System.
The temporary building permit and PTU control the supporting structure: whether the frame, its fixings and its foundation are safe. This is where the PE comes in.
A large sign needs both, and BCA requires the PTU to be valid for the entire period the sign is displayed.
When is a BCA advertisement licence needed?
BCA requires a licence to display an outdoor advertising sign or signboard. "Outdoor" includes any roofed space that is not fully enclosed on all sides and is accessible to the public or to general pedestrian traffic. A signboard relates to the premises it is fixed to. An advertising sign promotes goods, brands, services or events.
BCA lists these as not needing a licence:
A single signboard, or a series of related signboards, with a total area of not more than 5 square metres. The applicant must submit a declaration form for this exemption.
Signboards displayed by a religious body, a government-aided school, or a charity-run hospital, clinic, nursing or welfare home.
Signs on stalls in hawker centres, food centres or markets.
Signs in underpasses, tunnels or MRT stations.
BCA states that it typically takes 7 working days to assess a complete application, and that evaluation by the Urban Redevelopment Authority (URA), where needed, may add about two weeks. The application must include an elevation showing the sign's dimensions and a sectional view showing the fixing method and materials, so that BCA can see the sign is structurally safe to display.
When does a sign or hoarding need a PE and a Permit to Use?
BCA's definition of a temporary building includes any structure used only for the outdoor display of an advertisement or signboard. Its examples include free-standing frames, panels and hoardings, outdoor signs and their supporting structures. According to BCA's guidance, a PTU is required when either of these applies:
The advertising sign or signboard exceeds 10 square metres in area and is supported by an advertising structure.
The structure exceeds 10 square metres, or its highest point is 4 metres or more above the surface it stands on.
Put the other way, a standalone frame, panel, hoarding or board is exempt from the PTU only if every part of it is less than 4 metres above the plane it stands on and its largest side is 10 square metres or less. BCA adds that even exempt structures remain subject to certain provisions of the Building Control (Temporary Buildings) Regulations 2018.
Banners have their own rule. BCA requires PE certification, shown on the structural drawings, for a banner that exceeds 30 square metres, or one that exceeds 10 square metres and is displayed with bars or rods.
What does the PE do under the temporary building rules?
The owner must engage a PE to design the structure, supervise its erection and inspect it. BCA sets out the sequence:
The application is submitted through BCA's electronic submission system and must reach BCA at least 3 weeks before construction is scheduled to start.
BCA grants preliminary approval of the plans, after which erection may begin.
The PE supervises the works, keeps records of materials and ensures the prescribed tests on concrete, reinforcement, structural steel and welding are carried out.
Within 7 days after completion, the PE provides the certificate of supervision. BCA then processes the PTU.
The structure may be used only after the PTU is granted.
The PTU fee is $200 per structure where there is no measurable floor area. A temporary building is generally permitted for up to 36 months. When the approval lapses or the PTU expires, the structure must be demolished within 14 days and BCA notified within 7 days after demolition.
The engineering itself is mostly about wind: overturning and sliding of the base, the strength of posts and connections, and the capacity of whatever the structure is fixed to. For the wider picture on temporary works, see temporary structure endorsement for scaffolding and formwork.
What about construction site hoardings?
Protective structures in public places or on public roads, such as protective hoardings, catch platforms, fences and safety netting, are on BCA's list of temporary buildings that do not require a PTU. That exemption is not a relaxation of the safety duty. The Building Control Regulations place the duty on the builder to erect protective hoardings of solid and robust construction before starting works that could obstruct or endanger the public, to maintain them, and to remove them on completion. This is why builders commonly ask a PE to design tall hoardings and noise barriers even where no PTU is required.
Once a hoarding carries advertising, it is being used for outdoor display, and the licence and size thresholds above should be checked. Scaffolds erected behind the hoarding follow separate MOM rules, set out in PE endorsement for scaffolds.
Which authority and regulation governs what?
BCA, advertisement licensing: outdoor advertising signs and signboards, including fees and annual renewal.
BCA, building control: the Building Control (Temporary Buildings) Regulations 2018 for supporting structures, and the Building Control Regulations for protective hoardings and for insignificant building works.
URA: outdoor sign guidelines on location, size and form. For areas outside the Central Area, URA's guidelines state that planning permission is not required for outdoor signs and that applications go to BCA, but signs on conservation buildings and National Monuments need URA clearance first.
Common mistakes
Measuring only the sign face. The thresholds apply to the structure as well, and the 4 metre trigger is measured to the highest point.
Assuming a licence covers the structure. A licence application for a large sign is not accepted without a PTU covering the whole display period.
Fixing over footpaths without clearance. BCA requires signs over a footpath or verandah-way to be at least 2.5 metres above it.
Proposing sign types that are not allowed. BCA's guidelines prohibit signs above roofs or roof parapet levels and free-standing signs promoting brands, products or services.
Building without approval. If the structure should have been approved and was not, the remedy is regularisation of unauthorised works.
FAQ
Does a small shop signboard need a PE?
Usually not. Signboards totalling not more than 5 square metres are exempt from licensing with a declaration, and a PTU is only triggered by the 10 square metre and 4 metre thresholds.
Does a construction hoarding need a Permit to Use?
Protective hoardings in public places are exempt from the PTU, but the builder must still make them solid and robust.
Can any engineer endorse the structure?
No. BCA requires the owner to engage a professional engineer to design, supervise and inspect the structure. See how to check a Professional Engineer.