There is no single "PE endorsement form" in Singapore. A Professional Engineer (PE) endorses whatever document the receiving party requires, and each agency has its own: HDB issues a renovation permit with conditions for the PE, BCA uses structural plan application forms and standard certificates on CORENET, SCDF has a lodgement e-form for minor works, JTC has self-declaration forms, and an MCST usually wants the certification wording from BCA's 2014 advisory on the renovation plan. Where no agency form exists, the endorsement takes the form of signed and stamped drawings, calculations and a letter or certificate.

This article lists the real forms by situation, then gives a checklist of what to send an engineer before asking for a quotation and what you should receive back. It is part of our PE endorsement guide.

Is there a standard PE endorsement form?

No. "PE endorsement" describes an act, not a document: a registered engineer with a practising certificate takes professional responsibility for specific drawings, calculations or works by signing and stamping them. The form it takes depends on who asked for it. The Professional Engineers Board states that a person who engages in professional engineering work in the prescribed branches must be a registered professional engineer with a practising certificate in force, or work under the direction or supervision of one. What that engineer signs is set by the agency, landlord or MCST receiving it.

So the first question is who is asking for the endorsement and what exactly they asked for. For the underlying idea, see PE endorsement meaning.

Which forms apply to hacking a wall in an HDB flat?

HDB's process runs on an electronic renovation application made by the contractor, not on a PE form submitted by the owner. HDB's pages name these documents:

  • Acknowledgement form: signed by the flat owner and attached by the contractor to the electronic application.

  • Floor plan showing the proposed work: required for works such as demolition of walls. HDB sells the flat's floor plan for $5 through its Purchase of Residential Floor Plan e-Service if the owner no longer has the sales brochure copy.

  • Renovation permit: HDB's written approval, with conditions.

  • Notice of Renovation: displayed outside the flat until the works are complete.

Where the work is demolition of non-load bearing reinforced concrete elements, HDB requires a PE in civil or structural engineering to supervise, and requires a copy of the approved plan and the conditions of approval to be given to that PE. HDB's guideline pages do not name a specific PE form, so use the paperwork HDB issues or asks for on the job. Details are in PE endorsement for wall hacking in HDB flats and condos.

What does an MCST expect for condo renovation?

An MCST following BCA's advisory of 14 January 2014 expects the renovation plan itself to carry the PE's certification. The advisory's Annex A gives the sample wording, titled "Standard Certification by the Professional Engineer for Renovation Works Involving Demolition of Non-Structural Elements". In it the PE states that they have personally checked the approved structural plan and inspected the structural condition of the building or unit, and certifies that no structural element will be altered or demolished in the proposed renovation works. It is signed, stamped and dated.

Which BCA forms and certificates does a structural submission use?

A structural plan submission to BCA is made by a Qualified Person on CORENET using BCA's application form and standard certificates. BCA's structural plan submission page lists:

  • Application form for structural plan approval: Form BCA-BE-STAPPV01 (BEV/A1)

  • One set of detailed structural plans signed by the QP for structural works, with the first and last sheets endorsed with BCA's standard certification by the Qualified Person (Appendix B). In it the QP certifies that the plans and design calculations were prepared by them in accordance with the Building Control Act, the Building Control Regulations and other applicable requirements.

  • For additions and alterations where structural stability or integrity is not affected: plans endorsed by a PE with the additional certificate in Appendix D, stating that the engineer has inspected the existing building and investigated its overall structure and that, in their opinion, the building and its foundation can resist the forces altered by the works.

  • Where an Accredited Checker is required: the Accredited Checker's Certificate, Form BCA-BE-STAPPV01-ACC (BEV/A2), the checklist Form BCA-BE-ACCHECKLIST (BEV/A3), and the AC's evaluation report.

At completion, BCA's TOP and CSC page requires the Certificate of Supervision of Building Works (form BPD_CSC02 or e-form BCA-CSC-CSPBW) and the Declaration by Qualified Person for the application (form BPD_CSC07 or e-form BCA-CSC-CSCDQP), along with the builder's certificate of completion. Only a QP who is a PE in the civil or structural discipline can apply for structural plan approval. The whole sequence is in QP submission step by step, and the difference between the two roles in PE endorsement vs QP submission.

What forms apply to temporary buildings, scaffolds and other temporary works?

For a temporary building, BCA requires the owner to engage a civil or structural PE and the Permit to Use is granted on the PE's certificate of supervision. BCA's temporary building page describes two stages:

  • Preliminary approval: the owner applies and submits plans through the PE on CORENET e-Submission. BCA must receive the application at least 3 weeks before the scheduled construction.

  • Permit to Use (PTU): after construction, the owner submits the professional engineer's certificate of supervision for the building works for the temporary building (Form BCA-CSC-CTSTBW) and, where applicable, the certificate of supervision for the lightning protection system.

For scaffolds there is no BCA form, because scaffolds fall under MOM's Workplace Safety and Health (Scaffolds) Regulations. MOM's scaffold FAQ lists the scaffolds that need a design by a PE, including metal scaffolds exceeding 30 metres in height outside shipyards, scaffolds on cantilever or jib supports, and hanging scaffolds from which a person may fall more than 2 metres. The Regulations also require the PE to examine such a scaffold after erection and certify it safe for use, and to inspect it at least every 3 months. The PE's output is a set of design drawings and calculations and a certificate. Details are in PE endorsement for scaffolds.

What does SCDF's minor additions and alterations lodgement need?

SCDF's Minor A&A lodgement is made by a Qualified Person on CORENET with e-form MAACFSW.XFD and the final plan, before the works start. SCDF's page states:

  • The lodgement scheme applies only to the minor alterations or additions listed in the Schedule to the fire safety regulations.

  • The plans are lodged by a registered architect or a PE (civil, structural, mechanical or electrical).

  • The fee is $90 per submission.

  • The QP endorses the title block of the plan, certifying that the works have been satisfactorily completed on a stated date and whether they affect the existing fire protection systems.

  • The applicant or tenant must seek consent from the building owner or management corporation before carrying out the works.

Larger fire safety works need plan approval and a Fire Safety Certificate. See the fire safety jargon guide.

What does JTC ask for?

JTC requires its consent as landowner for development or renovation works on JTC land and buildings, and it uses self-declaration forms. JTC's plan consent pages name:

  • For submissions by a Qualified Person: the self-declaration form "JTC_LPD_SD.XDFX", downloaded from the CORENET electronic submission software for professionals under form templates for JTC plan consent, and a letter of declaration for plan consent (SD-LD), stamped and signed by the lessee or tenant.

  • For submissions without a Qualified Person: the self-declaration form "JTC_LPD_SD_NonQP.XDFX" from CORENET 2.0, with the declaration page stamped and signed by the lessee or tenant.

JTC states that if the authorities require a QP's endorsement for the project, the submission must be made by a QP. See JTC factory renovation.

What should you send an engineer before asking for a quotation?

Send enough for the engineer to know what exists, what is proposed and who needs the endorsement. A complete enquiry contains:

  1. Address and unit number, and the type of premises (HDB flat, condo unit, landed house, shop, factory unit).

  2. Who is asking for the endorsement and their exact words: the HDB letter, the MCST renovation form, the landlord's fit-out guide, the main contractor's requirement or the agency's written direction.

  3. Drawings or sketches with dimensions: existing layout, proposed layout, and the elements to be removed, added or loaded.

  4. Photos of the area, including ceilings, beams and columns nearby.

  5. Existing approved plans. Structural and building plans can be bought from BCA's plan purchase system by the registered proprietor, the MCST chairman or a person they authorise, with a current property tax statement as proof of ownership. HDB sells flat floor plans. Our guide on how to buy approved plans has the steps.

  6. The proposed works and loads: what is being built, the weight and footprint of any equipment, racking, tank or platform, and manufacturer's data sheets.

  7. Landlord, MCST or JTC requirements, including any standard forms they want signed.

  8. Timeline: when works are meant to start, and any dates already fixed with the contractor or the estate.

  9. History: earlier renovation, known unauthorised works, cracks or leaks.

Without items 2 and 5 an engineer can only guess the scope. For what drives fees, see our cost article.

What should you receive back?

You should receive documents that identify the engineer, the work and the basis of the endorsement. For most endorsements that means:

  • Endorsed drawings, each sheet signed, stamped and dated by the PE, showing the works exactly as they are to be built or demolished

  • Calculations or an engineering assessment supporting the drawings, where the work has structural effect

  • The letter, certificate or agency form the receiving party asked for, in their wording

  • Conditions and limits: what the endorsement covers, what it assumes, and what would require the engineer to be called back

  • A record of the site inspection, with date and observations

  • For supervised works, an inspection or completion record after the works

Check the engineer's name and branch against the PEB directory. The steps are in how to check a Professional Engineer, and what the stamp shows is in PE stamp and PE chop in Singapore.

Common mistakes

  • Asking for "the PE form" without saying who wants it.

  • Expecting an endorsement of drawings the engineer has not checked against the approved plans or the site. BCA's own sample certifications record a personal check and inspection.

  • Changing the works after the endorsement. BCA requires approval before material changes to approved structural plans are built, and the same logic applies to a private endorsement: the stamp covers what was drawn.

FAQ

Where can I download a PE endorsement form?

There is no universal form. Download the form of the agency or party asking for the endorsement, such as BCA's structural plan forms on CORENET or JTC's self-declaration form, or use the certification wording they specify.

Who can sign a PE endorsement?

A registered professional engineer with a practising certificate in the branch that covers the work. For structural drawings that is a PE in the civil or structural discipline.

What documents does a PE need to endorse wall hacking?

The floor plan or approved structural plan, the proposed layout marking the walls to be removed, photos, and the HDB or MCST requirement. The PE also needs to inspect the unit.

Is a PE endorsement letter the same as BCA approval?

No. An endorsement is the engineer's certification. BCA approval is a decision of the Commissioner of Building Control on a submission made by a Qualified Person. See when PE endorsement is required.

How long does it take to get a PE endorsement?

It depends on how quickly the approved plans can be obtained and a site inspection arranged. Where BCA approval is needed, BCA's service standard for structural plans without an Accredited Checker is 7 working days after complete documents are submitted.