PE Endorsement for Scaffolds in Singapore: When a Professional Engineer Is Required
Updated: Nov 12
Not every scaffold in Singapore needs a Professional Engineer (PE). Under the Workplace Safety and Health (Scaffolds) Regulations 2011, a PE design is required for specific higher-risk cases: metal scaffolds above 30 metres (15 metres in a shipyard), scaffolds on cantilever or jib supports, hanging scaffolds, heavily loaded work platforms and the overhead supports of suspended scaffolds. Other scaffolds can be built to standard configurations by trained erectors, in most cases under an approved scaffold contractor.
Which scaffolds need a PE design?
The Ministry of Manpower (MOM) publishes the list of scaffolds that require design by a PE. In summary:
Work platforms used to provide footing for more than 2 persons in a bay, or to support tools and materials exceeding 25 kg in a bay.
Metal scaffolds supporting more than 4 persons in any bay, up to a maximum of 8 persons.
Metal scaffolds exceeding 30 metres in height, or 15 metres in a shipyard.
Scaffolds erected on cantilever or jib supports.
Outriggers or other overhead supports for a suspended scaffold whose work platform is supported by wire ropes.
A suspended scaffold and its attachments that have been re-positioned or shifted to another location in the same workplace.
Suspended scaffolds manufactured outside Singapore, whose design must be certified by a PE or by a third-party inspection agency approved by the Commissioner for Workplace Safety and Health.
Ties for timber scaffolds that are not the standard arrangement passing through an opening in the wall.
Hanging scaffolds from which a person may fall more than 2 metres.
Trestle scaffolds with more than 3 tiers, or with a work platform more than 4.5 metres above the surface they stand on.
For tower scaffolds, MOM states that PE endorsement is not mandatory except for the special applications in the list above.
What does the PE actually do?
The duty is more than stamping a drawing. For metal scaffolds above the height thresholds, regulation 30 of the Scaffolds Regulations requires that:
The scaffold is erected in accordance with the design and drawings of the PE.
The PE examines the scaffold after erection and issues a certificate stating that it is safe for use.
The certified design, drawings and certificate are kept at the workplace for inspection.
A PE inspects the scaffold at least once every 3 months.
For cantilever or jib supports, MOM explains that the supports must be built to the PE's design documentation (calculations, drawings and construction procedures) and that the supports, together with the scaffold they carry, must be examined by a PE and a certificate issued before use.
MOM is also clear about site deviations. A scaffold designed by a PE must be constructed in accordance with that design. The PE's certificate of supervision is a second assurance of safety and is not a way to reconcile differences after the fact. Where a deviation could affect strength, stiffness or stability, the scaffold must be redesigned and the revised documents issued before work continues.
What changed for suspended scaffolds (gondolas) in 2025?
On 10 January 2025, MOM and the Building and Construction Authority (BCA) issued a joint circular on outriggers and overhead supports for suspended scaffolds. Its main requirements are:
All outriggers or other overhead supports must be designed by a PE, with detailed drawings and calculations.
The design must confirm that the supporting structure can take the added load. Existing structural drawings should be referenced and verified on site. If information is missing, the PE must check the structure, for example by concrete core tests or non-destructive tests.
Supports must not be designed to sit on brick or block masonry parapets, thin walls or sloping parapet walls unless the PE has verified their strength and integrity.
Tie-backs must not touch or be anchored to roof installations such as M&E services.
The PE endorses a site-specific layout plan, inspects the installed supports and issues a Certificate of Inspection.
The Authorised Examiner must not certify a suspended scaffold that has no PE design, and only an approved scaffold contractor may install it.
Because a gondola is also registrable lifting equipment, this overlaps with the rules in our article on PE endorsement for lifting operations.
Who else must be involved besides the PE?
Approved scaffold contractor (ASC): required to construct, erect, alter or dismantle scaffolds, except tower scaffolds, trestle scaffolds and scaffolds less than 4 metres high at the uppermost lift (excluding handrails).
Scaffold erectors and scaffold supervisor: all scaffolds, including the excluded types, must be erected by trained erectors under the immediate supervision of a trained scaffold supervisor.
Scaffold supervisor's inspection: a scaffold must be inspected on completion and then at intervals of not more than 7 days, or after weather likely to have affected it, with results entered in a register. MOM's guidance excepts trestle scaffolds and scaffolds from which a person is not liable to fall more than 2 metres.
How these roles sit alongside the site team on a building project is explained in site supervision for structural works.
Which authority and regulation governs what?
MOM administers the Workplace Safety and Health (Scaffolds) Regulations 2011. The Workplace Safety and Health (Work at Heights) Regulations also apply to all work-at-height activities.
Singapore Standards give the technical detail: SS 659:2020 (Code of Practice for Scaffolds) and SS 598:2014 (Code of Practice for Suspended Scaffolds).
BCA co-issued the 2025 suspended scaffold circular because the supports load the building structure.
Scaffold material used as a support structure, such as an event backdrop or LED wall frame, is not a scaffold under the Scaffolds Regulations. MOM notes that BCA regulations may apply instead. See PE endorsement for hoarding and signboards for the temporary building rules.
Under the Scaffolds Regulations, a professional engineer is a person registered under the Professional Engineers Act. You can confirm this using our guide on how to check a Professional Engineer.
Common mistakes
Treating 4 metres as the PE threshold. The 4 metre figure decides whether an approved scaffold contractor is needed. PE design depends on the list above.
Building first and engineering later. MOM does not accept a certificate issued to paper over a scaffold that differs from the design.
Reusing a design at a new location. MOM advises consulting the PE, because foundation conditions and tie-back points differ from site to site.
Fixing gondola outriggers to parapets nobody has checked. The 2025 circular illustrates inadequate design, departures from the layout plan and unsafe installation as the three typical failures.
Overloading platforms. MOM states 220 kgf per square metre as the maximum loading on a metal scaffold work platform, and only where it is so designed.
FAQ
Does every scaffold above 4 metres need PE endorsement?
No. From 4 metres an approved scaffold contractor must take charge, but a PE design is needed only for the listed cases, such as metal scaffolds above 30 metres or scaffolds on cantilever supports.
Do tower scaffolds need a PE?
Not as a rule. MOM's guidance adds that SS 659:2020 limits aluminium tower scaffolds to 12 metres indoors and 8 metres outdoors.
How often must a scaffold be inspected?
By the scaffold supervisor at intervals of not more than 7 days. Metal scaffolds that require PE design must also be inspected by a PE at least once every 3 months.