Micropiles and Jack In Piles in Singapore: Foundations for Restricted Sites
Micropiles and jack-in piles are the two foundation types most often chosen in Singapore when a normal piling rig cannot be used: inside existing buildings, under low headroom, on narrow landed-house plots, and next to neighbours where noise and vibration must stay low. A micropile is a small-diameter drilled and grouted pile that removes soil as it is formed. A jack-in pile is a preformed pile pressed into the ground by a hydraulic jack, which displaces soil but gives a force reading on every pile. This article explains how each works, where each fits, and what BCA's circulars and the local pile practice guidelines require. It is part of our geotechnical engineering guide.
What is a micropile, and how does it work?
A micropile is a small-diameter bored pile in which a steel bar, bundle of bars or steel pipe is grouted into a drilled hole, and the steel carries most of the load. Load passes from the steel to the grout and from the grout to the ground, mainly by friction along the shaft, so capacity comes from the bonded length in competent soil or rock more than from the small base.
Three features make it useful on restricted sites. The drilling rig is compact and can work under a ceiling or beam. The drill can core through existing footings, slabs and obstructions. And because the pile is a non-displacement type, it causes very little ground heave or lateral soil movement. The local practice guidelines for piles (18 January 2022) contain one specific micropile provision: where steel reinforcement is counted in the structural capacity, as in a micropile, the design axial capacity is divided by a factor of 1.5 to account for geometric imperfections and nominal eccentricity in a bored cast-in-place pile.
What is a jack-in pile, and how does it work?
A jack-in pile, also called a jacked or pressed pile, is a preformed pile pushed into the ground by a hydraulic jacking system reacting against dead weight on the machine. The GeoSS guide Good Practice for Installation of Jacked Foundation Piles in Singapore (8 October 2015), listed on BCA's guidelines page, describes the preformed sections as prestressed spun piles, precast reinforced concrete piles or steel H-piles, joined by welding as they go down.
The guide describes the method as vibration free, free of air pollution and low in noise, with good pile verticality and some form of load testing performed on every pile during installation. It records jacking machines of up to 800 tonnes capacity in Singapore and recommends using a machine up to about 75% of its maximum capacity. The limitation is weight and size: the machine needs a firm, well-drained platform and room to stand over each pile position, which can rule it out along a boundary wall or indoors.
Where are micropiles and jack-in piles used?
Both are used where access, headroom or neighbours rule out conventional bored or driven piling, but they suit different constraints.
Underpinning: micropiles are drilled beside or through an existing footing to transfer its load to deeper ground.
Low headroom: micropile rigs work inside basements, factories and under existing floors, with reinforcement installed in short coupled lengths.
Additions and alterations to existing buildings: new columns, lift pits, extra storeys or heavier equipment often need added foundations inside a building in use. See the additions and alterations guide and machine foundations and floor loading.
Near neighbours: jack-in piling avoids the hammer noise and vibration of driven piles, which is why it is widely used for landed houses and infill sites.
For the general comparison of pile types see foundation design in Singapore.
How is jacking force used as an installation check?
The jacking force recorded at the end of installation is the termination criterion for a jack-in pile: the pile is accepted when it has been pressed to a specified multiple of working load and stops moving. The 2022 local practice guidelines state that jacked-in displacement piles shall be installed based on 2.25 times working load. The GeoSS guide describes the procedure used in Singapore:
The pile is jacked in steps to a force of 2 to 2.5 times working load until practical refusal.
The force is released to zero and re-applied, and the downward movement between cycles is the set.
The pile is considered set if movement does not exceed 5 mm with a holding time of at least 30 seconds, and two consistent sets are recommended.
The load cells measuring jacking force must be calibrated by an accredited laboratory before the first jack at each site or every 6 months, whichever is shorter.
The termination criterion should itself be verified by a maintained load test, and revised if the test does not confirm it.
BCA circular APPBCA-2022-15 (1 September 2022) requires the Qualified Person (QP) to specify the termination criteria on the piling plan, namely jacked load, holding time and set movement. Two corrections matter. Soil above the pile cut-off level adds friction during jacking that will not exist later, and soft clay that helps during jacking can reverse into negative skin friction in the long term, so both must be allowed for in the jacking force. If a pile reaches its criterion but is more than 20% shorter than the approved length, it is a major deviation and an amendment plan must be submitted.
Do jack-in piles affect neighbouring buildings?
Yes, they can: jack-in piles are displacement piles, and the soil they push aside moves toward adjacent structures. The GeoSS guide records that jacked piling has caused damage to adjacent buildings, particularly in landed developments where structures are close together. It lists the unfavourable conditions as a high density of piles, thick soft clay, neighbours in close proximity, neighbouring buildings on footings over soft clay, and the weight of the machine itself. The protective measures it sets out are:
Relief wells, generally bored holes of 400 mm to 600 mm diameter, at the boundary beside neighbouring structures or services.
Pre-boring at the pile point, slightly smaller than the pile.
Monitoring of ground and building movement, with adjacent buildings not allowed to settle or heave by more than 25 mm as a common industry practice.
A temporary earth retaining wall where there is a sensitive adjacent structure, a trial on the first pile, or an open trench.
Where many of these conditions coexist, the guide says large displacement piling should be discouraged or avoided, and names non-displacement piles such as bored piles or grouted micropiles, or small-displacement steel H-piles, as the more favourable systems. APPBCA-2022-15 makes the impact assessment and the protective measures part of the plan submission. See impact assessment and pre-construction surveys.
What noise and vibration limits apply?
The National Environment Agency (NEA) limits construction noise at residential buildings within 150 m of a site to 75 dBA averaged over the 12 hours from 7am to 7pm, 65 dBA over any hour from 7pm to 10pm and 55 dBA over any hour from 10pm to 7am, on Mondays to Saturdays. A 5-minute limit of 90 dBA also applies in the daytime. Under NEA's no-work rule, sites within 150 m of residential buildings and noise-sensitive premises may not work from 10pm on Saturday to 7am on Monday, or from 10pm on the eve of a public holiday to 7am on the day after it.
These limits are the reason low-noise installation methods matter on infill sites. For vibration, the BCA permit conditions quoted in APPBCA-2022-15 require the builder to install adequate vibration monitoring devices before starting any piling works and to take precautionary measures to prevent excessive vibration or damage to neighbouring properties.
What testing is required?
Testing depends on building height. For buildings of 10 storeys or more and for buildings of 5 to 9 storeys with a footprint larger than 100 sq m, the joint circular APPBCA-2016-08 fixes minimum numbers of load tests. For other building works, the circular states that the Fifth Schedule of the Building Control Regulations applies and the structural plans must show how its requirements are met. The 2022 local practice guidelines add that for cases outside the 10-storey rule the QP assesses the need for an ultimate load test, and that a working load test should be carried out for projects with major building work.
Working load tests go to 1.5 or 2 times working load, with allowable pile-top settlement of 15 mm or 25 mm respectively. For jack-in piles, APPBCA-2022-15 classes all landed properties and all buildings up to 3 storeys as Type C, where pile heave monitoring is optional for a standalone building, and requires the QP to specify load tests or integrity tests on plan for assessing the structural integrity of the installed piles. Details are in pile load tests and pile integrity tests.
Which authority approves micropile and jack-in pile works?
BCA approves them as structural works under the Building Control Act 1989: new piles and underpinning are not insignificant building works, so structural plans by a QP and a permit are needed before work starts. Under the Fourth Schedule of the Building Control Regulations 2003, an Accredited Checker's certificate is not required for houses of not more than 3 storeys, or for alterations and additions that do not materially affect key structural elements. The governing technical documents are SS EN 1997-1 with its Singapore National Annex, the Guidelines on Local Practices for Pile Foundation Design and Construction (2022), APPBCA-2022-15 for jacked piles and the GeoSS good practice guide (2015). NEA governs construction noise. For the submission route see QP submission step by step.
How does this look on a landed house or an A&A project?
On a landed-house rebuild, the usual question is whether jack-in piles can be used beside neighbours on shallow footings. The engineer checks the thickness of soft clay from the boreholes, the distance to the neighbouring houses and the number of piles, and then either specifies jack-in piles with pre-boring, relief wells and settlement markers on the neighbours, or switches to bored piles or micropiles along the boundary.
On an additions and alterations project inside an existing building, the question is headroom and existing foundations. Micropiles are drilled through the existing slab, new pile caps are tied into the existing structure, and the engineer checks how the new piles share load with the older foundations. The local practice guidelines note that relative stiffness must be considered whenever new and existing piles work together in one foundation system. See retaining walls and slopes for landed houses for related landed-house rules and soil investigation in Singapore for borehole requirements.
What goes wrong?
Most problems come from treating the installation record as proof of long-term capacity. Typical cases are jack-in piles that reach the jacking force at a shallow depth on an intermediate hard layer and are accepted without review, piles lifted by the installation of their neighbours and not re-jacked, cracks in adjacent houses where relief wells or pre-boring were omitted, uncased relief wells that collapsed under the weight of the machine, and micropiles whose grout was not placed continuously so that the bonded length is shorter than designed.
FAQ
Are jack-in piles really vibration free?
The GeoSS guide describes the method as vibration free with low noise. It still displaces soil, so nearby ground and buildings can move even without vibration.
How do I know a jack-in pile has enough capacity?
By the recorded jacking force and set at termination, typically 2 to 2.5 times working load with movement not exceeding 5 mm over at least 30 seconds, verified by a maintained load test.
When should micropiles be chosen over jack-in piles?
When headroom or access is too limited for a jacking machine, when piles must pass through existing footings, or when neighbouring buildings are too sensitive to soil displacement.
Does underpinning need BCA approval?
Yes. Underpinning and new piles are structural works that need plan approval and a permit.
Do landed-house piles need load tests?
There is no fixed number for a house in APPBCA-2016-08. The QP must show that the Fifth Schedule requirements are met and specifies the tests on the piling plan.
Can piling work be done on Sundays near homes?
Not within 150 m of residential buildings, under NEA's no-work rule, unless a permit or exemption applies.
Sources
Guidelines on local practices for pile foundation design and construction, 18 January 2022
GeoSS: Good practice for installation of jacked foundation piles in Singapore, 8 October 2015
BCA: Guidelines for structural plan applications (index of circulars)
Building Control Regulations 2003, First Schedule and Fourth Schedule (Singapore Statutes Online)