Pile Load Tests and Pile Integrity Tests in Singapore: What BCA Requires

Nov 12
8 min read

In Singapore, the minimum number and type of pile tests for most multi-storey buildings is set by the joint BCA / IES / ACES / GeoSS circular APPBCA-2016-08 of 22 September 2016. For a building of 10 storeys or more it requires ultimate load tests on at least 1 pile or 0.5% of the working piles, working load tests on at least 2 piles or 1%, and non-destructive integrity tests on at least 2 piles or 2%, whichever is greater in each case. This guide explains each test, the numbers, who certifies the results and why piles fail. It is part of our complete guide to geotechnical engineering in Singapore.

Which rules govern pile testing in Singapore?

Pile testing is governed by the Building Control Regulations 2003, the Approved Document and a set of BCA joint circulars, with design carried out to SS EN 1997-1 (Eurocode 7) and its Singapore National Annex (see how Eurocode 7 governs geotechnical design in Singapore). The 2016 circular explains the chain: the Regulations require buildings to meet the performance requirements in the Fifth Schedule, and the Approved Document sets out acceptable solutions that include a list of ground investigation, loading and quality control tests for foundations.

The documents a designer works from are:

  • APPBCA-2016-08 (22 September 2016): test schedule for buildings of 10 storeys or more, and for buildings of 5 to 9 storeys with a footprint larger than 100 sq m. It applies where the first structural plans were submitted on or after 1 April 2017 and it superseded Advisory Note 1/03.

  • APPBCA-2021-17 (1 September 2021): guidelines on adopting rapid load tests.

  • APPBCA-2022-18 (1 September 2022): performance-based pile design for bored piles.

  • Guidelines on Local Practices for Pile Foundation Design and Construction (revision of 18 January 2022), which records that Eurocode 7 replaced SS CP4 as the code of practice for foundation design from 1 April 2015.

  • APPBCA-2025-17 (1 September 2025): bored piles in limestone areas.

For other building types, the 2016 circular says the Fifth Schedule requirements still apply and the structural plans must show how they are met. Our article on foundation design, pile types and site investigation covers the design side.

How many pile tests does BCA require?

For buildings of 10 storeys or more, Table 1 of APPBCA-2016-08 sets three minimum quantities, each "whichever is greater":

  • Ultimate load test: 1 number or 0.5% of the total number of working piles.

  • Working load test: 2 numbers, or 1% of the total number of working piles, or 1 for every 50 metres length of the proposed building.

  • Non-destructive integrity test (high-strain dynamic test or sonic logging test): 2 numbers or 2% of the total number of working piles.

For buildings of 5 to 9 storeys with a footprint larger than 100 sq m, Table 2 requires working load tests on 1 pile or 0.5% of the working piles, whichever is greater. These are minimums. The circular states that Eurocodes and the Singapore National Annex take precedence where they are more onerous, and that Qualified Persons (QPs) must judge whether more testing is needed where ground conditions are adverse or highly variable.

What is an ultimate load test?

An ultimate load test (ULT) is a test on a preliminary pile, loaded far beyond its working load, to verify the shaft friction and end bearing values assumed in design. BCA's local practice guidelines note that the pile is normally tested to 2.5 to 3.0 times the characteristic load, and that failure is usually defined as the load at which settlement reaches 10% of the pile diameter or continues without further load increase.

The test pile is instrumented with strain gauges so that the load carried by each soil or rock layer can be separated. The same guidelines require ULT for buildings of 10 storeys or more and leave it to the QP for structural works to assess the need in other cases. Two points from the BCA documents matter in practice:

  • The working piles must be installed by the same method as the ultimate test pile, with workmanship that is no worse. The test pile must not be built under more favourable conditions.

  • Under the Singapore National Annex, a lower model factor (1.35 instead of 1.55) may be used when resistance is verified by an instrumented maintained load test, so a well planned ULT can shorten the working piles.

Under APPBCA-2022-18 the design QP may submit more than one set of pile design parameters for approval in a single submission, and adopt the set that the instrumented ULT verifies, without waiting for an amendment plan.

What is a working load test?

A working load test (WLT) is a proof test on a working pile to confirm it settles within limits under service load. APPBCA-2016-08 requires the test to reach a minimum of 1.5 times or 2 times the characteristic load, with the maximum settlement at the pile top generally not exceeding 15 mm or 25 mm respectively.

The circular requires load tests to be carried out by maintained loads, with the load measured by both a calibrated load gauge and a calibrated pressure gauge. The 2022 local practice guidelines refer designers to BS EN ISO 22477-1:2018 for the load step sequence. Reaction for a static test comes from kentledge, tension piles or ground anchors. A bi-directional test instead uses a load cell cast into the pile, so the pile is jacked against itself.

When can rapid load tests or dynamic tests replace static tests?

Rapid load tests may replace up to 100% of static working load tests, provided site-specific correlation tests against static maintained load tests are carried out as set out in APPBCA-2021-17. Replacing an ultimate load test with a rapid load test is considered case by case and requires pre-consultation with BCA.

A rapid load test, of which the Statnamic test is the best known type, applies a brief but quasi-static load pulse. The 2021 circular requires the specialist firm to follow BS EN ISO 22477-10, and treats a correlation as unacceptable if the rapid test settlement differs from the static test settlement by more than 20% or 3 mm, whichever is greater. The QP must allow for creep and loading rate effects that a short test cannot capture.

A high-strain dynamic test, commonly done with a Pile Driving Analyser (PDA), measures force and velocity under a hammer blow. In BCA's schedule it is listed as a non-destructive integrity test for quality control and does not count towards the working load test quantity.

What integrity and quality control tests apply to bored piles?

Integrity tests check that the pile shaft is sound and continuous, and for bored piles under buildings of 10 storeys or more BCA recommends further quality control tests in Table 3 of APPBCA-2016-08:

  • Sonic logging: an ultrasonic pulse is sent between tubes cast into the pile. Because the tubes force test piles to be pre-selected, the builder and supervising QP must ensure those piles are built in a way representative of the other working piles. The circular refers to ASTM D6760-08 or equivalent.

  • Interface coring at the pile base: 5% of working piles, reducible to 2% if base grouting is carried out, where the design uses a characteristic unit end bearing resistance of more than 10 MPa.

  • Concrete core test below cut-off level: 5% of working piles, where characteristic cube strength is above 40 MPa and working compressive stress exceeds 7.5 MPa.

  • Pile profile test before concreting: 100% of working piles larger than 1.8 m in diameter that have no steel casing through soft or loose soil, or no redundancy.

Low-strain integrity testing, where the pile head is tapped with a hand-held hammer and the reflected wave is read, is quick and widely used as a screening tool. It is not one of the two methods named in Table 1.

Who supervises and certifies pile load tests?

The supervising Qualified Person, the builder and the site supervisors are responsible for pile tests, and a Certificate of Supervision on Pile Load Test must be submitted to BCA within 28 days of completing each load test, with the load test report attached. Where the foundation is for a building of 30 or more storeys, it is geotechnical building works and a QP(Geo) and AC(Geo) are also involved, as explained in our guide to what a PE(Geo) does.

Workplace safety is a separate duty. A joint MOM and BCA circular of 5 April 2012 reminds contractors that pile testing must be conducted under the direct supervision of a designated person and that nobody may approach the test area while load is being increased or decreased, except on that person's instruction. Site roles generally are covered in our article on site supervision for structural works.

What goes wrong: common reasons piles fail tests

Piles usually fail tests because of construction defects or ground that differs from the boreholes, and less often because of the test set-up itself. Typical causes are:

  • A soft toe: loose debris or sediment left at the base of a bored pile, so end bearing mobilises only after large settlement. BCA addresses this by requiring the characteristic shaft resistance of bored piles to be at least 1.3 times the characteristic load unless base enhancement is used and verified by testing.

  • Necking, soil inclusions or poor concrete in the shaft, which sonic logging and coring are designed to find.

  • Founding the pile short of the competent stratum because rock or hard soil levels vary between boreholes. See our guide to soil investigation and what BCA requires.

  • Cavities or slump zones in limestone. APPBCA-2025-17 calls for ultimate load tests on piles in treated cavity ground, working load tests on the onerous pile in each representative zone and integrity tests on working piles that encountered cavities.

  • An over-designed test pile that barely moves, so the design parameters are never mobilised and nothing is learned.

  • Kentledge problems. In the incident described in the 2012 circular, a kentledge frame tilted on 16 January 2011 and concrete blocks fell onto a public road. The investigation found the main cause was inadequate design of the foundation supporting the kentledge.

FAQ

How many piles must be load tested in Singapore?

For a building of 10 storeys or more: ultimate load tests on 1 pile or 0.5% of working piles, working load tests on 2 piles or 1% of working piles or 1 per 50 m of building length, and integrity tests on 2 piles or 2%, whichever is greater in each case (APPBCA-2016-08).

What settlement is allowed in a working load test?

Generally not more than 15 mm at 1.5 times the characteristic load, or 25 mm at 2 times the characteristic load, measured at the pile top.

Is a PDA test accepted in place of a static load test?

Not as a working load test. BCA's schedule lists the high-strain dynamic test as a non-destructive integrity test. Rapid load tests are the method BCA allows as a replacement for static working load tests, subject to correlation.

Is CP4 still used for pile testing?

SS CP4 was replaced by Eurocode 7 from 1 April 2015. Some CP4 practices were retained, including the 15 mm and 25 mm settlement criteria, through the 2016 circular and the 2022 local practice guidelines.

Do small buildings need pile load tests?

The fixed schedule applies to buildings of 10 storeys or more and to buildings of 5 to 9 storeys with a footprint over 100 sq m. For other works the QP must still show how the Fifth Schedule performance requirements are met.

Can a failed pile be accepted?

That is an engineering decision for the QP, who may re-test, down-rate the pile, add compensating piles or redesign the pile cap, and must reflect the outcome in the submission to BCA.

Sources