Factory Additions and Alterations Guide 2027: JTC BCA and SCDF
Additions and alterations to a factory in Singapore usually need up to four separate clearances: the landowner's consent (JTC on JTC land), URA for planning where the use or floor area changes, BCA for structural plans and the permit, and SCDF for fire safety works. Approval from one does not cover the others, so the order and scope matter more than the speed of any single submission.
Written in November 2026 from published rules; check the linked official sources for updates.
Twelve-step checklist for factory additions and alterations
Each step gives what to do, who it applies to, the rule and where to read more.
Confirm the approved use and the lease conditions. Who: every tenant or owner. Rule: a change of use happens when the activity moves away from what was approved, even if nothing is built. SCDF treats the use of factory space as storage as a change of use. Read factory change of use.
Test the 60/40 split. Who: anyone adding offices, showrooms, canteens or dormitories. Rule: URA requires at least 60% of industrial gross floor area to be used for industrial purposes, leaving 40% for ancillary uses. In a multi-user development the split applies to the whole development and within each strata unit. Read factory change of use.
Check whether the work is insignificant building works. Who: everyone. Rule: the First Schedule of the Building Control Regulations 2003 lists works needing no BCA plan approval or permit, such as a single level storage platform within 4 m height and 50 sqm, or a low machine plinth within the limits. BCA states a permit is required for all other building works. Read insignificant building works.
Check the floor. Who: anyone installing machinery, racking or platforms. Rule: the engineer checks the slab, beams, columns and foundations along the load path, including concentrated loads. Read machine foundations and floor loading.
Get the existing drawings. Who: everyone. Rule: approved plans can often be bought from BCA or obtained from the landlord. Where they cannot, the engineer establishes the structure by measurement, scanning and testing. Read how to buy approved plans.
Appoint a Qualified Person. Who: any work needing authority submissions. Rule: a Qualified Person is a registered architect or a professional engineer with a valid practising certificate, and only a QP who is a civil or structural PE can apply for structural plan approval. Read PE endorsement vs QP submission.
Apply for JTC consent. Who: tenants and owners on JTC land. Rule: JTC consent covers renovation works on JTC land and buildings, including additions, alterations and amendments, even where other authorities also approve. The submission includes a cover letter, JTC self-declaration form, QP letter of declaration and drawings with a GFA table. JTC's fit-out page states that all fitting-out and renovation works, temporary or permanent, need JTC's approval and that its consultant can be a PE, registered architect or QP. Read JTC factory renovation consent.
Check JTC's machinery and fixing rules. Who: tenants in JTC buildings. Rule: under JTC's Space Submission Handbook, machinery is exempt from plan consent only if each machine does not exceed 750 kg or the design imposed load, whichever is lesser. Bolts and anchors must not penetrate more than 40 mm into structural elements, and hacking or coring into columns, beams and slabs is not allowed. Read machine foundations and floor loading.
Submit planning where needed. Who: changes of use and added GFA. Rule: URA's Plan Lodgment Scheme excludes secondary uses in industrial developments such as canteens, showrooms, childcare centres and workers' dormitories, which need formal planning permission. Read URA written permission timelines.
Submit structural plans and obtain the permit. Who: structural works. Rule: BCA processes structural plans without an Accredited Checker's certificate within 7 working days of a complete submission, and the permit within 7 working days. An Accredited Checker's certificate is needed where additions and alterations materially affect key structural elements. Read Accredited Checker.
Submit fire safety plans. Who: works affecting fire safety, and changes of use. Rule: SCDF approval is needed before the works begin, plans are submitted by a QP, and a Registered Inspector inspects completed works. In a factory, storage areas are limited to 100 sqm in aggregate without sprinklers, rising to 700 sqm with an automatic sprinkler system (Fire Code 2023, clause 9.6.1c). Read SCDF fire safety submission.
Complete and close out. Who: everyone. Rule: JTC states that on receiving the TOP or CSC, one complete set of each document must be submitted to JTC within one month. An FSC must be obtained before the premises are used or occupied. Read TOP and CSC.
CORENET X in 2027
CORENET X has been mandatory for new projects of 30,000 sqm GFA and above since 1 October 2025 and of 5,000 sqm and above from 1 October 2026. Smaller projects may stay on CORENET 2.0 for now, under the BCA and URA circular of 23 July 2026. Read CORENET X complete guide.
What has not changed
A permit is still required for all building works except insignificant building works.
JTC consent, URA permission, BCA approval and SCDF approval remain separate.
Land Betterment Charge, which replaced Differential Premium, Development Charge and Temporary Development Levy from 1 August 2022, can be triggered by added floor area.
Building works without approved plans or a permit carry a fine of up to $200,000, imprisonment of up to 2 years, or both.
See the Singapore Building Compliance Handbook 2027 for the wider picture.
Common mistakes
Signing the lease or starting renovation before URA's and JTC's decisions. Both advise against it.
Treating storage as the same use as production.
Running JTC, BCA and SCDF scopes separately so the GFA table and plans no longer describe the same building.
Adding platforms or racking around a machine without re-checking the floor.
Ignoring the unit-level 60/40 split in strata units.
FAQ
Does JTC approval replace BCA approval?
No. JTC acts as landowner. BCA approves structural plans and issues the permit.
Do I need JTC consent for a small renovation?
JTC states that all fitting-out and renovation works, temporary or permanent, need its approval.
Who can submit to JTC?
JTC says its consultant can be a PE, registered architect or Qualified Person.
Can an unauthorised addition be kept?
A QP can submit plans to BCA for approval, which is not guaranteed. See regularisation of unauthorised works.
How are fees worked out?
See PE endorsement cost in Singapore. These are indicative points for context, not a benchmark or a quotation. Every project is different, so ask for a written quotation based on your drawings and scope.
Sources
CVC Engineers is a multidisciplinary practice that takes architectural, civil, structural and geotechnical scope under one appointment, including additions and alterations and BCA submissions. WhatsApp +65 9342 7551. Last reviewed: November 2026.


Comments