Tunnelling Pipe Jacking and Shafts in Singapore: When Underground Works Become Geotechnical Building Works
In Singapore, a tunnel with a diameter, width or height of more than 2 m is geotechnical building works under the Building Control Act, and so is a shaft, trench or other excavation deeper than 6 m. Geotechnical building works need a geotechnical Qualified Person, QP(Geo), and a specialist Accredited Checker, AC(Geo), on top of the usual structural QP and AC. Smaller pipe-jacked utilities and their shafts still need an earth retaining or stabilising structure (ERSS) submission in most cases, and shafts for utility works are now also covered by BCA's risk-based guidelines in circular APPBCA-2026-23 of 19 October 2026. This article is part of our complete guide to geotechnical engineering in Singapore.
What are the main tunnelling methods used in Singapore?
Four methods cover almost all tunnels built in Singapore: bored tunnelling, pipe jacking, mined tunnelling and cut-and-cover.
Bored tunnelling uses a tunnel boring machine (TBM) that excavates the full face behind a shield and erects a segmental lining as it advances. Pressurised-face machines balance the soil and water pressure at the face, which is what makes tunnelling under buildings in soft ground possible.
Pipe jacking and microtunnelling push pipe sections from a launch shaft to a reception shaft behind a small remotely operated boring machine. They are the usual trenchless methods for sewers, drains and cable tunnels.
Mined tunnelling excavates in short advances and supports the ground with sprayed concrete, steel ribs or pipe roofs. The New Austrian Tunnelling Method (NATM) is the best known form.
Cut-and-cover builds the tunnel box inside a deep excavation supported by retaining walls and struts, then backfills over it.
Every bored or jacked drive starts and ends in a shaft, so shafts are part of almost every tunnelling job.
When is a tunnel geotechnical building works?
A tunnel is geotechnical building works when its diameter, width or height is more than 2 m. BCA's Geotechnical Building Works submission requirements (June 2026) define tunnelling works as any excavation or other building works to make a tunnel of that size, and give these examples:
Bored or jacked-in tunnel with a diameter over 2 m: both the permanent tunnel lining and the temporary tunnel support system are geotechnical building works.
Mined tunnel over 2 m in height or width: the temporary tunnel support system is geotechnical building works, and so is a permanent tunnel structure exceeding 2 m.
Cut-and-cover tunnel in an excavation deeper than 6 m: the temporary earth retaining and support system is geotechnical building works.
For utility pipes the same 2 m figure applies. Pipes larger than 2 m in diameter, with their associated shafts or manholes in excavations deeper than 6 m, are geotechnical building works. What a PE(Geo) does on such projects is explained in our article on geotechnical engineering and the PE(Geo).
Are shafts treated as ERSS, and what are the thresholds?
Yes. A shaft is an excavation supported by an earth retaining structure, so it follows the ERSS thresholds. Under BCA's June 2026 guidance:
Up to 1.5 m deep (1 m if the structure is not reinforced concrete or steel): plan approval is not required.
Over 1.5 m and up to 4 m: a QP submits, and no AC is required.
Over 4 m and up to 6 m: a QP and an AC.
Over 6 m and classified as geotechnical building works: QP, QP(Geo), AC and AC(Geo).
Over 6 m but not classified as geotechnical building works, for example the excavation for a sewer manhole associated with a pipe of 2 m diameter or less: a QP and an AC.
Two exemptions matter for small works. An excavation for a shaft or trench with a plan area not exceeding 10 sq m, such as a diaphragm wall trench or a bored pile excavation, is exempted from the geotechnical building works requirements but is still subject to ERSS submission requirements. A trench for laying a sewer or utility not exceeding 1 m in internal diameter, including its associated shaft or manhole, is classified as insignificant building works needing no plan submission, unless it lies within a construction site with other building works and the trench exceeds 10 sq m or 2 m in depth. For utility pipes larger than 1 m and up to 2 m, the pipe plan is submitted by a QP and an AC. See our guides to ERSS submission thresholds and deep excavation and AC(Geo) requirements.
What do BCA's 2026 risk-based guidelines for utility shafts require?
Circular APPBCA-2026-23, issued jointly by BCA, ACES, IES and GeoSS on 19 October 2026, classifies every ERSS shaft for utility works as Low, Medium or High risk according to the ground and how close buildings are. It applies to shafts for sewer, water and other utility pipes that require structural plan submission, and its stated aim is to prevent ground loss or water ingress during shaft excavation, particularly in soft, reclaimed or highly permeable soils.
The risk matrix combines three ground types with three proximity classes:
Ground: very stiff to hard soil (SPT-N above 15), stiff soil (SPT-N 8 to 15), and soft to firm soil (SPT-N below 8) or any soil with permeability of 5 x 10⁻⁷ m/s or more.
Proximity: "close proximity" means buildings or structures within 1H of the shaft, up to a maximum of 10 m, where H is the excavation depth. The "zone of influence" extends to the 10 mm settlement line or 1.5H, whichever is larger. Everything else is greenfield.
Result: a shaft in close proximity to buildings is Medium risk in very stiff to hard soil and High risk in the other two ground types. Greenfield shafts are Low risk except in soft or permeable ground, where they are Medium.
For shafts in close proximity to buildings, a physical retaining wall installed before excavation, such as a sheet pile or secant bored pile wall, is the default construction method unless BCA agrees otherwise at pre-consultation. The circular ranks a cast-in-situ caisson shaft in challenging ground with ground improvement as a high-risk method, because it depends critically on the quality of the ground improvement.
Other requirements include:
Boreholes: at least 1 for a shaft under 6 m inner diameter with no buildings in close proximity, rising to 3 for a shaft over 12 m with buildings nearby, with one borehole on the building side.
Exposure time: for caisson shafts, recommended soil face exposure before the ring is cast is within a day for SPT-N of 15 or less, within 2 days up to SPT-N 50, and within 3 days above that.
Ground improvement verification by trial, coring and strength testing, with total core recovery of at least 85%. Details are in our article on ground improvement in Singapore.
Instrumentation: at least one set of inclinometer and piezometer or water standpipe, and rod-type settlement markers at 3 m intervals around a caisson shaft or 5 m around a shaft with a physical wall.
Supervision: the supervising QP checks each critical stage or caisson ring before signing the ERSS_Annex C record. Visible soil ingress or significant water ingress must be stopped at once, for example by backfilling or flooding the shaft, and reported immediately to the Commissioner of Building Control.
The circular also reiterates the importance of having a single design QP and a single supervising QP for all building works in a project, including the ERSS.
What are settlement and volume loss?
Volume loss is the extra ground excavated by a tunnel beyond its theoretical volume, expressed as a percentage of the tunnel face area, and it is what causes settlement at the surface. Ground moves towards the face, around the shield and into the gap behind the lining before grout fills it.
That lost volume appears at ground level as a settlement trough above the tunnel, deepest over the centreline and fading to either side. Engineers predict the trough from an assumed volume loss, the tunnel depth and the soil type, then assess each building, pile and utility within it for settlement, tilt and distortion. Control comes from face pressure, continuous grouting of the tail void and monitoring. The assessment process is described in our article on impact assessment and pre-construction surveys.
What does LTA require near MRT lines?
Any boring, jacking, piling or tunnelling within the railway protection zone, the land within 40 m of the outermost edge of the railway, is a restricted activity that needs LTA's prior written permission. LTA also defines a railway safety zone of 60 m and a first reserve of 6 m from the railway structure.
The Code of Practice for Railway Protection (2024 edition) sets these limits and conditions for works that could affect rapid transit structures:
Differential movement of a tunnel section limited to 15 mm or less, or an angular rotation of less than 1:1000, whichever is lesser.
Peak particle velocity at any rapid transit structure not exceeding 15 mm/sec.
Piezometric pressure in compressible soils within the first and second reserves not reduced by more than 10 kPa.
A new tunnel to be continuously and fully supported with a permanent lining. Techniques such as NATM, where the ground is not immediately supported after excavation, are not acceptable unless the inherent risks are reduced to acceptable levels.
Continuous tail void grouting, and measures to prevent ingress of water carrying fines or soil.
More detail is in our guide to building near MRT lines.
What must be done about existing utilities before excavating?
Existing utilities must be located and the owning agency notified or its approval obtained before any shaft or tunnel work starts. For water pipes, PUB's advisory note (March 2026 edition) requires the QP or contractor to purchase the Water Services Plan, confirm pipe positions by trial holes dug by manual excavation, notify PUB for pipes smaller than 300 mm in diameter and obtain PUB's approval for pipes of 300 mm or more. PUB reviews such submissions within 14 working days.
Where a utility cannot be diverted and passes through an ERSS wall, BCA circular APPBCA-2024-23 (2 December 2024) applies to excavations deeper than 4 m. It limits the utility gap to a maximum width of 3 m, requires borehole information within 15 m of the gap, ground improvement for soil with SPT-N below 30, structural lagging installed in small excavation lifts, and a set of inclinometer, piezometer and water standpipe near the gap.
Which authority governs what?
BCA: plan approval, permits and supervision for tunnels, shafts and ERSS under the Building Control Act, with design to SS EN 1997-1 and its Singapore National Annex.
LTA: works in the railway protection zone and railway corridor.
PUB: works near water pipes and sewers. Damaging a water pipe of 300 mm or more in diameter carries a fine of up to $200,000, imprisonment of up to 3 years, or both, under the Public Utilities Act as cited in PUB's advisory.
Other utility owners: clearances for their own services.
The sequence of agency clearances is set out in our guide to the order of authority submissions.
What goes wrong with shafts and tunnels?
Ground loss is the recurring failure: soil or water enters the excavation and a void works its way up to the surface. BCA's 2026 circular says cases of ground loss and water ingress during shaft excavation, particularly in reclaimed sand and soft clays, prompted the risk-based approach.
On 26 July 2025 a sinkhole formed on Tanjong Katong Road South next to a worksite where a shaft was being built to connect three new sewer pipelines, and a car fell in. According to the authorities' statement of 11 June 2026, part of the shaft allegedly failed, allowing soil to enter. The alleged breaches included works that did not comply with approved plans, mandatory tests that were not carried out and a failure to report an earlier road depression. BCA reviewed more than 60 similar ongoing projects afterwards.
Common causes are leaving a soil face exposed for longer than its stand-up time, defective ground improvement, gaps at utilities, groundwater drawdown and ignoring early signs such as seepage or a depression in the road. Groundwater risks are covered in our article on groundwater control and dewatering.
FAQ
At what size does a tunnel need a PE(Geo) in Singapore?
When its diameter, width or height is more than 2 m. It is then geotechnical building works and needs a QP(Geo) and an AC(Geo).
Does a pipe jacking shaft need BCA approval?
Usually yes. Unless the work is insignificant building works, a shaft deeper than 1.5 m needs an ERSS plan submission by a QP, with an AC above 4 m. The trench and shaft for a utility of 1 m internal diameter or less is generally insignificant building works.
Is a small shaft exempt from geotechnical building works?
A shaft or trench with a plan area not exceeding 10 sq m is exempted from the geotechnical building works requirements, but BCA states that it is still subject to ERSS submission requirements.
What is the default shaft construction method next to buildings?
A physical retaining wall installed before excavation. Under APPBCA-2026-23 this is the default for shafts in close proximity to buildings unless BCA agrees otherwise at pre-consultation.
What is volume loss in tunnelling?
It is the volume of ground lost into the tunnel during excavation beyond the tunnel's theoretical volume, expressed as a percentage of the face area. It determines the size of the surface settlement trough.
How close to an MRT tunnel can I tunnel or jack a pipe?
Any such work within 40 m of the railway is a restricted activity in the railway protection zone and needs LTA's prior written permission. The limits in LTA's Code of Practice for Railway Protection must be met.
Who must be told if soil or water enters a shaft?
Under APPBCA-2026-23 the builder and the supervising QP must notify the Commissioner of Building Control immediately of visible soil ingress or significant water ingress.
Sources
BCA Geotechnical Building Works submission requirements, June 2026
BCA circular APPBCA-2026-23, Risk-based Guidelines on ERSS Shafts for Utility Works, 19 October 2026
PUB advisory note on prevention of damage to water pipes, March 2026
MOM, BCA and LTA joint statement on the Tanjong Katong Road South sinkhole, 11 June 2026