Land Reclamation Design in Singapore: Fill Seawalls Drains and Settlement Control
Land reclamation in Singapore is designed around five decisions: the finished platform level, the edge structure that contains the fill, the fill material, the treatment of the soft clay beneath it, and how settlement is predicted and measured before the land is handed over. PUB states that since 2011 newly reclaimed land must be at least 4 m above mean sea level, and critical infrastructure such as Tuas Port has been built to 5 m. This article explains each design step with figures from official MPA, HDB and PUB documents. It belongs to our geotechnical engineering guide.
How is reclaimed land designed, step by step?
Reclamation design runs in a fixed order: investigate the seabed, set the platform level, design the containment, place the fill, treat the soft clay and monitor until settlement criteria are met.
Marine site investigation: boreholes and cone penetration tests to map the thickness and strength of the soft marine clay.
Platform level: fixed from PUB's minimum reclamation level plus the settlement still expected after handover.
Containment: a bund, seawall or caisson wall, checked for stability on the soft seabed.
Filling: in stages, so that the clay gains strength under each lift.
Ground treatment: prefabricated vertical drains and surcharge for clay, densification for loose sand fill.
Monitoring and handover: instruments confirm that the required consolidation has been reached.
The underlying soil behaviour is explained in marine clay settlement and consolidation.
What fill is used, and where does it come from?
Sand is the conventional fill, but recent Singapore projects have replaced a large part of it with dredged seabed material and excavated earth. For Tuas Port Phase 1, the Maritime and Port Authority of Singapore (MPA) stated in February 2023 that recycled dredged seabed material and land-excavated material accounted for more than half of the reclamation fill, and that dredged hard rock was reused for shore protection and fill. At the Pulau Tekong polder, the Housing and Development Board (HDB) and PUB reported in September 2025 that over 10 million cubic metres of clayey soil dredged for the stormwater pond was repurposed as infill.
The engineering distinction is drainage. Sand fill drains freely and can be densified quickly. Clay fill has a high water content and must itself be consolidated with drains and surcharge before it can carry load, which lengthens the programme and makes settlement prediction more demanding.
How are bunds, seawalls and caissons designed?
The edge structure is designed first because it must stand on the weakest ground, the untreated seabed, while holding back fill on one side and resisting waves on the other. Three forms are used.
Containment bund with rock revetment: a sand core with rock armour on the seaward face. PUB describes a dyke as a raised embankment, typically of sand and clay, built along coastlines to keep out seawater.
Seawall: PUB describes a seawall as a vertical barrier of concrete, rocks and rubble, and notes that it is usually difficult to raise after construction.
Caissons: large precast concrete cells floated into position and sunk onto a prepared foundation. For Tuas Port Phase 1, MPA records 221 caissons, each 10 storeys high and about 15,000 tonnes, forming 8.6 km of wharf and seawall, and serving as both earth-retaining walls and foundations for the wharf structures. Phase 2 involves 9.1 km of caissons.
The design checks are overall slope stability through the soft clay, bearing capacity and sliding of the structure, settlement of the wall line, and erosion protection. Where the clay under the edge structure is too weak, it is dredged and replaced or strengthened by ground improvement before the wall is placed.
What is the difference between a polder and conventional fill?
Conventional reclamation raises the ground above sea level with fill, while a polder keeps the land below sea level behind a dike and pumps the water out. Singapore's first polder, at the north-western tip of Pulau Tekong, had its main construction works announced as complete on 8 September 2025. The official figures are:
About 800 hectares of land added.
A 10 km coastal dike standing up to 6 m above mean sea level, with the polder land about 1.2 m below mean sea level.
Close to 50% saving in sand compared with conventional filling.
A cement bentonite wall within the dike to minimise seepage, with a seepage drain behind it.
A 45 km drainage network, a 116-hectare stormwater collection pond designed to hold up to 5 million cubic metres, and two pumping stations.
More than 170 CCTVs and over 260 sensors monitoring the dike and water levels.
PUB operates and maintains the dike and drainage system, and the dike height can be raised if sea levels require. The trade-off is that a polder depends permanently on its dike and pumps, so seepage control and inspection become part of the design life.
How is soft clay treated with vertical drains and surcharge?
Prefabricated vertical drains (PVDs) with surcharge is the standard treatment for soft clay under reclamation: the drains shorten the path that water must travel, and the surcharge supplies the pressure that squeezes it out. Without drains, water in a thick clay layer can only escape to the top or bottom of the layer, and because consolidation time rises with the square of the drainage path, this can take decades. Drains installed on a close grid let water flow horizontally to the nearest drain instead.
The surcharge is extra fill placed above the final level and removed once the target consolidation is reached, so that most of the settlement the finished land would have suffered occurs during construction. HDB's 2025 factsheet describes exactly this at Tekong: PVDs inserted at regular intervals into the clayey fill, overlaid with sand to compress it and force water up through the drains. At Tuas Port Phase 1, MPA records soil improvement works over 414 hectares, including 294 hectares of newly reclaimed land, with the fill treated so that the land stays stable within the limits needed for automated guided vehicles.
How is settlement predicted and monitored?
Settlement is predicted by consolidation theory using laboratory compressibility data, and then corrected against field measurements as filling proceeds. The prediction has three parts: immediate settlement, primary consolidation as pore water drains, and long-term secondary compression. Because clay properties vary across a site, engineers back-analyse the measured settlement curve during the surcharge period to estimate the ultimate settlement and the degree of consolidation reached.
Typical instruments are settlement plates on the seabed and fill surface, deep settlement gauges within the clay, piezometers to track the dissipation of excess pore water pressure, and inclinometers near bunds to detect lateral movement. Surcharge is removed only when both settlement and pore pressure records show that the specified consolidation has been achieved. See soil and rock mechanics basics for the parameters involved.
What platform level and sea level rise allowance is required?
PUB states that from 1991 to 2011 new coastal land was reclaimed to at least 3 m above mean sea level, and that since 2011 the minimum reclamation level for newly reclaimed land and the minimum platform level for new developments have been at least 4 m above mean sea level. New critical infrastructure is built at 5 m or more: MPA states that Tuas Port Phase 1 was built 5 m above mean sea level, and PUB cites Changi Airport Terminal 5 at 5.5 m.
The basis is the Third National Climate Change Study, which projects mean sea level around Singapore rising by up to 1.15 m by 2100. The National Climate Change Secretariat adds that with storm surges and high tides sea levels could rise by up to 5 m, and that around 30% of the island is less than 5 m above mean sea level. A designer therefore adds expected post-construction settlement to the minimum level, so that the land still meets it at the end of its design life.
Which authority governs reclamation and coastal protection?
PUB, the national water agency, governs platform levels, drainage and coastal protection, and BCA governs the structures. The main instruments are:
PUB's minimum reclamation and platform levels, described above, and its Code of Practice on Surface Water Drainage, which governs stormwater management.
The Coastal Protection Bill, passed in March 2026, which renames the Sewerage and Drainage Act as the Sewerage, Drainage and Coastal Protection Act and makes coastal landowners responsible for coastal protection measures on their land.
PUB's Code of Practice on Coastal Protection, announced on 17 June 2026 and taking effect from 2028, which sets coastal protection levels and design, inspection and maintenance requirements.
BCA's geotechnical building works requirements (June 2026): an earth embankment or dam, or a caisson retaining earth fill, higher than 6 m is geotechnical building works needing a PE(Geo) and AC(Geo).
Reclamation projects are carried out by agencies according to use: MPA for Tuas Port, and HDB with PUB for the Tekong polder. PUB also lists land reclamation itself as a coastal protection measure, with the planned Long Island off the East Coast, about 800 hectares, as the example.
What should engineers check when building on reclaimed land?
Buildings on reclaimed land need a higher level of geotechnical scrutiny because the ground may still be settling. The GeoSS guide on ground investigation to Eurocode 7 (2015) places foundations for high-rise buildings of more than 10 storeys on reclaimed land in Geotechnical Category 3, the highest. Three checks follow.
Negative skin friction: the 2022 local practice guidelines for piles require drag force to be considered where the clay is still consolidating, which is typical under recent fill.
Rafts: under BCA circular APPBCA-2024-14, ground likely to undergo consolidation settlement from backfilling is not suitable for raft or piled raft foundations.
Services and floors: ground-bearing slabs, drains and utility connections settle with the fill while piled structures do not, so the junctions need flexible details.
What goes wrong in reclamation?
The characteristic failures are edge instability during filling and settlement that continues after handover. Filling too fast over soft clay can cause a bund to slide before the clay has gained strength, which is why lifts are staged and inclinometers are read between them. Under-treated clay, whether from drains that stop short of the base of the layer or surcharge removed early, shows up years later as differential settlement, ponding and damaged services. Variable fill, such as lumps of dredged clay within sand, settles unevenly and is hard to detect without closely spaced testing.
FAQ
How high must reclaimed land be in Singapore?
At least 4 m above mean sea level since 2011, according to PUB, with critical infrastructure at 5 m or more.
How long does reclaimed land take to settle?
It depends on clay thickness and treatment. Vertical drains and surcharge are used precisely to bring forward settlement that would otherwise take many years; the designer specifies a target degree of consolidation and verifies it by monitoring.
What are prefabricated vertical drains?
They are thin band-shaped drains pushed vertically into soft clay on a grid so that pore water has a short horizontal path to escape under surcharge.
Why did Singapore build a polder at Pulau Tekong?
HDB and PUB state that empoldering saved close to 50% of the sand that conventional filling would have needed, while the 10 km dike also protects the land from rising sea levels.
Is reclaimed land safe to build on?
Yes, when the ground has been treated and verified and the foundations are designed for it, including drag force on piles where clay is still consolidating.
Who maintains coastal protection structures?
Under the legislation passed in March 2026, landowners of prescribed coastal places are responsible for their coastal protection measures and must make annual declarations to PUB once the Code of Practice on Coastal Protection takes effect.
Sources
PUB: Coastal protection approach (reclamation and platform levels)
PUB and HDB: Singapore's first polder at Pulau Tekong adds 800 hectares of land, 8 September 2025
HDB and PUB: Media factsheet, Constructing Singapore's first polder
MPA: First phase of Tuas Port reclamation works completes, 30 November 2021
MPA: Engineering innovations for Tuas Port Phase 1 reclamation project recognised, 7 February 2023
MPA: Welcome address at completion of Tuas Port Phase 1 reclamation, 30 November 2021
PUB: Introduction of Coastal Protection Bill, 3 February 2026
PUB: New Code of Practice on Coastal Protection, 17 June 2026
BCA: Geotechnical Building Works submission requirements, June 2026
GeoSS: Guide on ground investigation and geotechnical characteristic values to EC7, 2015
BCA: Requirements and guidelines for raft and piled-raft foundation, APPBCA-2024-14