Construction Procurement Trends in Singapore: Statistics and What Is Changing

Nov 12
9 min read

Singapore awarded about S$50.5 billion of construction contracts in 2025, and the Building and Construction Authority (BCA) forecasts S$47 billion to S$53 billion for 2026. Around 55% of the 2025 total came from the public sector, which is why public procurement policy sets the direction for the whole industry. That direction is clear in BCA's publications: tenders judged on quality as well as price, earlier contractor involvement, collaborative contract terms, and digital and off-site delivery. This article collects the latest official figures, each with its date and source.

How big is Singapore's construction market in 2026?

BCA's forecast, released on 22 January 2026, puts total construction demand for 2026 at S$47 billion to S$53 billion in nominal terms, similar to 2025. Construction demand is the value of contracts awarded. The key figures are:

  • 2024: preliminary demand of S$44.2 billion and construction output of about S$38.4 billion (BCA, 23 January 2025).

  • 2025: preliminary demand of S$50.5 billion and output of about S$41.7 billion (BCA, 22 January 2026). BCA's later statistics table revises 2025 demand to S$50.65 billion.

  • 2026: forecast demand of S$47 billion to S$53 billion and output of S$43 billion to S$46 billion.

  • 2027 to 2030: forecast average demand of S$39 billion to S$46 billion a year.

  • January to May 2026: S$26.07 billion of contracts awarded, on BCA's preliminary count.

By type of work, BCA's 2026 forecast is S$13.5 billion to S$15.3 billion for institutional and other buildings, S$11.6 billion to S$13.4 billion for civil engineering, S$6.2 billion to S$6.8 billion for public residential, S$6.1 billion to S$6.7 billion for commercial, S$5.0 billion to S$5.5 billion for private residential, and S$4.6 billion to S$5.4 billion for industrial. BCA names an airport terminal development, an integrated resort expansion, a new general and community hospital and two rail line extensions among the projects supporting 2026 demand.

How is demand split between the public and private sectors?

In 2025 the public sector accounted for S$28.01 billion and the private sector for S$22.51 billion of a preliminary total of S$50.52 billion, according to BCA's statistics table with data as at February 2026. That is about 55% public and 45% private, on our arithmetic from BCA's figures. The split differs sharply by type of work:

  • Residential: S$9.53 billion public, S$6.22 billion private.

  • Institutional and others: S$10.57 billion public, S$5.58 billion private.

  • Civil engineering: S$6.28 billion public, S$3.02 billion private.

  • Industrial: S$0.63 billion public, S$6.46 billion private.

  • Commercial: S$1.00 billion public, S$1.23 billion private.

Two consequences follow. A contractor or consultant working in housing, institutions or infrastructure is mostly working under public sector procurement rules. And industrial building, which is mostly private, is procured outside those rules, on whatever contract form the owner chooses. The forms themselves are compared in our article on standard construction contracts in Singapore.

Is there an official statistic on how often design and build is used?

No. We found no official BCA, SingStat or data.gov.sg statistic that breaks down Singapore construction contracts by procurement method, whether design and build, traditional design-bid-build or another model. BCA publishes demand by sector and type of work, not by contract model. Percentages quoted online for the "share" of design and build in Singapore should be treated as estimates unless they name an official source.

What BCA does publish is the menu. Its January 2020 guide identifies three early contractor involvement models for public projects: Design and Build, Design Development and Build, and Design Bid Build with Early Contractor Involvement. It publishes its public sector conditions of contract in both a construction works version and a design and build version. How the models differ is explained in Design and Build vs Traditional Contracts in Singapore.

What is collaborative contracting and how far has it spread?

Collaborative contracting is a set of contract mechanisms that commit the parties to shared project goals, early warning of risks and structured resolution of issues, and BCA reported more than 20 ongoing and upcoming pilot projects in January 2026. The count has grown from nine upcoming projects by seven government procuring agencies when the refreshed Built Environment Industry Transformation Map was launched on 6 September 2022.

BCA offers two routes:

  • An Option Module on collaborative contracting used with the Public Sector Standard Conditions of Contract. BCA lists its principles as a collaborative working relationship, partnering workshops, structured dispute avoidance and resolution with an independent third party, early notification of risks, proactive project management with clear response and claim settlement timelines, and key performance incentives. The modules are still marked as under pilot.

  • The NEC4 contract, a collaborative form that originated in the United Kingdom. BCA launched Singapore-specific clauses for construction and engineering projects on 29 April 2024 and for facilities management on 15 August 2025. NEC4 provides an option for a target cost approach.

BCA's January 2026 release reports that the first NEC4 target cost contract has been awarded for infrastructure works by a public agency, allowing project parties to share cost savings or overruns, and that the first NEC4 facilities management contract in Asia has been awarded. As reported by EdgeProp Singapore on 30 April 2026, BCA also described the first private residential project to use NEC4 and named collaborative contracting, lean construction, and robotics, automation and AI as its focus areas.

How does the public sector now evaluate tenders?

Public sector tenders are scored on quality as well as price, and the weight on quality is substantial. The frameworks published by BCA are:

  • Price Quality Method (PQM), for contractors: applies to public construction tenders under the general building and civil engineering workheads with an estimated construction cost of S$3 million and above. Price carries 40% to 60% for building works and 50% to 70% for civil engineering works, with quality making up the balance. An environmental sustainability attribute became mandatory in the version dated 1 November 2024.

  • Quality Fee Method (QFM), for consultants: quality carries 70% to 90% and fees 10% to 30%. The latest version applies to expressions of interest called on or after 1 December 2025.

  • Reduced Fee Score: piloted in March 2024 for consultancy tenders with an estimated construction cost of S$50 million and below, and expanded from December 2025 to S$100 million. BCA reported on 4 March 2026 that 10 of 11 tenders since the launch were awarded to the bids with the highest quality scores.

  • Tender Lite: a category for tenders with an estimated procurement value not exceeding S$1 million, with streamlined conditions, extended to construction in May 2025. The Ministry of Finance reported more than 1,000 Tender Lite tenders published and more than 800 awarded as of 30 June 2025, across all categories.

For consultants, the Government has also made the limitation of liability clause in the Standard Consultancy Agreement mandatory, and in March 2025 it announced a review of the fit for purpose clauses in the public sector design and build conditions.

What are the IDD and DfMA adoption numbers?

Adoption of Integrated Digital Delivery (IDD) and Design for Manufacturing and Assembly (DfMA), measured by gross floor area of new developments, has roughly doubled since 2022. The series is:

  • 2022 baseline at the launch of the transformation map: IDD 34%, DfMA 44%, each with a target of 70% by 2025.

  • 2023: IDD 58%, DfMA about 61% (BCA, 5 March 2025).

  • 2024: IDD 67%, DfMA 68% (BCA, 5 March 2025).

  • 2025: 76% for both, surpassing the 70% target, as reported by EdgeProp Singapore from BCA's remarks at an industry summit on 30 April 2026. We did not find this figure in a BCA release, so treat it as reported.

IDD connects the design, fabrication, construction and asset management stages digitally. DfMA moves work off site, and BCA lists precast concrete systems, mass engineered timber, prefabricated prefinished volumetric construction, prefabricated bathroom units, prefabricated mechanical and electrical systems and structural steel as its technologies. Both push procurement towards earlier contractor and fabricator involvement, because a design cannot be optimised for manufacture without the manufacturer. Regulatory submission is moving the same way: see our CORENET X guide.

What do the productivity statistics show?

BCA's published project productivity indicator for building projects rose from 0.381 sqm per manday in 2010 to 0.455 in 2020, a gain of about 19%, and stood at 0.451 in 2021, the latest year in the table. The indicator is total constructed floor area divided by the total number of site worker mandays.

The gap between building types is wide. In 2021 public housing projects recorded 0.554 sqm per manday, industrial 0.571, institutional 0.404, non-landed residential 0.395, commercial 0.382 and landed residential 0.204. Repetition and prefabrication explain much of the difference.

Measurement is tightening. BCA states that from 1 May 2026 builders of applicable projects must submit construction productivity data through a biometric authentication system. The requirement covers new building, upgrading and addition and alteration projects with a gross floor area of 5,000 sqm or more. On 30 April 2026 BCA also introduced a Kit-of-Parts pathway for standardised prefabricated components, which it expects to lower precast manufacturing costs by at least 10% and manpower needs by at least 20%.

What is happening to tender prices?

BCA's Tender Price Index (2010 = 100) rose from 99.9 in 2019 to 117.1 in 2021 and 130.7 in 2022, and has flattened since: 136.1 in 2023, 137.7 in 2024, 139.1 in 2025 and 140.2 in the first quarter of 2026. Tender prices are therefore about 40% above their 2019 level, on our arithmetic, but rose by only about 1% in 2025. For owners this is the main argument for fixing scope early, whichever procurement model is chosen.

Which authority or law governs what?

  • BCA: construction demand statistics, the public sector contract forms, the PQM and QFM frameworks, and the collaborative contracting pilots.

  • Ministry of Finance: government procurement policy, including Tender Lite.

  • Building and Construction Industry Security of Payment Act 2004: in force since 1 April 2005, with amendments that commenced on 15 December 2019. It gives a statutory right to progress payments and adjudication through the Singapore Mediation Centre.

  • Building Control Act 1989: the appointments and duties that apply under every procurement model. See roles of the QP, builder and developer in design and build.

Common mistakes in reading these numbers

  • Treating construction demand as work done. Demand is contracts awarded; output is the value of work certified. Output in 2025 was about S$41.7 billion against demand of S$50.5 billion.

  • Quoting a design and build "market share" for Singapore. No official figure exists.

  • Assuming the lowest bid wins public work. Quality carries up to 60% for building tenders under PQM and 70% to 90% for consultancy tenders under QFM.

  • Assuming a collaborative contract removes statutory roles. The Qualified Person, the site supervisors and the Accredited Checker are required whatever the form.

  • Reading the medium-term forecast as a fall in activity. BCA's 2027 to 2030 range of S$39 billion to S$46 billion a year is an average, and one-off projects lift individual years.

FAQ

How much construction work is awarded in Singapore each year?

Preliminary demand was S$44.2 billion in 2024 and S$50.5 billion in 2025. BCA forecasts S$47 billion to S$53 billion for 2026.

What share of construction demand is public sector?

About 55% in 2025: S$28.01 billion public against S$22.51 billion private, from BCA's February 2026 table.

What percentage of Singapore projects use design and build?

There is no official statistic. BCA does not publish construction demand by procurement method.

What is the Price Quality Method?

BCA's framework for evaluating public sector construction tenders of S$3 million and above on both price and quality, with price weighted at 40% to 60% for building works.

Is NEC4 used in Singapore?

Yes, on a pilot basis. BCA launched Singapore-specific clauses in April 2024 and reported more than 20 collaborative contracting pilots, across NEC4 and its own option module, in January 2026.

Did Singapore meet its 2025 DfMA and IDD targets?

Adoption reached 67% for IDD and 68% for DfMA in 2024 on BCA's figures, and 76% for both in 2025 as reported in April 2026, against a target of 70%.

Does the Security of Payment Act apply to design and build contracts?

BCA states that a person with a written contract who has carried out construction work or supplied goods or services under it can make a payment claim under the Act, and that contractors, subcontractors, consultants and suppliers benefit from it.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly. See our BCA submission services and professional engineer consultation pages, or WhatsApp +65 9342 7551. Last reviewed: November 2026.