Foundations and Piling for Landed House Rebuilds in Singapore

Nov 12
6 min read

A landed house rebuild in Singapore is founded on shallow footings or a raft where firm soil is near the surface, and on piles (commonly micropiles, jack-in piles or bored piles) where it is not. The choice is made by the structural engineer after a site investigation, which Regulation 31 of the Building Control Regulations requires wherever foundations are proposed, and it is shaped as much by the neighbours and site access as by the soil. This guide sets out the options, the BCA circulars that apply to landed houses, and what changes when you reuse old foundations. It is part of our complete guide to rebuilding a landed house.

What foundation types are used for landed houses?

Most landed rebuilds use one of five foundation types. In plain terms:

  • Pad and strip footings: concrete bases under columns and walls that spread load into firm soil near the surface. Cheapest to build where the ground allows it.

  • Raft: one thick slab under the whole house, used where soil is moderately weak or loads are uneven, and often combined with a basement slab.

  • Micropiles: small-diameter drilled piles, usually grouted with a steel core, installed by compact rigs. BCA's survey guideline groups micro bored piles with non-displacement and small displacement piles.

  • Jack-in piles: precast concrete or steel pipe piles pressed into the ground hydraulically rather than hammered. Closed-ended jacked-in steel pipe piles are displacement piles.

  • Bored piles: larger cast-in-place piles drilled to a competent stratum, used for heavier loads or deep founding levels.

Our article on foundation design and pile types covers each type in more depth.

What decides the choice of foundation?

The soil profile decides first, then loads, neighbours and access. Singapore's geology changes over short distances, from soft marine clay to residual soils of the Jurong Formation or Bukit Timah granite (see our geotechnical engineering guide). The engineer weighs:

  • Depth to a stratum strong enough to carry the house without excessive settlement.

  • Loads: number of storeys, a basement, a swimming pool, roof gardens.

  • Soft clay that will consolidate and drag piles down (negative skin friction).

  • Groundwater level, which affects excavation and raft design.

  • Neighbours: vibration, ground heave from displacement piles, and attached party walls.

  • Access and headroom: narrow side setbacks and low overhead clearance rule out large rigs.

  • Railway protection zones and existing foundations left in the ground.

What does Regulation 31 require, and how many boreholes does a house need?

Regulation 31 requires the QP for structural works to carry out proper and adequate site investigation, in accordance with relevant standards and codes of practice, where foundations, site formation or related earthworks are proposed. BCA's June 2026 ERSS requirements add that the design QP must ensure site investigation works are carried out by an inspection body accredited by the Singapore Accreditation Council, and that the SI report carries PE certification. BCA's circular on requirements for site investigation reports (1 September 2025) sets the content of the report.

BCA does not publish a fixed borehole count for a single house; the QP decides what is adequate. In practice, borehole planning for a house plot considers:

  • Coverage of the footprint, especially near heavily loaded columns and the boundaries next to neighbours.

  • Depth well below the expected pile toe or founding level, to prove the bearing stratum is continuous.

  • Whether boulders or hard layers could stop jack-in or driven piles short.

  • Groundwater observation where a basement is planned.

See soil investigation in Singapore for test methods.

How does BCA's driven or jacked pile circular apply to landed houses?

BCA circular APPBCA-2022-15 (1 September 2022) classifies all landed properties, and all buildings up to 3 storeys, as Type C buildings. Design and construction of driven or jacked piles must comply with Eurocode 7 and BS EN 12699. For Type C:

  • Pile-heave monitoring is optional for an independent Type C building, rising to 50% of working piles where it cannot be demarcated from a Type A or B building.

  • No written confirmation from the Commissioner of Building Control is needed before pile caps start; works above the piles may proceed once the QP has assessed that the piles were installed as designed.

  • An amendment submission is still required where pile length is reduced by more than 20%.

The circular's design guidelines ask the QP to check borehole adequacy, consider negative skin friction, specify termination criteria on plan (for jacked piles: jacked load, holding time and set movement), assess the impact of piling on all buildings within the piling influence zone, specify instrumentation and protective measures such as relief wells or pre-boring, and specify load tests and/or integrity tests on plan. Under the amended Conditions of Permit, the builder must install vibration monitoring devices before any piling starts.

What pile testing applies to a low-rise house?

For a landed house, the QP(ST) decides whether an ultimate pile load test is needed. The GeoSS guideline on local practices for pile foundation design and construction (revision 18 January 2022) states that, for buildings of 10 storeys or more, an instrumented ultimate load test must be carried out as prescribed in joint BCA/IES/ACES/GeoSS circular APPBCA-2016-08 (22 September 2016); "for other cases", the QP(ST) assesses its necessity. The same guideline gives acceptance criteria for working load tests under that circular: 15 mm or 25 mm maximum settlement at the pile top when tested to 1.5 or 2.0 times the characteristic load. Separately, for driven or jacked piles, APPBCA-2022-15 requires load and/or integrity tests to be specified on plan. Our article on pile load and integrity tests explains the test types.

Can you reuse the existing foundations?

Sometimes, and the decision differs between A&A and a rebuild. In additions and alterations, the existing footings or piles usually stay, and the engineer checks they can carry the new loads; URA's lodgment route requires PE certification where non-conforming structures are retained. In a full rebuild, old piles can be reused only if, as the GeoSS guideline puts it, detailed records (pile design, installation, load test and as-built plans) are available and the existing condition can be evaluated by testing, such as static or dynamic load tests, integrity tests and material strength tests. The design must also account for different stiffness between old and new piles in the same group, and demolition must be supervised so the piles survive. Start by buying the approved plans from BCA; without records, reuse is rarely practical. Our A&A versus rebuild article covers the wider choice.

How are neighbours protected during piling?

Through a pre-construction survey, an impact assessment and a pile type chosen for the setting. BCA's guideline APPBCA-2015-03 sets the minimum survey zone for landed piling at 10 m from the site boundary for non-displacement and small displacement piles (such as micro bored piles and steel H-piles) and 20 m for displacement piles (such as RC piles and closed-ended jacked-in steel pipe piles). Displacement piles push soil sideways and upwards, which is why heave monitoring and relief measures appear in the circular. Beside old houses on shallow footings, engineers often prefer non-displacement options. Work hours follow NEA rules: no work from 10 pm Saturday to 7 am Monday for sites within 150 m of homes, unless NEA has issued a permit.

What about restricted access and railway zones?

Tight landed plots often need compact rigs. Micropile and mini bored pile rigs can work in narrow side setbacks and under low headroom, which is why they suit terrace and semi-detached rebuilds; see micropiles and jack-in piles. Near the MRT, LTA's handbook on works in the railway protection zone states that piling is generally not allowed within the 1st reserve, and that piles allowed case by case between 3 m and 6 m from an underground rail structure must not be installed by percussive or displacement methods. See building near MRT lines.

Common mistakes

  • Designing piles from one borehole and finding a boulder layer during installation.

  • Choosing displacement piles beside a fragile attached house.

  • Assuming old piles can be reused without records or testing.

  • Ignoring negative skin friction in reclaimed or soft clay areas.

  • Forgetting that a basement changes the founding level and the excavation approvals.

FAQ

Does every landed house in Singapore need piles?

No. Where firm soil is near the surface and loads are modest, footings or a raft can work; the engineer decides after site investigation.

Are jack-in piles quieter than driven piles?

Jacking presses piles in hydraulically rather than hammering them, so it avoids impact noise, but closed-ended jacked piles still displace soil and need heave assessment.

Is a pile load test compulsory for a house?

The GeoSS guideline makes ultimate load tests mandatory for buildings of 10 storeys or more; for other cases the QP(ST) assesses the need, and jacked or driven piles must have load or integrity tests specified on plan.

Can my contractor reuse the old piles to save time?

Only if records exist and testing confirms their condition and capacity, and the design accounts for mixing old and new piles.

Who signs the foundation design?

A Professional Engineer in the civil or structural discipline, acting as QP for structural works.

Sources

CVC Engineers advocates education and public awareness, and has a dedicated team to help resolve this properly, including foundation design review and BCA submissions for landed rebuilds. WhatsApp +65 9342 7551.

Last reviewed: November 2026.